Description
CERTIFIED ASBESTOS INSPECTORS.
Base award description: CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL.
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-01-30+$314,950= $314,950
- Mod 12012-05-31+$0= $314,950
- Mod 22012-07-18+$200,000= $514,950
- Mod A000012012-12-27+$0= $514,950
- Mod P000032012-12-27+$130,000= $644,950
- Mod P000052012-12-31+$0= $644,950
- Mod P000062013-01-30+$0= $644,950
- Mod P000072013-04-16+$600,400= $1,245,350
- Mod P000082013-12-26+$0= $1,245,350
- Mod P000102014-02-14+$23,295= $1,268,645
- Mod P000112014-02-27+$47,065= $1,315,710
- Mod P000092014-03-24+$7,313= $1,323,023
- Mod P000122014-04-01+$53,640= $1,376,663
- Mod P000132016-06-03-$41,525= $1,335,138
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-01-30 | +$314,950 | $314,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-31 | +$0 | $314,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. EXTEND PERFORMANCE PERIOD TO 12/31/2012. |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-18 | +$200,000 | $514,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. ADDED FUNDING. |
| Mod A00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-27 | +$0 | $514,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. ADD 52.232-99 AND CHANGE PAYMENT FROM NET 30 TO NET 14… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-27 | +$130,000 | $644,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. ADDED FUNDING. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-31 | +$0 | $644,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. EXTENDED PERFORMANCE PERIOD |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-30 | +$0 | $644,950 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. EXTEND PERFORMANCE PERIOD TO 12/31/2013. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-16 | +$600,400 | $1,245,350 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. EXTEND PERFORMANCE PERIOD TO 12/31/2013. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-26 | +$0 | $1,245,350 | CERTIFIED ASBESTOS BUILDING INSPECTION OF SOIL REMOVAL. EXTEND PERFORMANCE PERIOD TO 2/14/2014. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-14 | +$23,295 | $1,268,645 | CERTIFIED ASBESTOS INSPECTOR FOR SOIL EXCAVATION. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-27 | +$47,065 | $1,315,710 | CERTIFIED ASBESTOS INSPECTOR FOR SOIL EXCAVATION |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-24 | +$7,313 | $1,323,023 | CERTIFIED ASBESTOS INSPECTOR FOR SOIL EXCAVATION. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-01 | +$53,640 | $1,376,663 | CERTIFIED ASBESTOS INSPECTORS FOR SOIL EXCAVATION. |
| Mod P00013· CLOSE OUT | 2016-06-03 | −$41,525 | $1,335,138 | CERTIFIED ASBESTOS INSPECTORS. |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI RDL1MPNQ4MA7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25914P4940 | 259-NETWORK CONTRACT OFFICE 19 · B510 · SPECIAL STUDIES/ANALYSIS- ENVIRONMENTAL ASSESSMENTS | $1,380 | FY2014 |
| VA101F14C0019 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · F108 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL REMEDIATION | $839,470 | FY2014 |
| VA25912C0300 | 259-NETWORK CONTRACT OFFICE 19 · Z1NC · MAINTENANCE OF POLLUTION ABATEMENT AND CONTROL FACILITIES | $13,125 | FY2012 |
| VA25912P0382 | 259-NETWORK CONTRACT OFFICE 19 · F108 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL REMEDIATION | $6,300 | FY2012 |
| VA259C1064 | 442-CHEYENNE · Y199 · CONSTRUCT/MISC BLDGS | $75,900 | FY2011 |
Other recipients under F115 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101F17J2848 | LRS MD JV LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $251,284 | FY2017 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F12P0045_3600_-NONE-_-NONE- · retrieved 2026-09-26.