Description
EXTENSION FOR CPS SERVICES TO MARCH 31, 2026.
Base award description: AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. SEISMIC SCI AND CLC.
Modification chain · 50 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-08-31+$4,597,485= $4,597,485
- Mod SA0012010-03-26+$13,421= $4,610,906
- Mod 22010-05-03+$16,737= $4,627,643
- Mod SA0032010-06-29+$64,205= $4,691,848
- Mod SA0042010-10-04+$90,197= $4,782,045
- Mod SA0052010-11-30+$39,399= $4,821,444
- Mod SA0062010-12-09+$35,000= $4,856,444
- Mod SA0072011-02-08+$19,000= $4,875,444
- Mod SA0082012-01-31+$97,000= $4,972,444
- Mod P000012013-06-11+$6,762= $4,979,206
- Mod P000022014-05-02+$1,800= $4,981,006
- Mod P000032014-09-30+$5,000,000= $9,981,006
- Mod P000042015-02-25+$26,928= $10,007,934
- Mod P000052015-04-02+$16,500= $10,024,434
- Mod P000062015-04-03+$600,000= $10,624,434
- Mod P000072015-04-15+$200,000= $10,824,434
- Mod P000082015-04-24+$0= $10,824,434
- Mod P000092015-05-07+$700,000= $11,524,434
- Mod P000102015-06-25+$320,000= $11,844,434
- Mod P000112015-10-26+$200,000= $12,044,434
- Mod P000122016-09-30+$99,869= $12,144,303
- Mod P000132017-08-25+$213,254= $12,357,557
- Mod A000022018-03-20+$86,228= $12,443,785
- Mod P000142018-05-01+$0= $12,443,785
- Mod P000152018-11-29+$137,434= $12,581,219
- Mod P000162019-06-05+$90,000= $12,671,219
- Mod P000172019-08-15+$0= $12,671,219
- Mod P000182021-03-12+$169,099= $12,840,318
- Mod P000192021-04-06+$70,000= $12,910,318
- Mod P000202021-04-21+$200,200= $13,110,518
- Mod P000212021-06-22+$250,000= $13,360,518
- Mod P000222021-08-19+$75,103= $13,435,621
- Mod P000232021-08-27+$150,000= $13,585,621
- Mod P000242021-09-15+$4,405,024= $17,990,645
- Mod P000252021-09-30+$0= $17,990,645
- Mod A000042022-06-30-$277,823= $17,712,822
- Mod A000032022-08-15+$130,981= $17,843,803
- Mod P000262022-10-24+$0= $17,843,803
- Mod A000052023-05-01+$36,654= $17,880,457
- Mod A000062023-07-28+$15,500= $17,895,957
- Mod A000072023-07-28+$68,454= $17,964,411
- Mod A000082024-04-26+$500,000= $18,464,411
- Mod A000102024-07-18+$725,045= $19,189,456
- Mod A000112025-01-07+$1,019,207= $20,208,663
- Mod P000272025-06-05+$0= $20,208,663
- Mod A000122025-08-22+$282,299= $20,490,962
- Mod A000132025-09-15+$158,448= $20,649,410
- Mod A000142025-11-28+$79,224= $20,728,634
- Mod A000152026-04-16+$0= $20,728,634
- Mod A000162026-04-16+$0= $20,728,634
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-08-31 | +$4,597,485 | $4,597,485 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. SEISMIC SCI AND CLC. |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-26 | +$13,421 | $4,610,906 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-03 | +$16,737 | $4,627,643 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. SA# 2 EMERGENCY POWER AND CHILLER STUDY |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-29 | +$64,205 | $4,691,848 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-04 | +$90,197 | $4,782,045 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. SA# 2 EMERGENCY POWER AND CHILLER STUDY |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-30 | +$39,399 | $4,821,444 | TO HAVE THE A/E PROVIDE A BLAST CONSULTANT. |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-09 | +$35,000 | $4,856,444 | TO HAVE THE A/E PROVIDE A SPECIALTY LIGHTING CONSULTANT. |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-08 | +$19,000 | $4,875,444 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-31 | +$97,000 | $4,972,444 | TO HAVE AND A/E STUDY THE DESIGN IMPACT OF ADDING 5 BEDS TO THE LONG TERM SCI |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-11 | +$6,762 | $4,979,206 | AE CONTRACT FOR DESIGN SERVICES AT VAMC SAN DIEGO, CA. SEISMIC SCI AND CLC. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-05-02 | +$1,800 | $4,981,006 | TO HAVE AND A/E STUDY THE DESIGN IMPACT OF ADDING 5 BEDS TO THE LONG TERM SCI |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-30 | +$5,000,000 | $9,981,006 | IGF:OT::IGF CHANGE ORDER FOR AE TO DESIGN VA SAN DIEGO MEDICAL CENTER NEW SPINAL CORD INJURY (SCI), COMMUNITY… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$26,928 | $10,007,934 | TO HAVE THE A/E ADD COMMISSIONING SERVICES TO THE SOW |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-02 | +$16,500 | $10,024,434 | TO HAVE THE A/E ADD ATS ELECTRICAL TESTING SERVICES TO THE SOW |
| Mod P00006· CHANGE ORDER | 2015-04-03 | +$600,000 | $10,624,434 | IGF:OT::IGF CHANGE ORDER FOR AE TO DESIGN VA SAN DIEGO MEDICAL CENTER NEW SPINAL CORD INJURY (SCI), COMMUNITY… |
| Mod P00007· CHANGE ORDER | 2015-04-15 | +$200,000 | $10,824,434 | IGF:OT::IGF CHANGE ORDER FOR AE TO DESIGN VA SAN DIEGO MEDICAL CENTER NEW SPINAL CORD INJURY (SCI), COMMUNITY… |
| Mod P00008· CHANGE ORDER | 2015-04-24 | +$0 | $10,824,434 | IGF:OT::IGF CHANGE ORDER FOR AE TO DESIGN VA SAN DIEGO MEDICAL CENTER NEW SPINAL CORD INJURY (SCI), COMMUNITY… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-07 | +$700,000 | $11,524,434 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-25 | +$320,000 | $11,844,434 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-26 | +$200,000 | $12,044,434 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-30 | +$99,869 | $12,144,303 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-25 | +$213,254 | $12,357,557 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00002· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2018-03-20 | +$86,228 | $12,443,785 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00014· OTHER ADMINISTRATIVE ACTION | 2018-05-01 | +$0 | $12,443,785 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-29 | +$137,434 | $12,581,219 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00016· CHANGE ORDER | 2019-06-05 | +$90,000 | $12,671,219 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00017· CHANGE ORDER | 2019-08-15 | +$0 | $12,671,219 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00018· DEFINITIZE CHANGE ORDER | 2021-03-12 | +$169,099 | $12,840,318 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00019· CHANGE ORDER | 2021-04-06 | +$70,000 | $12,910,318 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00020· CHANGE ORDER | 2021-04-21 | +$200,200 | $13,110,518 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00021· CHANGE ORDER | 2021-06-22 | +$250,000 | $13,360,518 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00022· DEFINITIZE CHANGE ORDER | 2021-08-19 | +$75,103 | $13,435,621 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00023· CHANGE ORDER | 2021-08-27 | +$150,000 | $13,585,621 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00024· DEFINITIZE CHANGE ORDER | 2021-09-15 | +$4,405,024 | $17,990,645 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00025· ADD SUBCONTRACTING PLAN | 2021-09-30 | +$0 | $17,990,645 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00004· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-06-30 | −$277,823 | $17,712,822 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00003· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-08-15 | +$130,981 | $17,843,803 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00026· DEFINITIZE CHANGE ORDER | 2022-10-24 | +$0 | $17,843,803 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00005· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-05-01 | +$36,654 | $17,880,457 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00006· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-07-28 | +$15,500 | $17,895,957 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00007· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-07-28 | +$68,454 | $17,964,411 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00008· CHANGE ORDER | 2024-04-26 | +$500,000 | $18,464,411 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod A00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-18 | +$725,045 | $19,189,456 | TO DEFINITIZE NTE MOD A00008. |
| Mod A00011· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2025-01-07 | +$1,019,207 | $20,208,663 | TO HAVE AND A/E PROVIDE A POOL CONSULTANT. |
| Mod P00027· OTHER ADMINISTRATIVE ACTION | 2025-06-05 | +$0 | $20,208,663 | TO CORRECT EVERYTHING THAT WAS OUTLAID IN FY25 AND DE-OBLIGATE ALL INCORRECT FUNDING IN A UDO STATUS |
| Mod A00012· CHANGE ORDER | 2025-08-22 | +$282,299 | $20,490,962 | EXTENSION FOR CPS SERVICES. |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-15 | +$158,448 | $20,649,410 | EXTENSION FOR CPS SERVICES TO NOVEMBER 30, 2025. |
| Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-11-28 | +$79,224 | $20,728,634 | EXTENSION FOR CPS SERVICES TO DECEMBER 31, 2025. |
| Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-16 | +$0 | $20,728,634 | EXTENSION FOR CPS SERVICES TO MARCH 31, 2026. |
| Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-16 | +$0 | $20,728,634 | EXTENSION FOR CPS SERVICES TO MARCH 31, 2026. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI VMA9KU45CDZ3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26216J0131 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $0 | FY2016 |
| VA26216P0107 | 258-NETWORK CNTRCT OFF 22G (36C258) · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $0 | FY2016 |
| VA26216P0121 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $70,000 | FY2016 |
| VA26216P0013 | 262-NETWORK CONTRACT OFFICE 22 · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $77,267 | FY2016 |
| VA26216P0014 | 262-NETWORK CONTRACT OFFICE 22 · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $43,138 | FY2016 |
| VA26213J1526 | 262-NETWORK CONTRACT OFFICE 22 · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $129,893 | FY2013 |
Other recipients under C114 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VATODEC05 | LEO A. DALY LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | -$1,261 | FY2018 |
| VATOJUL07 | LEO A. DALY LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | -$188,468 | FY2016 |
| VA101CFMP0148 | CANNON DESIGN, INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,571 | FY2011 |
| VACFM05C0095 | E B A ERNEST BLAND ASSOCIATES, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $53,624 | FY2011 |
| V101BP0249 | N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $0 | FY2011 |