Description
TO ADJUST THE CONTRACTOR'S BOND PREMIUM BECAUSE OF THE MODIFICATIONS ISSUED TO THE CONTRACT DURING CONSTRUCTION.
Base award description: UTIL
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-04-24+$0= $0
- Mod SA0012010-01-25+$0= $0
- Mod SA0022010-01-25+$25,947= $25,947
- Mod SA0032010-01-25+$49,970= $75,917
- Mod SA0042010-04-16+$2,780= $78,697
- Mod SA0052010-08-30+$65,680= $144,377
- Mod SA0062011-05-03-$13,930= $130,447
- Mod SA0072011-05-03+$19,310= $149,757
- Mod SA0082011-05-03+$46,409= $196,166
- Mod SA0092011-05-03+$3,738= $199,904
- Mod SA0102011-05-03+$10,596= $210,500
- Mod SA0112011-05-03+$14,749= $225,249
- Mod TE0012011-05-03+$0= $225,249
- Mod SA0122011-06-29+$21,708= $246,957
- Mod SA0132011-11-16+$587= $247,544
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-04-24 | +$0 | $0 | UTIL |
| Mod SA001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-25 | +$0 | $0 | WORK AT OXYGEN PAD |
| Mod SA002· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-25 | +$25,947 | $25,947 | CHILLEED WATER CONNECTION BLDG 5 |
| Mod SA003· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-25 | +$49,970 | $75,917 | ADDITIONAL BORING/DELETIONOF OXYGEN PIPING |
| Mod SA004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-16 | +$2,780 | $78,697 | REMOVE TREES |
| Mod SA005· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-30 | +$65,680 | $144,377 | SECTIONALIZING CABINETS |
| Mod SA006· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | −$13,930 | $130,447 | DELETE RELOCATION OF DUCT BANK TO TRANSFORMER 64. RELOCATION NO LONGER NECCESSARY DUE TO STATION PROGRAM CHANG… |
| Mod SA007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$19,310 | $149,757 | THE NORMAL FEEDERS FEEDING ATS CS WERE TOO SHORT AND HAD TO BE REPLACED. |
| Mod SA008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$46,409 | $196,166 | TO PROVIDE A NEUTRAL FEEDER FOR PANEL ESGA THAT WAS NOT SHOWN ON THE CONTRACT DOCUMENTS. |
| Mod SA009· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$3,738 | $199,904 | TO REMOVE AND DISPOSE OF ASBESTOS WALL PANELS THAT HAD TO BE REMOVED IN ORDER TO DEMOLISH AND REMOVE THE EXIST… |
| Mod SA010· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$10,596 | $210,500 | BECAUSE THERE IS NO SAFETY BARRIER ALONG THE EDGE OF THE ROAD TO PREVENT VEHICLES FROM LEAVING THE ROAD AND GO… |
| Mod SA011· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$14,749 | $225,249 | TO REPLACE THE DAMAGED ELECTRONIC CONTOL BOARDS IN THE THE TWO EXISTING MEDIUM VOLTAGE GENERATORS. |
| Mod TE001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-03 | +$0 | $225,249 | TO ADD 21 CALENDAR DAYS TO THE CONTRACT DUE TO DELAY CAUSED BY LIGHTNING DAMAGE TO THE NEW MAIN SWITCHGEAR AND… |
| Mod SA012· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-29 | +$21,708 | $246,957 | INCREASE THE SIZE OF MAKEUP WATER LINES TO THE COOLING TOWER. |
| Mod SA013· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-16 | +$587 | $247,544 | TO ADJUST THE CONTRACTOR'S BOND PREMIUM BECAUSE OF THE MODIFICATIONS ISSUED TO THE CONTRACT DURING CONSTRUCTIO… |
Related awards · 2
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y159 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0001 | ESAC/LS, A JOINT VENTURE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $817,310 | FY2009 |
| VA101CFMC0073 | AFFILIATED WESTERN, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $2,552,009 | FY2009 |