Description
MODIFICATION FOR BOND PREMIUM ADJUSTMENT IN ACCORDANCE WITH VAAR 852.228-70 BOND PREMIUM ADJUSTMENT.
Base award description: OR
Modification chain · 170 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-24+$19,611,000= $19,611,000
- Mod SA0022009-11-30+$40,293= $19,651,293
- Mod SA0032009-12-02+$41,004= $19,692,297
- Mod SA0042010-01-28+$70,708= $19,763,004
- Mod CO01A2010-02-17+$38,335= $19,801,339
- Mod SA0012010-02-17+$23,046= $19,824,385
- Mod SA0052010-03-10+$13,409= $19,837,794
- Mod CO01B2010-03-12+$60,000= $19,897,794
- Mod SA0062010-03-17+$90,753= $19,988,547
- Mod TE0012010-04-20+$0= $19,988,547
- Mod CO01C2010-04-22+$60,000= $20,048,547
- Mod SA0072010-04-27-$10,766= $20,037,781
- Mod TE0022010-05-18+$0= $20,037,781
- Mod TE0032010-05-18+$0= $20,037,781
- Mod CO01D2010-05-28+$50,000= $20,087,781
- Mod TE0042010-06-24+$0= $20,087,781
- Mod TE0052010-07-16+$0= $20,087,781
- Mod SA0082010-07-27+$5,231= $20,093,012
- Mod SA0092010-08-19+$3,776= $20,096,788
- Mod SA0102010-08-25+$0= $20,096,788
- Mod SA0112010-09-17+$0= $20,096,788
- Mod CO01E2010-10-07+$35,000= $20,131,788
- Mod SA0122010-10-08+$21,424= $20,153,212
- Mod SA0132010-12-01+$0= $20,153,212
- Mod CO01F2010-12-09+$40,000= $20,193,212
- Mod SA0142010-12-16+$9,066= $20,202,278
- Mod CO01G2010-12-17+$15,000= $20,217,278
- Mod TE0062011-01-05+$0= $20,217,278
- Mod TE0072011-01-05+$0= $20,217,278
- Mod SA0162011-01-24+$10,576= $20,227,854
- Mod SA0172011-01-25+$11,315= $20,239,169
- Mod SA0182011-01-26+$3,353= $20,242,522
- Mod SA0152011-01-27+$80,581= $20,323,103
- Mod SA0192011-01-31+$10,938= $20,334,042
- Mod CO01H2011-02-07+$10,000= $20,344,042
- Mod SA0202011-02-25+$5,673= $20,349,714
- Mod SA0212011-02-25+$1,725= $20,351,439
- Mod SA0222011-02-28+$39,899= $20,391,338
- Mod CO01I2011-03-07+$30,000= $20,421,338
- Mod SA0252011-04-06+$1,011= $20,422,349
- Mod SA0262011-04-29+$6,576= $20,428,925
- Mod SA0272011-04-29+$581= $20,429,505
- Mod SA0282011-04-29-$6,781= $20,422,724
- Mod SA0292011-05-04+$8,102= $20,430,826
- Mod SA0302011-05-06-$32,879= $20,397,947
- Mod SA0312011-05-06-$1,976= $20,395,971
- Mod SA0342011-06-30+$3,365= $20,399,336
- Mod SA0352011-06-30+$19,780= $20,419,115
- Mod SA0362011-06-30+$4,282= $20,423,397
- Mod SA0372011-06-30+$5,093= $20,428,490
- Mod SA0382011-06-30+$4,259= $20,432,749
- Mod SA0392011-06-30+$1,081= $20,433,831
- Mod CO01K2011-08-05+$10,000= $20,443,831
- Mod CO01L2011-08-05+$20,000= $20,463,831
- Mod CO01J2011-08-15+$867,500= $21,331,331
- Mod SA0322011-08-29-$27,557= $21,303,774
- Mod SA0402011-08-29+$2,760= $21,306,535
- Mod SA0412011-08-29+$29,329= $21,335,864
- Mod SA0422011-08-29+$4,899= $21,340,763
- Mod SA0432011-08-29+$34,092= $21,374,855
- Mod SA0442011-08-29+$15,139= $21,389,994
- Mod SA0452011-08-29+$2,310= $21,392,304
- Mod SA0462011-08-29+$3,122= $21,395,426
- Mod SA0472011-08-29+$1,732= $21,397,158
- Mod SA0482011-08-29+$9,205= $21,406,363
- Mod SA0492011-08-30+$3,092= $21,409,455
- Mod SA0502011-08-30+$2,922= $21,412,377
- Mod SA0512011-08-30+$6,882= $21,419,260
- Mod SA0522011-09-21-$8,006= $21,411,253
- Mod SA0532011-09-21+$12,491= $21,423,744
- Mod SA0542011-09-21+$4,328= $21,428,073
- Mod SA0552011-09-21+$1,316= $21,429,389
- Mod SA0562011-09-21+$2,128= $21,431,517
- Mod SA0572011-09-21-$6,215= $21,425,301
- Mod SA0232011-09-22+$28,384= $21,453,686
- Mod SA0242011-09-22+$59,039= $21,512,725
- Mod SA0332011-09-22+$147,800= $21,660,525
- Mod TE0082011-09-22+$0= $21,660,525
- Mod SA0582011-10-05+$2,316= $21,662,841
- Mod SA0592011-10-28+$2,471= $21,665,312
- Mod SA0602011-10-28+$3,325= $21,668,636
- Mod SA0612011-10-28+$2,817= $21,671,454
- Mod SA0622011-11-07+$6,640= $21,678,093
- Mod SA0632011-11-07+$1,008= $21,679,101
- Mod CO01M2011-11-17+$60,000= $21,739,101
- Mod SA0652011-12-09-$8,649= $21,730,451
- Mod SA0662011-12-09+$1,527= $21,731,978
- Mod SA0672011-12-09+$1,356= $21,733,334
- Mod SA0682011-12-12-$913= $21,732,421
- Mod SA0692011-12-12+$551= $21,732,972
- Mod SA0702011-12-12+$41,810= $21,774,782
- Mod TE0092011-12-12+$0= $21,774,782
- Mod TE0102011-12-13+$0= $21,774,782
- Mod CO01N2011-12-19+$6,000= $21,780,782
- Mod SA0712011-12-19+$5,172= $21,785,954
- Mod SA0722012-01-09+$17,917= $21,803,871
- Mod SA0732012-01-09+$10,623= $21,814,495
- Mod SA0742012-01-09+$7,923= $21,822,418
- Mod SA0772012-01-26+$4,831= $21,827,249
- Mod SA0782012-01-26+$5,356= $21,832,605
- Mod SA0762012-01-30-$2,148= $21,830,458
- Mod TE0112012-02-02+$0= $21,830,458
- Mod CO01O2012-02-03+$16,000= $21,846,458
- Mod CO01P2012-02-07+$3,500= $21,849,958
- Mod CO01Q2012-02-07+$12,000= $21,861,958
- Mod SA0642012-02-22+$313,954= $22,175,912
- Mod SA0752012-02-23+$12,237= $22,188,149
- Mod SA0792012-03-23+$4,272= $22,192,420
- Mod SA0802012-04-26+$836= $22,193,256
- Mod SA0812012-04-26+$8,324= $22,201,580
- Mod SA0822012-04-26-$4,737= $22,196,843
- Mod SA0832012-04-26-$999= $22,195,844
- Mod SA0842012-07-11+$40,153= $22,235,997
- Mod SA0852012-07-20+$4,655= $22,240,652
- Mod SA0862012-08-08-$9,309= $22,231,343
- Mod SA0872012-08-16+$4,655= $22,235,997
- Mod SA0882012-10-23+$11,643= $22,247,640
- Mod SA0892012-10-23+$6,507= $22,254,147
- Mod SA0902012-10-23+$1,246= $22,255,393
- Mod SA0912012-10-23+$4,180= $22,259,573
- Mod SA0922012-10-23+$12,367= $22,271,940
- Mod SA0932012-10-23+$14,158= $22,286,098
- Mod P000012012-11-07+$55,534= $22,341,632
- Mod P000022012-11-07+$15,738= $22,357,370
- Mod P000032012-11-07+$1,739= $22,359,109
- Mod P000042012-11-07+$597= $22,359,707
- Mod P000052012-11-07+$11,430= $22,371,137
- Mod P000062012-11-28+$8,444= $22,379,580
- Mod P000072012-12-03+$11,128= $22,390,708
- Mod P000082012-12-03-$886= $22,389,822
- Mod P000092012-12-17+$465= $22,390,287
- Mod P000102012-12-17+$9,331= $22,399,618
- Mod P000122013-02-14+$354= $22,399,973
- Mod P000132013-02-14+$5,375= $22,405,348
- Mod P000142013-02-14+$3,003= $22,408,351
- Mod P000152013-02-14+$2,366= $22,410,717
- Mod P000162013-02-20+$4,590= $22,415,306
- Mod P000172013-03-22-$10,519= $22,404,787
- Mod P000192013-03-22+$4,848= $22,409,635
- Mod P000202013-03-22+$2,198= $22,411,834
- Mod P000212013-03-22+$9,591= $22,421,424
- Mod P000222013-03-22+$3,842= $22,425,266
- Mod P000182013-03-25+$1,076= $22,426,342
- Mod P000232013-03-29+$2,695= $22,429,037
- Mod P000242013-04-04+$3,768= $22,432,805
- Mod P000262013-04-26+$6,325= $22,439,130
- Mod P000252013-05-09+$33,310= $22,472,440
- Mod P000272013-05-09+$7,433= $22,479,873
- Mod P000282013-07-23+$458= $22,480,331
- Mod P000292013-07-23+$5,554= $22,485,884
- Mod P000302013-07-23-$304= $22,485,581
- Mod P000312013-07-31+$2,593= $22,488,174
- Mod P000322013-07-31-$1,122= $22,487,052
- Mod P000332013-07-31+$716= $22,487,768
- Mod P000342013-09-18+$480= $22,488,248
- Mod P000352013-09-18+$2,499= $22,490,747
- Mod P000362013-09-18+$497= $22,491,244
- Mod P000372013-09-18+$23,815= $22,515,059
- Mod P000382013-09-18+$15,015= $22,530,074
- Mod P000392013-09-27-$1,698= $22,528,376
- Mod P000402013-09-27+$8,742= $22,537,118
- Mod P000412013-10-29+$4,320= $22,541,437
- Mod P000422013-10-29+$1,052= $22,542,489
- Mod P000432013-10-29+$724= $22,543,213
- Mod P000442013-10-29+$1,629= $22,544,842
- Mod P000452013-10-29+$1,171= $22,546,013
- Mod P000462013-10-29+$644= $22,546,657
- Mod P000112013-11-05+$400,000= $22,946,657
- Mod P000472013-11-18-$6,983= $22,939,675
- Mod P000482013-12-20+$5,744= $22,945,419
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-24 | +$19,611,000 | $19,611,000 | OR |
| Mod SA002· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-30 | +$40,293 | $19,651,293 | VAPOR AND ALKALINITY SEALER FOR SLABS |
| Mod SA003· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-02 | +$41,004 | $19,692,297 | STORM SEWER CHANGES BETWEEN MH#2 AND MH#5 |
| Mod SA004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-28 | +$70,708 | $19,763,004 | BUILDING SANITARY SEWER CHANGES |
| Mod CO01A· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-02-17 | +$38,335 | $19,801,339 | EMERGENCY EXTERIOR STAIRS |
| Mod SA001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-02-17 | +$23,046 | $19,824,385 | CHANGE STORM SEWER |
| Mod SA005· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-10 | +$13,409 | $19,837,794 | RELOCATE ELECTRICAL SERVICE TO WAREHOUSE |
| Mod CO01B· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-12 | +$60,000 | $19,897,794 | ADDITIONAL ROCK REMOVAL, DRILLING PIERS |
| Mod SA006· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-17 | +$90,753 | $19,988,547 | ELECTRICAL FEEDER CHANGE |
| Mod TE001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-20 | +$0 | $19,988,547 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod CO01C· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-22 | +$60,000 | $20,048,547 | HVAC CHANGE |
| Mod SA007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-27 | −$10,766 | $20,037,781 | STORM AND SANITARY SEWER CHANGES NE CORNER |
| Mod TE002· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-18 | +$0 | $20,037,781 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod TE003· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-18 | +$0 | $20,037,781 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod CO01D· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-28 | +$50,000 | $20,087,781 | ADDITIONAL ROCK REMOVAL, SITE SEWERS |
| Mod TE004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-24 | +$0 | $20,087,781 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod TE005· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-16 | +$0 | $20,087,781 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod SA008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-27 | +$5,231 | $20,093,012 | ASBESTOS ABATEMENT, LAB B-025 |
| Mod SA009· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-19 | +$3,776 | $20,096,788 | STEEL SUPPORT CHANNELS |
| Mod SA010· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-25 | +$0 | $20,096,788 | OFFSITE ELECTRICAL STORAGE |
| Mod SA011· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-09-17 | +$0 | $20,096,788 | EMERGINCY EXTERIOR STAIRS |
| Mod CO01E· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-10-07 | +$35,000 | $20,131,788 | SECURITY HARDWARE |
| Mod SA012· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-10-08 | +$21,424 | $20,153,212 | SSD MODIFICATIONS |
| Mod SA013· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-12-01 | +$0 | $20,153,212 | EMERGENCY EXTERIOR STAIRS |
| Mod CO01F· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-12-09 | +$40,000 | $20,193,212 | CMU BOND BEAMS AND SUPPORT ANGLES |
| Mod SA014· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-12-16 | +$9,066 | $20,202,278 | CMU BOND BEAMS AND SUPPORT ANGLES |
| Mod CO01G· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-12-17 | +$15,000 | $20,217,278 | NEW ENDOVASCULAR OR SUITE |
| Mod TE006· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-05 | +$0 | $20,217,278 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod TE007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-05 | +$0 | $20,217,278 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod SA016· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-24 | +$10,576 | $20,227,854 | OR SUITE NURSE CALL SYSTEM |
| Mod SA017· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-25 | +$11,315 | $20,239,169 | DOOR HARDWARE CHANGES |
| Mod SA018· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-26 | +$3,353 | $20,242,522 | STUD FRAMING CHANGES FOR ELECTRICAL PANEL |
| Mod SA015· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-27 | +$80,581 | $20,323,103 | ADDITIONAL ROCK REMOVAL, SITE SEWERS |
| Mod SA019· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-31 | +$10,938 | $20,334,042 | ROOF OVERFLOW DRAIN REROUT |
| Mod CO01H· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-02-07 | +$10,000 | $20,344,042 | CYSTO PREP ROOM CHANGES |
| Mod SA020· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-02-25 | +$5,673 | $20,349,714 | RADIATOR DEMO |
| Mod SA021· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-02-25 | +$1,725 | $20,351,439 | RECUT LIMESTONE |
| Mod SA022· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-02-28 | +$39,899 | $20,391,338 | ADDITIONAL ROCK REMOVAL |
| Mod CO01I· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-07 | +$30,000 | $20,421,338 | CARDIAC OR G-102 CHANGES |
| Mod SA025· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-04-06 | +$1,011 | $20,422,349 | CONTRACT MODIFICATION |
| Mod SA026· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-04-29 | +$6,576 | $20,428,925 | CONTRACT MODIFICATION |
| Mod SA027· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-04-29 | +$581 | $20,429,505 | CONTRACT MODIFICATION |
| Mod SA028· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-04-29 | −$6,781 | $20,422,724 | CONTRACT MODIFICATION |
| Mod SA029· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-04 | +$8,102 | $20,430,826 | CONTRACT MODIFICATION |
| Mod SA030· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-06 | −$32,879 | $20,397,947 | CONTRACT MODIFICATION |
| Mod SA031· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-06 | −$1,976 | $20,395,971 | CONTRACT MODIFICATION |
| Mod SA034· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$3,365 | $20,399,336 | CONTRACT MODIFICATION |
| Mod SA035· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$19,780 | $20,419,115 | CONTRACT MODIFICATION |
| Mod SA036· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$4,282 | $20,423,397 | CONTRACT MODIFICATION |
| Mod SA037· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$5,093 | $20,428,490 | CONTRACT MODIFICATION |
| Mod SA038· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$4,259 | $20,432,749 | CONTRACT MODIFICATION |
| Mod SA039· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-30 | +$1,081 | $20,433,831 | CONTRACT MODIFICATION |
| Mod CO01K· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-05 | +$10,000 | $20,443,831 | CHANGE ORDER |
| Mod CO01L· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-05 | +$20,000 | $20,463,831 | CHANGE ORDER |
| Mod CO01J· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$867,500 | $21,331,331 | ENDOVASCULAR SUITE |
| Mod SA032· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | −$27,557 | $21,303,774 | CONTRACT MODIFICATION |
| Mod SA040· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$2,760 | $21,306,535 | CONTRACT MODIFICATION |
| Mod SA041· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$29,329 | $21,335,864 | CONTRACT MODIFICATION |
| Mod SA042· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$4,899 | $21,340,763 | CONTRACT MODIFICATION |
| Mod SA043· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$34,092 | $21,374,855 | CONTRACT MODIFICATION |
| Mod SA044· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$15,139 | $21,389,994 | CONTRACT MODIFICATION |
| Mod SA045· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$2,310 | $21,392,304 | CONTRACT MODIFICATION |
| Mod SA046· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$3,122 | $21,395,426 | CONTRACT MODIFICATION |
| Mod SA047· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$1,732 | $21,397,158 | CONTRACT MODIFICATION |
| Mod SA048· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-29 | +$9,205 | $21,406,363 | CONTRACT MODIFICATION |
| Mod SA049· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-30 | +$3,092 | $21,409,455 | CONTRACT MODIFICATION |
| Mod SA050· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-30 | +$2,922 | $21,412,377 | CONTRACT MODIFICATION |
| Mod SA051· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-30 | +$6,882 | $21,419,260 | CONTRACT MODIFICATION |
| Mod SA052· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | −$8,006 | $21,411,253 | CONTRACT MODIFICATION |
| Mod SA053· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | +$12,491 | $21,423,744 | CONTRACT MODIFICATION |
| Mod SA054· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | +$4,328 | $21,428,073 | CONTRACT MODIFICATION |
| Mod SA055· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | +$1,316 | $21,429,389 | CONTRACT MODIFICATION |
| Mod SA056· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | +$2,128 | $21,431,517 | CONTRACT MODIFICATION |
| Mod SA057· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-21 | −$6,215 | $21,425,301 | CONTRACT MODIFICATION |
| Mod SA023· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-22 | +$28,384 | $21,453,686 | ADDITIONAL ROCK REMOVAL |
| Mod SA024· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-22 | +$59,039 | $21,512,725 | ADDITIONAL ROCK REMOVAL |
| Mod SA033· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-22 | +$147,800 | $21,660,525 | CONTRACT MODIFICATION |
| Mod TE008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-22 | +$0 | $21,660,525 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod SA058· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-10-05 | +$2,316 | $21,662,841 | CONTRACT MODIFICATION |
| Mod SA059· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-10-28 | +$2,471 | $21,665,312 | CONTRACT MODIFICATION |
| Mod SA060· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-10-28 | +$3,325 | $21,668,636 | CONTRACT MODIFICATION |
| Mod SA061· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-10-28 | +$2,817 | $21,671,454 | CONTRACT MODIFICATION |
| Mod SA062· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-07 | +$6,640 | $21,678,093 | CONTRACT MODIFICATION |
| Mod SA063· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-07 | +$1,008 | $21,679,101 | CONTRACT MODIFICATION |
| Mod CO01M· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-17 | +$60,000 | $21,739,101 | CHANGE ORDER |
| Mod SA065· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-09 | −$8,649 | $21,730,451 | CONTRACT MODIFICATION |
| Mod SA066· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-09 | +$1,527 | $21,731,978 | CONTRACT MODIFICATION |
| Mod SA067· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-09 | +$1,356 | $21,733,334 | CONTRACT MODIFICATION |
| Mod SA068· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-12 | −$913 | $21,732,421 | CONTRACT MODIFICATION |
| Mod SA069· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-12 | +$551 | $21,732,972 | CONTRACT MODIFICATION |
| Mod SA070· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-12 | +$41,810 | $21,774,782 | CONTRACT MODIFICATION |
| Mod TE009· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-12 | +$0 | $21,774,782 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod TE010· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-13 | +$0 | $21,774,782 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod CO01N· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-19 | +$6,000 | $21,780,782 | CHANGE ORDER |
| Mod SA071· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-12-19 | +$5,172 | $21,785,954 | CONTRACT MODIFICATION |
| Mod SA072· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-09 | +$17,917 | $21,803,871 | CONTRACT MODIFICATION |
| Mod SA073· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-09 | +$10,623 | $21,814,495 | CONTRACT MODIFICATION |
| Mod SA074· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-09 | +$7,923 | $21,822,418 | CONTRACT MODIFICATION |
| Mod SA077· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-26 | +$4,831 | $21,827,249 | CONTRACT MODIFICATION |
| Mod SA078· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-26 | +$5,356 | $21,832,605 | CONTRACT MODIFICATION |
| Mod SA076· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-30 | −$2,148 | $21,830,458 | CONTRACT MODIFICATION |
| Mod TE011· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-02 | +$0 | $21,830,458 | CONTRACT EXTENSION DUE TO WEATHER |
| Mod CO01O· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-03 | +$16,000 | $21,846,458 | CHANGE ORDER |
| Mod CO01P· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-07 | +$3,500 | $21,849,958 | CHANGE ORDER |
| Mod CO01Q· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-07 | +$12,000 | $21,861,958 | CHANGE ORDER |
| Mod SA064· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-22 | +$313,954 | $22,175,912 | CONTRACT MODIFICATION |
| Mod SA075· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-02-23 | +$12,237 | $22,188,149 | CONTRACT MODIFICATION |
| Mod SA079· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-23 | +$4,272 | $22,192,420 | CONTRACT MODIFICATION |
| Mod SA080· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-04-26 | +$836 | $22,193,256 | CONTRACT MODIFICATION |
| Mod SA081· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-04-26 | +$8,324 | $22,201,580 | CONTRACT MODIFICATION |
| Mod SA082· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-04-26 | −$4,737 | $22,196,843 | CONTRACT MODIFICATION |
| Mod SA083· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-04-26 | −$999 | $22,195,844 | CONTRACT MODIFICATION |
| Mod SA084· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-07-11 | +$40,153 | $22,235,997 | DEMOLITION OF ALL PLASTER WALLS ENCOUNTERED IN LIEU OF GYP. BOARD WALLS. THIS INCLUDES THE CERAMIC WALL TILE,… |
| Mod SA085· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-07-20 | +$4,655 | $22,240,652 | REMOVE AND LEGALLY DISPOSE OF LEAD SHIELDING FOUND IN WALLS DURING FIRST FLOOR DEMOLITION. |
| Mod SA086· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-08-08 | −$9,309 | $22,231,343 | REMOVE LEAD SHIELDING FOUND IN WALLS DURING FIRST FLOOR DEMOLITION. |
| Mod SA087· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-08-16 | +$4,655 | $22,235,997 | REMOVE AND LEGALLY DISPOSE OF LEAD SHIELDING FOUND IN WALLS DURING FIRST FLOOR DEMOLITION. -HAZARDOUS WASTE. |
| Mod SA088· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$11,643 | $22,247,640 | TO REDUCE HEAT BUILD-UP IN ENDO CLOSET CONTAINING PHILLIPS EQUIPMENT. INSTALL RETURN DUCT GRILLE, CAP OFF SUP… |
| Mod SA089· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$6,507 | $22,254,147 | TO DEMOLISH AND DISPOSE OF EXISTING BLOCK CHASE AND ADDITIONAL TILE FLOORING NOT SHOWN ON DRAWINGS. |
| Mod SA090· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$1,246 | $22,255,393 | TO INFILL THE CHASE AT THE CEILING ON THE FIRST FLOOR OF PHASE 2 IN THE SOUTHWEST CORNER OF COLUMN LINE 7R AND… |
| Mod SA091· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$4,180 | $22,259,573 | TO SET UP AND REMOVE SCAFFOLDING IN AREAWAY FOR WORK THAT COULD NOT BE COMPLETED IN PHASE 1. |
| Mod SA092· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$12,367 | $22,271,940 | TO RELOCATE THE EXISTING HVAC HOT WATER EXPANSION LOOP FROM THE PROCEDURE ROOM CEILING TO CORRIDOR C103 CEILIN… |
| Mod SA093· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-10-23 | +$14,158 | $22,286,098 | TO RELOCATE SIX (6) SANITARY WASTE AND VENT PIPES AND ONE (1) COLD WATER LINE AT COLUMN LINE Q/6 THAT WAS FOUN… |
| Mod P00001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-07 | +$55,534 | $22,341,632 | TO PROVIDE MAJOR FLOOR PREPARATION ON THE EXISTING CONCRETE FLOOR SLAB IN PHASE 2 FIRST FLOOR, TO INCLUDE: MEC… |
| Mod P00002· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-07 | +$15,738 | $22,357,370 | TO MODIFY THE CONSTRUCTION OF THE FROZEN SECTION ROOM C111 FOR COORDINATION OF STRYKER AND OWNER FURNISHED EQU… |
| Mod P00003· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-07 | +$1,739 | $22,359,109 | TO CHANGE WALL TYPES TO ACCOMMODATE ELECTRICAL ROUGH-INS AS WELL AS TO PROVIDE ACCEPTABLE WALL FINISHES, PER R… |
| Mod P00004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-07 | +$597 | $22,359,707 | TO INSTALL ONE (1) NEW OXYGEN SHUT OFF VALVE TO EXISTING COPPER OXYGEN PIPING IN BASEMENT MECHANICAL ROOM. |
| Mod P00005· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-07 | +$11,430 | $22,371,137 | TO MODIFY THE EXISTING MEDICAL GAS ALARM PANEL IN OR/PACU TO SLAVE IN A NEW MEDICAL GAS MASTER ALARM PANEL INT… |
| Mod P00006· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-11-28 | +$8,444 | $22,379,580 | THIS SA-099 IS TO ADD 4 ROWS OF STRIP LIGHTING IN CENTER COVE SOFFIT OVER NURSE STATION AND TO ADD STRIP LIGHT… |
| Mod P00007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-12-03 | +$11,128 | $22,390,708 | MODIFY DRAWINGS IN PROCEDURE ROOM TO ADD WALL RECESS FOR STRYKER EQUIPMENT. |
| Mod P00008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-12-03 | −$886 | $22,389,822 | DELETE DOOR FRAME WALL AT CORRIDOR C102. |
| Mod P00009· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-12-17 | +$465 | $22,390,287 | STRYKER EQUIPMENT COORDINATION CHANGES TO OFFICES C110, C109, C106 AND C107. |
| Mod P00010· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-12-17 | +$9,331 | $22,399,618 | TO ADD MEDICAL GAS LINES TO BOOM 'E1' AND BOOM 'G1' IN PROCEDURE ROOM C192 AND MEDICAL GAS LINE TO SOUTH WALL… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-14 | +$354 | $22,399,973 | TO ADD A 16"X16" CEILING ACCESS PANEL WEST OF BOOM E1 IN THE PROCEDURE ROOM FOR ACCESS TO MEDICAL GAS CONNECTI… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-14 | +$5,375 | $22,405,348 | TO ADD SUPPORT STEEL PLATES, STEEL BEAMS AND ANCHORS AT RED IRON SUPPORTS FOR FOUR BOOMS IN PROCEDURE ROOM C19… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-14 | +$3,003 | $22,408,351 | TO INFILL AND PREPARE THE FLOOR SLAB TO RECEIVE RESILIENT RUBBER FLOORING IN THE AREA OF COLUMN LINE 8R. |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-14 | +$2,366 | $22,410,717 | TO INFILL AND PREPARE THE FLOOR SLAB TO RECEIVE RESILIENT RUBBER FLOORING IN THE AREA OF COLUMN LINE 8R. |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-20 | +$4,590 | $22,415,306 | TO PROVIDE A 3RD SECTION OF ELECTRICAL PANELBOARD TO LP1-M9-120VC PANELBOARD. THE THIRD SECTION SHOULD BE A… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-22 | −$10,519 | $22,404,787 | NEW PVC PIPING INSTALLED BY VAMC UNDER SEPARATE CONTRACT TO RERMAIN IN PLACE. OMIT NEW CAST IRON PIPING IN CO… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-22 | +$4,848 | $22,409,635 | TO REPLACE THE PIPE HANGERS AND SUPPORT RODS NOT IN COMPLIANCE WITH VA SPEC'S. THAT WERE UNCOVERED DURING ASBE… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-22 | +$2,198 | $22,411,834 | TO CHANGE THE STUD FRAMING IN HEADWALLS TO COORDINATE WITH MED GAS AND ELECTRICAL ROUGH-IN FOR HILL-ROM EQUIPM… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-22 | +$9,591 | $22,421,424 | TO DEMOLISH AND DISPOSE OF CERAMIC TILE AND PLASTER WALLS IN THE PHASE 2A AREA, IN LIEU OF DRYWALL AND METAL S… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-22 | +$3,842 | $22,425,266 | TO REMOVE AND DISPOSE OF 2ND (ADDITIONAL) LAYER OF FLOORING IN PHASE 2A AREA, IN LIEU OF ONE LAYER OF FLOORING… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-25 | +$1,076 | $22,426,342 | TO PATCH AND /OR FILL-IN HOLES UNCOVERED DURING DEMOLITION ON WEST AND NORTH WALLS OF CONSTRUCTION AREA TO MAK… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-29 | +$2,695 | $22,429,037 | TO REMOVE AND DISPOSE OF COPPER GROUNDING STRIPS ON THE CONCRETE SLAB AND PREP FLOOR SLAB. |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-04 | +$3,768 | $22,432,805 | TO ADD 7 - 1'X4' TYPE "N" LIGHT FIXTURE IN WAITING ROOM C178, NOT LABELED ON ES-104 DRAWING. |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-26 | +$6,325 | $22,439,130 | TO ADD TEL/DATA DROPS, A J-BOX FOR FUTURE PUSH PLATE, RELOCATE J-BOX ABOVE DOOR, RELOCATE ONE EXIT LIGHT AND A… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-09 | +$33,310 | $22,472,440 | TO PROVIDE A COMPRESSED SPD WORK SCHEDULE FOR DEMO AND NEW WORK ABOVE CEILING. RCC AND THEIR SUBS TO COMPLETE… |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-09 | +$7,433 | $22,479,873 | TO MODIFY AND RELOCATE THE EXISTING SPRINKLER SYSTEM BRANCH LINES ON FIRST FLOOR AS REQURIED TO MISS MECHANICA… |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-23 | +$458 | $22,480,331 | TO REPLACE PIPING INSULATION AND NON-COMPLIANT PIPING HANGERS (PER SPECIFICATION REQUIREMENTS) AFTER COMPLETIO… |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-23 | +$5,554 | $22,485,884 | TO DEMOLISH AND DISPOSE OF PLASTER/CMU WALLS AND ASSOCIATED METAL LATH ENCOUNTERED ON FIRST FLOOR OF PHASE 3 I… |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-23 | −$304 | $22,485,581 | TO PROVIDE A CREDIT FOR DELETING THE CONCRETE (ONLY) INFILL (APPROXIMATELY 35SF) AT THE 2ND FLOOR MECHANICAL R… |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-31 | +$2,593 | $22,488,174 | TO DEMOLISH/REMOVE FROM THE SITE ADDITIONAL CASEWORK, WINDOWS, PLUMBING FIXTURES AND PIPING NOT SHOWN ON DEMOL… |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-31 | −$1,122 | $22,487,052 | TO FURNISH A CREDIT FOR DELETING WALL DEMOLITION AND REPLACEMENT ALONG EXISTING CORRIDOR C1C9 BETWEEN COLUMN L… |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-31 | +$716 | $22,487,768 | TO DEMOLISH/REMOVE FROM SITE ADDITIONAL COLD/HOT WATER LINES, NATURAL GAS LINE, AND VACUUM LINE DISCOVERED IN… |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-18 | +$480 | $22,488,248 | TO INFILL UNFORESEEN RECESSED FLOOR SLAB AT COLUMN LA/7 (NOT SHOWN ON DRAWINGS) DISCOVERED DURING PHAES 3 DEMO… |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-18 | +$2,499 | $22,490,747 | TO REROUTE DOMESTIC HOT/COLD WATER LINES CONNECTIONS ABOVE THE KITCHEN STOREROOM AREA TO THE EXISTING WATER LI… |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-18 | +$497 | $22,491,244 | TO FREEZE EXISTING WATER LINE UNCOVERED DURING DEMOLITION WORKS (NOT SHOWN ON DRAWINGS) ON WEST SIDE OF COLUMN… |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-18 | +$23,815 | $22,515,059 | TO CONDUCT THE MAJOR FLOOR PREPARATION/GRINDING/PATCHING REQUIRED ON THE EXISTING CONCRETE FLOOR SLAB ON THE F… |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-18 | +$15,015 | $22,530,074 | TO MODIFY INSTRUMENT PROCESSING ROOM C185 PER ATTACHED DRAWINGS, AND TO ADD A UTILITY SINK TO SOILED UTILITY R… |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-27 | −$1,698 | $22,528,376 | TO FURNISH A CREDIT FOR REMOVAL OF EXISTING PIPING AND INSTALLATION OF NEW CAST IRON PIPING IAW DRAWINGS FOR P… |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-27 | +$8,742 | $22,537,118 | TO PROVIDE POWER (NOT SHOWN ON DRAWINGS) TO DOORS C176, C178, C179, C186, AND C190 IN PHASE 3 PER THE FOLLOWIN… |
| Mod P00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$4,320 | $22,541,437 | TO MODIFY/RELOCATE EXISTING SPRINKLER SYSTEM BRANCH LINES ON THE FIRST FLOOR OF PHASE 3 AS REQUIRED TO MISS ME… |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$1,052 | $22,542,489 | TO REPLACE PIPE INSULATION/HANGERS AFTER ABATEMENT PROCEDURES IN PHASE 3. PIPE INSULATION AT HANGERS TO BE BL… |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$724 | $22,543,213 | TO REPLACE PIPE INSULATION ON EXISTING UNINSULATED PIPES UNCOVERED DURING DEMOLITION WORKS IN PHASE 3 AREA, IN… |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$1,629 | $22,544,842 | TO RELOCATE WALL PHONE #81 AND NURSE CALL #84 TO THE EAST SIDE OF THE DOOR IN INSTRUMENT PROCESSING ROOM C185,… |
| Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$1,171 | $22,546,013 | TO RE-ROUTE THE CONDENSATE DRAIN LINE IN ROOM C112 OF PHASE 2 THROUGH THE ADJACENT DUCT CHASE AND INTO THE SUB… |
| Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-29 | +$644 | $22,546,657 | TO PROVIDE TWO (2) ADDITIONAL FAUCETS FOR DOUBLE INTEGRAL STAINLESS STEEL SINK IN ROOM C185, IN ACCORDANCE WIT… |
| Mod P00011· OTHER ADMINISTRATIVE ACTION | 2013-11-05 | +$400,000 | $22,946,657 | MODIFICATION IS FOR 105 DAYS OF SITE SPECIFIC DIRECT COST OVERHEAD. |
| Mod P00047· OTHER ADMINISTRATIVE ACTION | 2013-11-18 | −$6,983 | $22,939,675 | MODIFICATION TO DELETE ALL WORK ASSOCIATED WITH DEMOLITION/NEW INSTALLATIONS FOR HVAC DUCTWORK IN EXISTING CYS… |
| Mod P00048· OTHER ADMINISTRATIVE ACTION | 2013-12-20 | +$5,744 | $22,945,419 | MODIFICATION FOR BOND PREMIUM ADJUSTMENT IN ACCORDANCE WITH VAAR 852.228-70 BOND PREMIUM ADJUSTMENT. |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0167 | THE R.E.M. ENGINEERING CO INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $384,303 | FY2011 |
| VA101CFMC0130 | TTL ASSOCIATES INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $101,742 | FY2011 |
| VA101CFMC0111 | WALSH CONSTRUCTION PUERTO RICO | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $52,457,646 | FY2010 |
| VA101CFMC0085 | ARCHER WESTERN/DEMARIA JOINT VENTURE III | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $58,427,947 | FY2010 |
| VACFM05I0064 | N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $114,946 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0257_3600_-NONE-_-NONE- · retrieved 2026-09-26.