Description
UTILITIES INSTALLED UNDER PHASE 1A CONFLICTED WITH THE INSTALLATION OF WORK TO BE PERFORMED BY SUBSEQUENT-PHASE CONTRACTORS. REVIEW OF AS-BUILT PLANS, RFI'S, AND CONTRACT DOCUMENTS PROVES CONCLUSIVELY THAT THE 1A CONTRACTOR WAS AT FAULT. THIS CHANGE ORDER RECOUPS COSTS INCURRED BY THE GOVERNMENT AS A RESULT OF THESE IMPACTS TO OTHER PHASES.
Base award description: PREP SITE
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-07-30+$9,280,000= $9,280,000
- Mod SA0012009-10-06+$33,462= $9,313,462
- Mod SA0022009-11-02+$5,646= $9,319,108
- Mod SA0032009-11-16+$51,428= $9,370,536
- Mod SA0042009-12-11+$27,534= $9,398,070
- Mod SA0052009-12-11+$5,080= $9,403,150
- Mod SA0062010-01-14+$18,875= $9,422,025
- Mod SA0072010-01-29+$8,387= $9,430,412
- Mod SA0082010-02-26+$34,997= $9,465,409
- Mod SA0112010-04-21+$9,808= $9,475,217
- Mod SA0142010-05-12+$11,397= $9,486,614
- Mod SA0152010-05-12+$11,504= $9,498,118
- Mod SA0162010-05-12+$23,732= $9,521,850
- Mod SA0122010-05-18+$1,527= $9,523,377
- Mod SA0132010-06-14+$39,286= $9,562,663
- Mod SA0192011-06-09+$268= $9,562,931
- Mod SA0182011-06-19-$29,533= $9,533,398
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-07-30 | +$9,280,000 | $9,280,000 | PREP SITE |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-06 | +$33,462 | $9,313,462 | TESTING LAB SERVICES |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-02 | +$5,646 | $9,319,108 | MANHOLE RINGS/COVERS |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-16 | +$51,428 | $9,370,536 | HEADWALL A77 |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-11 | +$27,534 | $9,398,070 | WEST PROPERTY LINE IMPROVEMENTS |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-11 | +$5,080 | $9,403,150 | SITEWORK, UTILITIES&ROADS, PKG 1A, ORLANDO, FL |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-14 | +$18,875 | $9,422,025 | SA-006, MAIN ENTRANCE MODIFICATION |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-29 | +$8,387 | $9,430,412 | SA-007,RELO WEST PERIMETER FENCE |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-26 | +$34,997 | $9,465,409 | OUC DUCTBANK |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-21 | +$9,808 | $9,475,217 | VAULT A MECHNANICAL PIPING COORDINATION |
| Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-12 | +$11,397 | $9,486,614 | OUC/CITY OF ORLANDO CHANGES |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-12 | +$11,504 | $9,498,118 | OUC STABILIZATION |
| Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-12 | +$23,732 | $9,521,850 | INSULATORS/RECLAIM METER |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-18 | +$1,527 | $9,523,377 | OUC/CITY OF ORLANDO CHANGES |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-14 | +$39,286 | $9,562,663 | OUC/CITY OF ORLANDO CHANGES |
| Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-09 | +$268 | $9,562,931 | FINAL ADJUSTMENT OF BOND PREMIUM; FINAL RECONCILIATION OF UTILITY CONSUMPTION. |
| Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-19 | −$29,533 | $9,533,398 | UTILITIES INSTALLED UNDER PHASE 1A CONFLICTED WITH THE INSTALLATION OF WORK TO BE PERFORMED BY SUBSEQUENT-PHAS… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GH24ZFQWHST9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78626P0055 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $34,653 | FY2026 |
| 36C78626C0008 | NATIONAL CEMETERY ADMIN (36C786) · Y1EB · CONSTRUCTION OF MAINTENANCE BUILDINGS | $3,400,000 | FY2026 |
| 36C24426N0368 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,000 | FY2026 |
| 36C24426D0034 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2026 |
| 36C24426N0064 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $376,054 | FY2026 |
| 36C24425N1329 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $182,175 | FY2025 |
Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0167 | THE R.E.M. ENGINEERING CO INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $384,303 | FY2011 |
| VA101CFMC0130 | TTL ASSOCIATES INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $101,742 | FY2011 |
| VA101CFMC0111 | WALSH CONSTRUCTION PUERTO RICO | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $52,457,646 | FY2010 |
| VA101CFMC0085 | ARCHER WESTERN/DEMARIA JOINT VENTURE III | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $58,427,947 | FY2010 |
| VACFM05I0064 | N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $114,946 | FY2010 |