Description
DEOBLIGATION OF DESIGN DEVELOPMENT AS REQUIREMENT IS REMOVED FROM SCOPE.
Base award description: SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY)
Modification chain · 71 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-09-30+$6,142,243= $6,142,243
- Mod SA0012010-12-22+$64,530= $6,206,773
- Mod SA0022011-02-23+$15,512= $6,222,285
- Mod SA0032011-04-04+$13,156= $6,235,441
- Mod SA0042011-06-27+$48,702= $6,284,143
- Mod SA0052011-09-30+$0= $6,284,143
- Mod SA0062011-09-30+$37,142= $6,321,286
- Mod SA0072011-09-30+$77,944= $6,399,230
- Mod SA0092011-09-30+$368,722= $6,767,952
- Mod SA0082011-11-28+$0= $6,767,952
- Mod SA0102011-12-05+$266,935= $7,034,887
- Mod SA0122012-01-09+$8,439= $7,043,326
- Mod SA0132012-01-31+$31,626= $7,074,952
- Mod P000022012-05-18+$5,387= $7,080,339
- Mod SA0112012-06-22-$26,445= $7,053,894
- Mod P000032012-07-13+$388,223= $7,442,117
- Mod P000042012-07-19+$8,558= $7,450,675
- Mod P000052012-07-26+$38,992= $7,489,667
- Mod P000062012-08-24+$2,538= $7,492,205
- Mod P000072012-11-19+$35,120= $7,527,325
- Mod P000082013-01-10+$417,723= $7,945,048
- Mod P000092013-01-16+$37,255= $7,982,303
- Mod P000102013-07-22+$12,197= $7,994,499
- Mod P000112013-09-30+$877,382= $8,871,881
- Mod P000122014-01-14+$97,742= $8,969,623
- Mod P000132014-01-14+$70,343= $9,039,966
- Mod P000152014-01-31+$552,786= $9,592,752
- Mod P000162014-02-26+$80,596= $9,673,348
- Mod P000172014-02-26+$4,911= $9,678,259
- Mod P000182014-03-19+$12,846= $9,691,105
- Mod P000192014-06-24+$1,003,676= $10,694,781
- Mod P000202014-08-14+$80,547= $10,775,328
- Mod P000212014-09-05+$98,724= $10,874,052
- Mod P000222014-09-16+$11,829= $10,885,882
- Mod P000142014-09-30+$3,899,308= $14,785,189
- Mod P000232014-10-22+$9,727= $14,794,916
- Mod P000252015-01-26+$733,104= $15,528,020
- Mod P000242015-02-04+$60,154= $15,588,174
- Mod P000262015-06-18+$62,636= $15,650,810
- Mod P000272015-09-15+$86,366= $15,737,176
- Mod P000282015-12-14+$30,783= $15,767,958
- Mod P000302016-09-02-$5,323= $15,762,635
- Mod P000292016-09-21+$37,606= $15,800,241
- Mod P000312017-10-17+$410,713= $16,210,954
- Mod P000322017-11-06+$577,742= $16,788,696
- Mod P000332018-01-16+$981,894= $17,770,590
- Mod P000342018-04-13+$2,396,584= $20,167,174
- Mod P000352018-04-18+$270,576= $20,437,751
- Mod P000362018-04-20+$392,385= $20,830,136
- Mod P000372018-05-02+$766,259= $21,596,395
- Mod P000382018-05-11+$0= $21,596,395
- Mod P000392018-09-26+$0= $21,596,395
- Mod P000402018-10-30+$400,580= $21,996,974
- Mod P000422019-05-07+$11,026= $22,008,001
- Mod P000432019-08-03+$529,770= $22,537,771
- Mod P000412019-08-08+$1,794,215= $24,331,986
- Mod P00452020-07-16+$0= $24,331,986
- Mod P000462020-12-14+$529,770= $24,861,756
- Mod P000472021-10-01+$0= $24,861,756
- Mod P000492022-02-22+$1,734,981= $26,596,737
- Mod P000512022-06-10+$30,156= $26,626,894
- Mod P000502022-06-17+$7,390= $26,634,284
- Mod P000532022-09-16-$7,390= $26,626,894
- Mod P000542022-09-16+$7,390= $26,634,284
- Mod P000552022-12-27+$65,004= $26,699,288
- Mod P000522023-05-01+$2,675= $26,701,963
- Mod P000562023-05-26-$505,113= $26,196,850
- Mod P000582023-08-28-$1,573,314= $24,623,536
- Mod P000572024-06-13+$0= $24,623,536
- Mod P000602024-10-25+$0= $24,623,536
- Mod P000592025-09-30-$813,482= $23,810,053
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-09-30 | +$6,142,243 | $6,142,243 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-22 | +$64,530 | $6,206,773 | GOVERNMENT TO UNILATERALLY EXERCISE FIRM FIXED PRICED OPTION ITEM NO. 6, LEED CERTIFICATION - BLDG. 209 (SD AN… |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-23 | +$15,512 | $6,222,285 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) CONTRACTOR SHALL… |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-04 | +$13,156 | $6,235,441 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) CONTRACTOR SHALL… |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-27 | +$48,702 | $6,284,143 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) CONTRACTOR SHALL… |
| Mod SA005· OTHER ADMINISTRATIVE ACTION | 2011-09-30 | +$0 | $6,284,143 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) ADMINISTRATIVE CH… |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-30 | +$37,142 | $6,321,286 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) ADDITIONAL TIME I… |
| Mod SA007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-30 | +$77,944 | $6,399,230 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) AE TO PROVIDE ADD… |
| Mod SA009· EXERCISE AN OPTION | 2011-09-30 | +$368,722 | $6,767,952 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) THIS IS TO EXERCI… |
| Mod SA008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-28 | +$0 | $6,767,952 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 (SD AND DD ONLY) SA-008 IS TO ADD… |
| Mod SA010· EXERCISE AN OPTION | 2011-12-05 | +$266,935 | $7,034,887 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 THIS IS TO EXERCISE OPTION FOR LIN… |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-09 | +$8,439 | $7,043,326 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 THIS IS TO PROVIDE ADDITIONAL TOPO… |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-31 | +$31,626 | $7,074,952 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 THIS IS TO PROVIDE ADDITIONAL TOPO… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-18 | +$5,387 | $7,080,339 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. PUBLICATION OF NEPA FINDING OF NO… |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-22 | −$26,445 | $7,053,894 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209 THIS IS TO ADJUST THE DESIGN FEE F… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-13 | +$388,223 | $7,442,117 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. PUBLICATION OF NEPA FINDING OF NO… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-19 | +$8,558 | $7,450,675 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. PUBLICATION OF NEPA FINDING OF NO… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$38,992 | $7,489,667 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. PUBLICATION OF NEPA FINDING OF NO… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-24 | +$2,538 | $7,492,205 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. B209 CONSTRUCTION PRE-PROPOSAL CO… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-19 | +$35,120 | $7,527,325 | SEISMIC AND FCA CORRECTIONS OF 10 BUILDINGS AND RENOVATION OF BUILDING 209. B209 CONSTRUCTION PRE-PROPOSAL CO… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-10 | +$417,723 | $7,945,048 | B209 CONSTRUCTION PERIOD SERVICES, INCLUDING LEED CERTIFICATION FOR RENOVATION |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-16 | +$37,255 | $7,982,303 | TO ADD THIRD PARTY IH SERVICES |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-22 | +$12,197 | $7,994,499 | B209 ADDITIONAL DESIGN SERVICES INCLUDING ICEMAKER, LEED CERTIFICATION ADDED HOURS, ASBESTOS ABATEMENT OVERSIG… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-30 | +$877,382 | $8,871,881 | IDIQAE TO PROVIDE AE SERVICES FOR SCHEMATIC DESIGN (SD) 2 FOR BLDGS 205 AND 208, VA WEST LOS ANGELES MEDICAL C… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-14 | +$97,742 | $8,969,623 | IDIQAE TO MODIFICATION TO PROVIDE ADDITIONAL COMMISSIONING SERVICES NOT COVERED BY LEED COMMISSIONING FOR BLDG… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-14 | +$70,343 | $9,039,966 | IDIQAE TO TO PROVIDE ADDITIONAL CONSTRUCTION PERIOD SERVICES FOR BLDG 209, VA WEST LOS ANGELES MEDICAL CENTER,… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-31 | +$552,786 | $9,592,752 | FIFTY ADDITIONAL SITE VISITS DURING CONSTRUCTION PERIOD SERVICES FOR BUILDING 209. |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-26 | +$80,596 | $9,673,348 | B209 CPS 50 ADDITIONAL SITE VISITS. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-26 | +$4,911 | $9,678,259 | B209 CPS 50 ADDITIONAL SITE VISITS. |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-19 | +$12,846 | $9,691,105 | B205 AND B208 SD2 ADDITIONAL PRINTING COSTS AND GBCI FEES. |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-24 | +$1,003,676 | $10,694,781 | B205 AND B208 SD2 DD DESIGN SERVICES. |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-14 | +$80,547 | $10,775,328 | B205 AND B208 SD2 DD DESIGN SERVICES, TO TAKE ADDITIONAL CONCRETE SAMPLES. |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-05 | +$98,724 | $10,874,052 | B205 AND B208 ELECTRICAL STUDY AND METERING SERVICES. |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-16 | +$11,829 | $10,885,882 | B205 AND B208 DD1 PEER REVIEW PRINTING AND DISTRIBUTION SERVICES. |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-30 | +$3,899,308 | $14,785,189 | IDIQAE TO PROVIDE AE SERVICES FOR SEISMIC AND FCA CORRECTIONS FOR BLDGS 156, 157 AND 258 AND DISPOSITION REPOR… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-22 | +$9,727 | $14,794,916 | B205 AND B208 SD2 DD DESIGN SERVICES, TO TAKE ADDITIONAL CONCRETE SAMPLES AFTER HOURS. |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-26 | +$733,104 | $15,528,020 | B205 AND B208 CD DESIGN AWARD. |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-04 | +$60,154 | $15,588,174 | B205 AND B208 VARIOUS ADDITIONAL AE SERVICES. ELECTRICAL METERING, STORM DRAIN SYSTEM SURVEY, ADDITIONAL TOPOG… |
| Mod P00026· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2015-06-18 | +$62,636 | $15,650,810 | B205 AND B208 CD DESIGN AWARD. |
| Mod P00027· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2015-09-15 | +$86,366 | $15,737,176 | B205 AND B208 CD DESIGN AWARD. |
| Mod P00028· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2015-12-14 | +$30,783 | $15,767,958 | B205 AND B208 CD DESIGN AWARD. |
| Mod P00030· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2016-09-02 | −$5,323 | $15,762,635 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00029· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2016-09-21 | +$37,606 | $15,800,241 | B205 AND B208 CD DESIGN AWARD. |
| Mod P00031· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-10-17 | +$410,713 | $16,210,954 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00032· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-11-06 | +$577,742 | $16,788,696 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00033· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-01-16 | +$981,894 | $17,770,590 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00034· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-04-13 | +$2,396,584 | $20,167,174 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00035· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-04-18 | +$270,576 | $20,437,751 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00036· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-04-20 | +$392,385 | $20,830,136 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00037· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-05-02 | +$766,259 | $21,596,395 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00038· OTHER ADMINISTRATIVE ACTION | 2018-05-11 | +$0 | $21,596,395 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00039· FUNDING ONLY ACTION | 2018-09-26 | +$0 | $21,596,395 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00040· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-10-30 | +$400,580 | $21,996,974 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00042· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2019-05-07 | +$11,026 | $22,008,001 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00043· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2019-08-03 | +$529,770 | $22,537,771 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00041· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2019-08-08 | +$1,794,215 | $24,331,986 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P0045· OTHER ADMINISTRATIVE ACTION | 2020-07-16 | +$0 | $24,331,986 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00046· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2020-12-14 | +$529,770 | $24,861,756 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00047· OTHER ADMINISTRATIVE ACTION | 2021-10-01 | +$0 | $24,861,756 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00049· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-02-22 | +$1,734,981 | $26,596,737 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00051· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-06-10 | +$30,156 | $26,626,894 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00050· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-06-17 | +$7,390 | $26,634,284 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00053· OTHER ADMINISTRATIVE ACTION | 2022-09-16 | −$7,390 | $26,626,894 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00054· OTHER ADMINISTRATIVE ACTION | 2022-09-16 | +$7,390 | $26,634,284 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00055· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-12-27 | +$65,004 | $26,699,288 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00052· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-05-01 | +$2,675 | $26,701,963 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00056· CHANGE ORDER | 2023-05-26 | −$505,113 | $26,196,850 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00058· OTHER ADMINISTRATIVE ACTION | 2023-08-28 | −$1,573,314 | $24,623,536 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00057· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2024-06-13 | +$0 | $24,623,536 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00060· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2024-10-25 | +$0 | $24,623,536 | B205 AND B208 CD DESIGN AWARD. DEOBLIGATION OF EXCESS FUNDS. |
| Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-30 | −$813,482 | $23,810,053 | DEOBLIGATION OF DESIGN DEVELOPMENT AS REQUIREMENT IS REMOVED FROM SCOPE. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI K3ZVY8RLBSJ8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F24C0011 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $611,175 | FY2024 |
| 36C10F20C0012 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $6,484,310 | FY2020 |
| VA26216J7764 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $295,104 | FY2016 |
| VA26216J7279 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $10,000 | FY2016 |
| VA101F16J2658 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $163,546 | FY2016 |
| VA26216J3151 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $960,070 | FY2016 |
Other recipients under C215 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F25C50004 | ABOVE GROUP INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,083,926 | FY2025 |
| 36C10F24C50028 | BLUE TRIDENT, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,689,012 | FY2024 |
| 36C10F20N0089 | FFE ENVIRONMENTAL SERVICES INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,258,508 | FY2020 |
| 36C10F20N0062 | ALESIA ARCHITECTURE PC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $695,134 | FY2020 |
| 36C10F20N0020 | ALESIA ARCHITECTURE PC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $206,560 | FY2020 |