Description
LONG BEACH DEMO BUILDING 8 DESIGN, THIS MODIFICATION DEOBLIGATES THE FINAL RESIDUAL FUNDS FROM THIS PROJECT.
Base award description: LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II.
Modification chain · 38 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-04-30+$694,012= $694,012
- Mod P000022013-01-16+$37,623= $731,635
- Mod P000032013-04-24+$12,788= $744,423
- Mod P000042013-05-20+$58,345= $802,768
- Mod P000012013-06-17+$872,824= $1,675,592
- Mod P000052013-06-18+$11,971= $1,687,563
- Mod P000062013-06-28+$58,345= $1,745,908
- Mod P000072014-07-23+$99,858= $1,845,765
- Mod P000082014-07-23+$44,532= $1,890,297
- Mod P000092014-07-23+$76,527= $1,966,824
- Mod P000102014-08-01+$62,039= $2,028,863
- Mod P000112014-08-05+$23,434= $2,052,297
- Mod P000122014-08-21+$14,142= $2,066,439
- Mod P000132014-09-23+$8,208= $2,074,646
- Mod P000142014-10-22+$18,411= $2,093,058
- Mod P000152015-01-15+$17,380= $2,110,438
- Mod P000162015-01-29+$70,560= $2,180,998
- Mod P000172015-01-29+$96,730= $2,277,728
- Mod P000182015-09-16+$12,629= $2,290,358
- Mod P000192015-12-21+$127,224= $2,417,582
- Mod P000202016-03-08+$3,016= $2,420,597
- Mod P000212016-10-26+$2,523= $2,423,121
- Mod P000222016-12-29+$662= $2,423,782
- Mod P000232017-01-12+$18,899= $2,442,681
- Mod P000262017-07-12+$32,202= $2,474,883
- Mod P000252017-08-15+$20,705= $2,495,588
- Mod P000272017-09-18-$11,487= $2,484,101
- Mod P000282017-10-12+$5,572= $2,489,673
- Mod P000292019-03-15+$16,246= $2,505,919
- Mod P000302019-05-03+$15,000= $2,520,919
- Mod P000322019-09-25+$1,071,178= $3,592,097
- Mod P000312020-02-05+$129,144= $3,721,241
- Mod P000332020-04-15+$15,000= $3,736,241
- Mod P000342020-07-21+$7,353= $3,743,593
- Mod P000352020-08-28-$156,285= $3,587,309
- Mod P000362021-02-23+$0= $3,587,309
- Mod P000372022-03-09+$98,556= $3,685,865
- Mod P000382022-03-25-$30,033= $3,655,832
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-04-30 | +$694,012 | $694,012 | LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-16 | +$37,623 | $731,635 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II, BLDG 126OP SECOND FLOOR REDESIGN. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-24 | +$12,788 | $744,423 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II SD-2 PEER REVIEW PRESENTATION FOR VACO CSS… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-20 | +$58,345 | $802,768 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, BUILDING 8 DEMOLITION PRE-DESIGN. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-17 | +$872,824 | $1,675,592 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II. EXERCISE THE PRE-PRICED AND APPROVED CD… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-18 | +$11,971 | $1,687,563 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, PHASE II. EVALUATION OF HVAC EFFECT ON DESIGN. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-28 | +$58,345 | $1,745,908 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, BUILDING 8 DEMOLITION PRE-DESIGN. STRUCTURAL STUDY… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-23 | +$99,858 | $1,845,765 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, BUILDING 8 DEMOLITION PRE-DESIGN. STRUCTURAL STUDY… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-23 | +$44,532 | $1,890,297 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, BUILDING 8 DEMOLITION PRE-DESIGN. STRUCTURAL STUDY… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-23 | +$76,527 | $1,966,824 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, BUILDING 8 DEMOLITION PRE-DESIGN. STRUCTURAL STUDY… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-01 | +$62,039 | $2,028,863 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, B126 RENOVATE ENTRYWAY, CORRIDORS AND ELEVATOR LOBB… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-05 | +$23,434 | $2,052,297 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, INSTALL FOUR BARIATRIC LIFTS IN B126 AND 126OP. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-21 | +$14,142 | $2,066,439 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PROJECT 600-402B, RENOVATE THE OPTOMETRY CLINIC IN ACCORDANCE WITH PA… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-23 | +$8,208 | $2,074,646 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, DD1 PEER REVIEW PRINTING COSTS. |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-22 | +$18,411 | $2,093,058 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, DD1 VACO TRIP FOR 5 CONTRACTOR PERSONNEL. |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-15 | +$17,380 | $2,110,438 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, ELECTRICAL METERING. |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-29 | +$70,560 | $2,180,998 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, DIGITAL SECURITY DESIGN SERVICES. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-29 | +$96,730 | $2,277,728 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, DIGITAL IT DESIGN. |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-16 | +$12,629 | $2,290,358 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, SD-1 REVIEW PRINTING |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-21 | +$127,224 | $2,417,582 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, PROJECT 600-402B, ADDITIONAL CONSTRUCTION PHASING |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-08 | +$3,016 | $2,420,597 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD PRINTING AWARD PROJECT 600-402B |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-26 | +$2,523 | $2,423,121 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD2 PRINTING AWARD PROJECT 600-402B |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-29 | +$662 | $2,423,782 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL CD2 PRINTING AND DISTRIBUTION AWARD PROJECT 600-… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-01-12 | +$18,899 | $2,442,681 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL CD2 PRINTING AND DISTRIBUTION AWARD PROJECT 600-… |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-12 | +$32,202 | $2,474,883 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD2 PRINTING AWARD PROJECT 600-402B |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-15 | +$20,705 | $2,495,588 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD2 PRINTING AWARD PROJECT 600-402B |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-09-18 | −$11,487 | $2,484,101 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD2 PRINTING AWARD PROJECT 600-402B |
| Mod P00028· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-10-12 | +$5,572 | $2,489,673 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, CD2 PRINTING AWARD PROJECT 600-402B |
| Mod P00029· CHANGE ORDER | 2019-03-15 | +$16,246 | $2,505,919 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL DESIGN SERVICES FOR INSTALLATION OF AUDIOLOGY BO… |
| Mod P00030· CHANGE ORDER | 2019-05-03 | +$15,000 | $2,520,919 | IGF::OT::IGF LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL FUNDS FOR ADDED DESIGN SERVICES FOR INSTALLATION… |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-09-25 | +$1,071,178 | $3,592,097 | LONG BEACH SEISMIC DESIGN, PHASE II, BUILDING 8 DEMOLITION DESIGN THROUGH CD'S. |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-02-05 | +$129,144 | $3,721,241 | LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL FUNDS FOR ADDED DESIGN SERVICES FOR INSTALLATION OF AUDIOLOGY… |
| Mod P00033· CHANGE ORDER | 2020-04-15 | +$15,000 | $3,736,241 | LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL FUNDS FOR ADDED DESIGN SERVICES FOR INSTALLATION OF AUDIOLOGY… |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-07-21 | +$7,353 | $3,743,593 | LONG BEACH SEISMIC DESIGN, PHASE II, ADDITIONAL FUNDS FOR ADDED DESIGN SERVICES/SITE VISITS FOR COMMISSIONING… |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-28 | −$156,285 | $3,587,309 | LONG BEACH DEMO BUILDING 8 DESIGN, CHANGE TO DESIGN BUILD BRIDGING DOCUMENTS DESIGN |
| Mod P00036· OTHER ADMINISTRATIVE ACTION | 2021-02-23 | +$0 | $3,587,309 | LONG BEACH DEMO BUILDING 8 DESIGN, CHANGE TO DESIGN BUILD BRIDGING DOCUMENTS DESIGN EXTENSION OF OBLIGATION EN… |
| Mod P00037· OTHER ADMINISTRATIVE ACTION | 2022-03-09 | +$98,556 | $3,685,865 | CLOSEOUT FOR TASK ORDERS VA101F-12-J-0002 AND VA101F-12-J-0004, PER BUDGET ANALYST AUDIT OF ACCOUNTS. |
| Mod P00038· OTHER ADMINISTRATIVE ACTION | 2022-03-25 | −$30,033 | $3,655,832 | LONG BEACH DEMO BUILDING 8 DESIGN, THIS MODIFICATION DEOBLIGATES THE FINAL RESIDUAL FUNDS FROM THIS PROJECT. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI K3ZVY8RLBSJ8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F24C0011 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $611,175 | FY2024 |
| 36C10F20C0012 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $6,484,310 | FY2020 |
| VA26216J7764 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $295,104 | FY2016 |
| VA26216J7279 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $10,000 | FY2016 |
| VA101F16J2658 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $163,546 | FY2016 |
| VA26216J3151 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $960,070 | FY2016 |
Other recipients under C215 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F25C50004 | ABOVE GROUP INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,083,926 | FY2025 |
| 36C10F24C50028 | BLUE TRIDENT, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,689,012 | FY2024 |
| 36C10F20N0089 | FFE ENVIRONMENTAL SERVICES INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,258,508 | FY2020 |
| 36C10F20N0062 | ALESIA ARCHITECTURE PC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $695,134 | FY2020 |
| 36C10F20N0020 | ALESIA ARCHITECTURE PC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $206,560 | FY2020 |