Description
SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS. THE A/E HAS PROVIDED DESIGN RECOMMENDATIONS TO ACHIEVE COMPLIANCE. THE VAMC HAS REQUESTED THAT THESE CHANGES AND MODIFICATIONS BE IMPLEMENTED ON AN EXPEDITED BASIS TO SUPPORT CLINIC OPENING AT YEAR-END. THE GENERAL CONTRACTOR HAS AGREED TO ACCEPT THE CONTRACT CHANGE ORDER TO PERFORM THE WORK.
Base award description: CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC
Modification chain · 362 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-09-25+$53,144,925= $53,144,925
- Mod CO01A2010-03-05+$211,115= $53,356,040
- Mod CO01B2010-03-31+$6,738= $53,362,778
- Mod SA0012010-09-30+$20,868= $53,383,646
- Mod SA0022010-09-30+$43,598= $53,427,244
- Mod SA0032010-09-30+$52,974= $53,480,218
- Mod SA0042010-09-30+$38,216= $53,518,434
- Mod SA0052010-09-30+$42,629= $53,561,063
- Mod SA0062010-09-30+$18,660= $53,579,723
- Mod SA0072010-09-30+$5,732= $53,585,455
- Mod SA0082010-09-30+$5,621= $53,591,076
- Mod SA0092010-09-30+$39,370= $53,630,446
- Mod SA0102010-09-30+$39,774= $53,670,220
- Mod SA0112010-09-30+$1,477= $53,671,697
- Mod SA0122010-09-30+$88,454= $53,760,151
- Mod SA0132010-10-04+$21,877= $53,782,028
- Mod SA0142010-10-06+$50,531= $53,832,559
- Mod SA0152010-12-29+$440= $53,832,999
- Mod SA0162010-12-29+$20,000= $53,852,999
- Mod SA0172010-12-29+$2,310= $53,855,309
- Mod SA0182010-12-29+$3,134= $53,858,443
- Mod SA0202010-12-29+$3,218= $53,861,661
- Mod SA0212010-12-29+$9,468= $53,871,129
- Mod SA0222010-12-29+$5,022= $53,876,151
- Mod SA0232010-12-29+$18,692= $53,894,843
- Mod SA0242010-12-29+$54,528= $53,949,371
- Mod SA0252010-12-29+$7,645= $53,957,016
- Mod SA0272011-01-06+$43,601= $54,000,617
- Mod SA0312011-02-06+$10,484= $54,011,101
- Mod SA0322011-02-06+$16,126= $54,027,227
- Mod SA0332011-02-06+$2,769= $54,029,996
- Mod SA0392011-02-07+$5,379= $54,035,375
- Mod SA0292011-02-20-$36,128= $53,999,247
- Mod SA0302011-02-20+$3,189= $54,002,436
- Mod SA0402011-03-11+$99,639= $54,102,075
- Mod SA0412011-03-11+$5,192= $54,107,267
- Mod SA0462011-03-21+$24,850= $54,132,117
- Mod SA0472011-03-21+$20,781= $54,152,898
- Mod SA0422011-03-22+$5,070= $54,157,968
- Mod SA0432011-03-22+$4,131= $54,162,099
- Mod SA0592011-04-07+$66,478= $54,228,577
- Mod SA0542011-04-08+$8,506= $54,237,083
- Mod SA0552011-04-08+$3,119= $54,240,202
- Mod SA0482011-04-11+$35,674= $54,275,876
- Mod SA0602011-04-11+$9,367= $54,285,243
- Mod SA0622011-04-11+$71,351= $54,356,594
- Mod CO01C2011-04-12+$4,813= $54,361,407
- Mod CO01D2011-04-12+$2,445= $54,363,852
- Mod CO01E2011-04-12+$66,000= $54,429,852
- Mod SA0442011-04-13+$35,053= $54,464,905
- Mod SA0492011-04-13+$17,923= $54,482,828
- Mod SA0502011-04-13+$11,821= $54,494,649
- Mod SA0512011-04-13+$28,912= $54,523,561
- Mod SA0522011-04-13+$9,834= $54,533,395
- Mod SA0532011-04-13+$6,688= $54,540,083
- Mod SA0612011-04-14+$4,392= $54,544,475
- Mod SA0632011-04-14+$1,982= $54,546,457
- Mod SA0642011-04-14+$6,266= $54,552,723
- Mod SA0562011-05-03+$32,805= $54,585,528
- Mod SA0572011-05-03+$70,775= $54,656,303
- Mod SA0582011-05-03+$4,321= $54,660,624
- Mod SA0652011-05-03+$13,050= $54,673,674
- Mod SA0662011-05-03+$3,991= $54,677,665
- Mod SA0672011-05-03+$3,698= $54,681,363
- Mod SA0682011-05-09+$4,925= $54,686,288
- Mod SA0692011-05-09+$14,000= $54,700,288
- Mod SA0702011-05-09+$8,320= $54,708,608
- Mod SA0712011-05-09+$44,825= $54,753,433
- Mod SA0722011-05-09+$1,308= $54,754,741
- Mod SA0262011-05-10+$64,063= $54,818,804
- Mod SA0382011-05-10+$938= $54,819,742
- Mod SA0452011-05-10+$13,408= $54,833,150
- Mod SA0282011-05-18+$1,317= $54,834,467
- Mod SA0812011-07-20+$20,900= $54,855,367
- Mod SA0832011-07-20+$36,321= $54,891,688
- Mod SA0862011-07-20+$14,717= $54,906,405
- Mod SA0872011-07-20+$22,733= $54,929,138
- Mod SA0892011-07-20+$31,514= $54,960,652
- Mod SA0912011-07-20+$385= $54,961,037
- Mod SA0922011-07-20+$5,333= $54,966,370
- Mod SA0932011-07-20+$1,711= $54,968,081
- Mod SA0942011-07-20+$385= $54,968,466
- Mod SA0952011-07-20+$5,749= $54,974,215
- Mod SA0962011-07-20+$10,654= $54,984,869
- Mod SA0982011-07-20+$22,439= $55,007,308
- Mod SA0992011-07-20+$8,900= $55,016,208
- Mod SA1002011-07-20+$2,074= $55,018,282
- Mod SA1012011-07-20+$1,715= $55,019,997
- Mod SA1022011-07-20+$5,900= $55,025,897
- Mod SA1032011-07-20+$25,036= $55,050,933
- Mod CO01F2011-07-25+$97,079= $55,148,012
- Mod SA0972011-07-25+$604= $55,148,616
- Mod SA1042011-07-25+$4,069= $55,152,685
- Mod SA1052011-07-25+$18,931= $55,171,616
- Mod SA1062011-07-25+$8,091= $55,179,707
- Mod SA1072011-07-25+$9,532= $55,189,239
- Mod SA1082011-07-25+$20,540= $55,209,779
- Mod SA1092011-07-25+$1,867= $55,211,646
- Mod SA1102011-07-25+$7,432= $55,219,078
- Mod SA1112011-07-25+$2,305= $55,221,383
- Mod SA1122011-07-25+$1,419= $55,222,802
- Mod SA1132011-07-25+$72,295= $55,295,097
- Mod SA1142011-07-25+$47,429= $55,342,526
- Mod SA1152011-07-25+$11,509= $55,354,035
- Mod SA1182011-07-25+$10,521= $55,364,556
- Mod SA1202011-07-25+$30,279= $55,394,835
- Mod SA1192011-07-26+$39,289= $55,434,124
- Mod SA1302011-08-16+$4,840= $55,438,964
- Mod SA1312011-08-16+$11,334= $55,450,298
- Mod SA1322011-08-16+$25,021= $55,475,319
- Mod SA1332011-08-16+$2,124= $55,477,443
- Mod SA1342011-08-16+$21,322= $55,498,765
- Mod SA1352011-08-16+$2,821= $55,501,586
- Mod SA1362011-08-16+$17,024= $55,518,610
- Mod SA1372011-08-16+$12,222= $55,530,832
- Mod SA1382011-08-16+$3,000= $55,533,832
- Mod SA1392011-08-16+$12,848= $55,546,680
- Mod SA0792011-08-17+$385= $55,547,065
- Mod SA0802011-08-17+$20,723= $55,567,788
- Mod SA0842011-08-17+$2,353= $55,570,141
- Mod SA0852011-08-17+$2,818= $55,572,959
- Mod SA0882011-08-17+$1,382= $55,574,341
- Mod SA0902011-08-17+$6,332= $55,580,673
- Mod SA1222011-08-23+$4,285= $55,584,958
- Mod SA1232011-08-23+$98,118= $55,683,076
- Mod SA1242011-08-23+$8,000= $55,691,076
- Mod SA1422011-08-30+$87,975= $55,779,051
- Mod SA1442011-08-30+$13,031= $55,792,082
- Mod SA1452011-08-30+$10,332= $55,802,414
- Mod SA1462011-08-30+$7,350= $55,809,764
- Mod SA1472011-08-30+$1,460= $55,811,224
- Mod SA1482011-08-30+$14,042= $55,825,266
- Mod CO01G2011-09-06+$33,962= $55,859,228
- Mod CO01H2011-09-06+$11,550= $55,870,778
- Mod SA1212011-09-06+$5,817= $55,876,595
- Mod SA1252011-09-06+$9,492= $55,886,087
- Mod SA1272011-09-06-$37,636= $55,848,451
- Mod SA1282011-09-06+$7,581= $55,856,032
- Mod SA1292011-09-06+$50,776= $55,906,808
- Mod SA1402011-09-06+$2,694= $55,909,502
- Mod SA0192011-09-12+$22,086= $55,931,588
- Mod SA0342011-09-12+$15,825= $55,947,413
- Mod SA0352011-09-12+$16,350= $55,963,763
- Mod SA0362011-09-12-$13,237= $55,950,526
- Mod SA0372011-09-12+$15,289= $55,965,815
- Mod SA0732011-09-12+$12,047= $55,977,862
- Mod SA0742011-09-12+$3,740= $55,981,602
- Mod SA0752011-09-12+$8,628= $55,990,230
- Mod SA0762011-09-12+$9,183= $55,999,413
- Mod SA0772011-09-12+$1,500= $56,000,913
- Mod SA0822011-09-12+$33,782= $56,034,695
- Mod SA1172011-09-12+$34,257= $56,068,952
- Mod SA1262011-09-12+$1,746= $56,070,698
- Mod SA1412011-09-12+$27,314= $56,098,012
- Mod SA1512011-09-12+$56,661= $56,154,673
- Mod SA1522011-09-12+$21,915= $56,176,588
- Mod SA1532011-09-12+$5,508= $56,182,096
- Mod SA1542011-09-12-$37,547= $56,144,549
- Mod SA1562011-09-12+$86,071= $56,230,620
- Mod SA1572011-09-12+$3,388= $56,234,008
- Mod SA1582011-09-12+$36,186= $56,270,194
- Mod SA1592011-09-12+$6,229= $56,276,423
- Mod SA1602011-09-12+$92,713= $56,369,136
- Mod SA1612011-09-12+$4,822= $56,373,958
- Mod SA1622011-09-12+$5,017= $56,378,975
- Mod SA1642011-09-23+$14,640= $56,393,615
- Mod SA1682011-09-23+$1,782= $56,395,397
- Mod SA1692011-10-06+$8,726= $56,404,123
- Mod SA1702011-10-06+$21,094= $56,425,217
- Mod SA1762011-10-06+$35,458= $56,460,675
- Mod SA1712011-10-07+$10,996= $56,471,671
- Mod SA1722011-10-07+$14,670= $56,486,341
- Mod SA1732011-10-07+$19,713= $56,506,054
- Mod SA1742011-10-07+$10,918= $56,516,972
- Mod SA1752011-10-07+$15,457= $56,532,429
- Mod SA1772011-10-11+$9,877= $56,542,306
- Mod SA1782011-10-11+$15,638= $56,557,944
- Mod SA1162011-10-14-$275,000= $56,282,944
- Mod SA1662011-10-24+$6,557= $56,289,501
- Mod SA1492011-10-25+$15,083= $56,304,584
- Mod SA1502011-10-25+$16,295= $56,320,879
- Mod SA1632011-10-25+$31,874= $56,352,753
- Mod SA1792011-10-25+$59,050= $56,411,803
- Mod SA1802011-11-01+$52,051= $56,463,854
- Mod SA1812011-11-01+$54,254= $56,518,108
- Mod SA0782011-12-08+$25,000= $56,543,108
- Mod SA1672011-12-08+$27,579= $56,570,687
- Mod CO01J2011-12-14+$50,000= $56,620,687
- Mod CO01L2011-12-14+$15,000= $56,635,687
- Mod CO01O2011-12-20+$1,129= $56,636,816
- Mod SA1552011-12-23+$205,569= $56,842,385
- Mod SA1652011-12-28+$23,457= $56,865,842
- Mod CO01I2012-01-03+$95,424= $56,961,266
- Mod SA1822012-01-03+$10,825= $56,972,091
- Mod CO01M2012-01-16+$35,000= $57,007,091
- Mod CO01N2012-01-16+$40,000= $57,047,091
- Mod SA1832012-01-16+$14,440= $57,061,531
- Mod CO01K2012-01-20-$49,033= $57,012,498
- Mod CO01P2012-01-20+$3,421= $57,015,919
- Mod CO01Q2012-01-20+$11,227= $57,027,146
- Mod CO01R2012-01-20+$12,538= $57,039,684
- Mod CO01S2012-02-03+$1,841= $57,041,525
- Mod CO01T2012-02-13+$20,459= $57,061,984
- Mod CO01U2012-02-17+$3,780= $57,065,764
- Mod CO01V2012-02-17+$1,898= $57,067,662
- Mod CO01W2012-02-17+$17,560= $57,085,222
- Mod CO01X2012-02-17+$25,454= $57,110,676
- Mod CO01Y2012-02-17+$5,265= $57,115,941
- Mod CO01Z2012-02-17+$3,646= $57,119,587
- Mod CO02A2012-02-17+$3,569= $57,123,156
- Mod SA1842012-02-17+$4,964= $57,128,120
- Mod SA1852012-02-17+$1,802= $57,129,922
- Mod SA1432012-02-29+$73,709= $57,203,631
- Mod SA1862012-02-29+$8,408= $57,212,039
- Mod SA1872012-02-29+$59,947= $57,271,986
- Mod CO02B2012-03-06+$2,910= $57,274,896
- Mod SA1882012-03-07+$46,475= $57,321,371
- Mod SA1892012-03-08+$7,641= $57,329,012
- Mod SA1902012-03-08+$79,589= $57,408,601
- Mod SA1912012-03-08+$2,068= $57,410,669
- Mod SA1922012-03-08+$56,832= $57,467,501
- Mod SA1932012-03-08+$1,994= $57,469,495
- Mod SA1942012-03-08+$3,185= $57,472,680
- Mod CO02C2012-04-11+$19,984= $57,492,664
- Mod SA1962012-04-11+$6,021= $57,498,685
- Mod CO02E2012-04-12+$4,939= $57,503,624
- Mod CO02D2012-04-16+$19,297= $57,522,921
- Mod CO02F2012-04-18+$40,689= $57,563,610
- Mod CO02G2012-04-18+$14,138= $57,577,748
- Mod CO02H2012-04-24+$9,220= $57,586,968
- Mod CO02I2012-04-24+$19,844= $57,606,812
- Mod CO02J2012-04-24+$16,959= $57,623,771
- Mod CO02K2012-04-24+$15,027= $57,638,798
- Mod CO02L2012-04-24+$8,246= $57,647,044
- Mod CO02M2012-04-24+$15,065= $57,662,109
- Mod SA1982012-05-14+$9,005= $57,671,114
- Mod SA1952012-05-16+$3,691= $57,674,805
- Mod SA1972012-05-16+$7,814= $57,682,619
- Mod CO02N2012-05-24+$11,061= $57,693,680
- Mod CO02O2012-05-24+$8,075= $57,701,755
- Mod CO02P2012-05-25+$3,914= $57,705,669
- Mod SA1992012-05-31+$385= $57,706,054
- Mod CO02Q2012-06-11+$2,054= $57,708,108
- Mod SA2002012-06-19+$4,569= $57,712,677
- Mod SA2012012-06-19+$17,339= $57,730,016
- Mod SA2042012-06-19+$298= $57,730,314
- Mod SA2052012-06-19+$4,525= $57,734,839
- Mod SA2062012-06-19+$1,080= $57,735,919
- Mod SA2072012-06-19+$2,841= $57,738,760
- Mod SA2032012-06-20+$1,586= $57,740,346
- Mod SA2122012-06-22+$2,538= $57,742,884
- Mod SA2152012-06-22-$141= $57,742,743
- Mod SA2022012-07-19-$3,424= $57,739,319
- Mod CO02R2012-07-20+$8,469= $57,747,788
- Mod SA2102012-07-20+$4,500= $57,752,288
- Mod SA2212012-07-20+$25,966= $57,778,254
- Mod SA2092012-07-23+$1,342= $57,779,596
- Mod SA2182012-07-23+$9,637= $57,789,233
- Mod SA2192012-07-23-$252= $57,788,981
- Mod SA2112012-07-25+$2,805= $57,791,786
- Mod SA2162012-07-25+$6,000= $57,797,786
- Mod SA2202012-07-26+$13,192= $57,810,978
- Mod SA2222012-07-26+$7,055= $57,818,033
- Mod SA2232012-07-26+$8,845= $57,826,878
- Mod SA2242012-07-26+$6,478= $57,833,356
- Mod SA2252012-07-26+$16,704= $57,850,060
- Mod CO02S2012-07-27+$2,000= $57,852,060
- Mod SA2262012-08-08+$31,730= $57,883,790
- Mod SA2272012-08-22-$11,465= $57,872,325
- Mod SA2302012-08-22+$1,608= $57,873,933
- Mod SA2312012-08-22+$8,450= $57,882,383
- Mod SA2322012-08-22+$13,192= $57,895,575
- Mod SA2332012-08-22+$14,971= $57,910,546
- Mod SA2342012-08-27+$19,213= $57,929,759
- Mod SA2352012-08-27+$18,952= $57,948,711
- Mod SA2372012-08-27+$9,853= $57,958,564
- Mod SA2392012-09-07+$39,054= $57,997,618
- Mod SA2142012-09-17+$14,074= $58,011,692
- Mod SA2172012-09-17+$40,015= $58,051,707
- Mod CO02T2012-09-24+$95,518= $58,147,225
- Mod SA2132012-09-29+$140,827= $58,288,052
- Mod SA2282012-10-04+$75,354= $58,363,406
- Mod CO02W2012-10-06+$6,855= $58,370,261
- Mod SA2292012-10-06+$25,177= $58,395,438
- Mod SA2402012-10-06+$1,770= $58,397,208
- Mod SA2412012-10-06+$17,213= $58,414,421
- Mod SA2422012-10-06+$18,978= $58,433,399
- Mod SA2432012-10-06+$5,665= $58,439,064
- Mod SA2442012-10-06+$16,322= $58,455,386
- Mod SA2452012-10-06+$1,708= $58,457,094
- Mod SA2462012-10-06+$2,830= $58,459,924
- Mod SA2472012-10-06+$2,346= $58,462,270
- Mod SA2492012-10-06+$10,650= $58,472,920
- Mod SA2482012-10-10+$4,793= $58,477,713
- Mod SA2512012-10-17+$1,551= $58,479,264
- Mod SA2532012-10-17+$2,047= $58,481,311
- Mod SA2542012-10-17+$6,720= $58,488,031
- Mod SA2562012-10-22+$2,882= $58,490,913
- Mod SA2572012-10-22+$17,735= $58,508,648
- Mod SA2582012-10-22+$10,269= $58,518,917
- Mod SA2382012-10-24+$21,610= $58,540,527
- Mod SA2592012-10-25+$28,277= $58,568,804
- Mod SA2552012-11-02+$14,865= $58,583,669
- Mod SA2602012-11-02+$12,291= $58,595,960
- Mod SA2612012-11-02+$8,552= $58,604,512
- Mod SA2632012-11-27+$12,500= $58,617,012
- Mod SA2642012-11-27+$37,210= $58,654,222
- Mod CO02V2012-11-28+$5,660= $58,659,882
- Mod CO02X2012-11-28+$25,000= $58,684,882
- Mod SA2662012-12-05+$7,589= $58,692,471
- Mod SA2692012-12-05+$2,863= $58,695,334
- Mod CO02Z2012-12-21+$20,000= $58,715,334
- Mod CO02Y2012-12-28+$19,000= $58,734,334
- Mod SA2712013-01-07+$2,621= $58,736,955
- Mod P000032013-01-16+$3,411= $58,740,366
- Mod CO03A2013-01-17+$5,351= $58,745,717
- Mod SA2672013-01-28+$20,631= $58,766,348
- Mod P000012013-01-31+$2,206= $58,768,554
- Mod P000042013-02-14+$15,000= $58,783,554
- Mod P000072013-02-14+$16,321= $58,799,875
- Mod P000082013-02-19+$38,751= $58,838,626
- Mod P000112013-02-20+$19,171= $58,857,797
- Mod P000052013-02-22+$1,366= $58,859,163
- Mod P000132013-03-12+$10,000= $58,869,163
- Mod SA2622013-03-21+$615= $58,869,778
- Mod P000092013-04-05-$1,064= $58,868,714
- Mod P000142013-04-15-$1,650= $58,867,064
- Mod P000152013-04-15+$6,370= $58,873,434
- Mod P000182013-04-24+$2,325= $58,875,759
- Mod P000192013-04-24-$549= $58,875,210
- Mod P000232013-04-29+$5,400= $58,880,610
- Mod P000162013-04-30+$98,000= $58,978,610
- Mod P000202013-04-30-$7,699= $58,970,911
- Mod P000212013-04-30+$1,007= $58,971,918
- Mod P000222013-04-30-$6,406= $58,965,512
- Mod P000172013-05-02+$0= $58,965,512
- Mod P000242013-05-03+$7,454= $58,972,966
- Mod P000252013-05-20+$5,767= $58,978,733
- Mod P000262013-05-31+$81,895= $59,060,628
- Mod P000312013-05-31+$24,000= $59,084,628
- Mod P000282013-06-03+$2,539= $59,087,167
- Mod P000292013-06-04+$3,686= $59,090,853
- Mod P000302013-06-04+$3,905= $59,094,758
- Mod P000272013-06-06+$13,712= $59,108,470
- Mod P000322013-06-06-$10,634= $59,097,836
- Mod P000332013-06-06-$5,000= $59,092,836
- Mod P000342013-06-06+$4,241= $59,097,077
- Mod P000362013-06-06+$8,936= $59,106,013
- Mod P000372013-06-06+$28,533= $59,134,546
- Mod P000352013-06-07+$11,534= $59,146,080
- Mod SA2732013-07-17+$12,786= $59,158,866
- Mod P000392013-07-19+$30,645= $59,189,511
- Mod P000402013-07-19+$0= $59,189,511
- Mod P000412013-07-19+$27,227= $59,216,738
- Mod P000422013-07-19+$0= $59,216,738
- Mod P000432013-07-19+$3,453= $59,220,191
- Mod P000442013-08-01+$3,678= $59,223,869
- Mod P000452013-08-14+$2,321= $59,226,190
- Mod P000462013-08-14-$1,627= $59,224,563
- Mod P000382013-09-20+$14,482= $59,239,045
- Mod SA2522013-10-17+$9,543= $59,248,588
- Mod CO02U2013-10-22+$1,977= $59,250,565
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-09-25 | +$53,144,925 | $53,144,925 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC |
| Mod CO01A· CHANGE ORDER | 2010-03-05 | +$211,115 | $53,356,040 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC, CO-01A |
| Mod CO01B· CHANGE ORDER | 2010-03-31 | +$6,738 | $53,362,778 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC, CO-01B |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$20,868 | $53,383,646 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-001 |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$43,598 | $53,427,244 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-004 |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$52,974 | $53,480,218 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-003 |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$38,216 | $53,518,434 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-004 |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$42,629 | $53,561,063 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-005 |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$18,660 | $53,579,723 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-006 |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$5,732 | $53,585,455 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-007 |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$5,621 | $53,591,076 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-008 |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$39,370 | $53,630,446 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-009 |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$39,774 | $53,670,220 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-010 |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$1,477 | $53,671,697 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-011 |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$88,454 | $53,760,151 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-012 |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-04 | +$21,877 | $53,782,028 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-013 |
| Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-06 | +$50,531 | $53,832,559 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-014 |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$440 | $53,832,999 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-015 |
| Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$20,000 | $53,852,999 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-016 |
| Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$2,310 | $53,855,309 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-017 |
| Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$3,134 | $53,858,443 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-018 |
| Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$3,218 | $53,861,661 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-020 |
| Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$9,468 | $53,871,129 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-021 |
| Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$5,022 | $53,876,151 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-022 |
| Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$18,692 | $53,894,843 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-023 |
| Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$54,528 | $53,949,371 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-024 |
| Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$7,645 | $53,957,016 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-025 |
| Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-06 | +$43,601 | $54,000,617 | LEE COUNTY OUTPATIENT CLINIC SA-012 |
| Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-06 | +$10,484 | $54,011,101 | LEE COUNTY OUTPATIENT CLINIC SA-031 |
| Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-06 | +$16,126 | $54,027,227 | LEE COUNTY OUTPATIENT CLINIC SA-032 |
| Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-06 | +$2,769 | $54,029,996 | LEE COUNTY OUTPATIENT CLINIC SA-032 |
| Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-07 | +$5,379 | $54,035,375 | LEE COUNTY OUTPATIENT CLINIC SA-039 |
| Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-20 | −$36,128 | $53,999,247 | LEE COUNTY OUTPATIENT CLINIC SA-029 |
| Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-20 | +$3,189 | $54,002,436 | LEE COUNTY OUTPATIENT CLINIC SA-030 |
| Mod SA040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-11 | +$99,639 | $54,102,075 | LEE COUNTY OUTPATIENT CLINIC SA-040 |
| Mod SA041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-11 | +$5,192 | $54,107,267 | LEE COUNTY OUTPATIENT CLINIC SA-041 |
| Mod SA046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-21 | +$24,850 | $54,132,117 | LEE COUNTY OUTPATIENT CLINIC SA-046 |
| Mod SA047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-21 | +$20,781 | $54,152,898 | LEE COUNTY OUTPATIENT CLINIC SA-047 |
| Mod SA042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-22 | +$5,070 | $54,157,968 | LEE COUNTY OUTPATIENT CLINIC SA-042 |
| Mod SA043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-22 | +$4,131 | $54,162,099 | LEE COUNTY OUTPATIENT CLINIC SA-043 |
| Mod SA059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-07 | +$66,478 | $54,228,577 | LEE COUNTY OUTPATIENT CLINIC SA-059 |
| Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$8,506 | $54,237,083 | LEE COUNTY OUTPATIENT CLINIC SA-054 |
| Mod SA055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$3,119 | $54,240,202 | LEE COUNTY OUTPATIENT CLINIC SA-055 |
| Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-11 | +$35,674 | $54,275,876 | LEE COUNTY OUTPATIENT CLINIC SA-048 |
| Mod SA060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-11 | +$9,367 | $54,285,243 | LEE COUNTY OUTPATIENT CLINIC SA-060 |
| Mod SA062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-11 | +$71,351 | $54,356,594 | TO RELOCATE THE DOMESTIC WATER TANK PUMP FROM IN GROUND TO AN ENCLOSURE ABOVE GROUND. SA-062 |
| Mod CO01C· CHANGE ORDER | 2011-04-12 | +$4,813 | $54,361,407 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC, CO-01C |
| Mod CO01D· CHANGE ORDER | 2011-04-12 | +$2,445 | $54,363,852 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC, CO-01D |
| Mod CO01E· CHANGE ORDER | 2011-04-12 | +$66,000 | $54,429,852 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC, CO-01E |
| Mod SA044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$35,053 | $54,464,905 | LEE COUNTY OUTPATIENT CLINIC SA-044 |
| Mod SA049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$17,923 | $54,482,828 | LEE COUNTY OUTPATIENT CLINIC SA-049 |
| Mod SA050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$11,821 | $54,494,649 | LEE COUNTY OUTPATIENT CLINIC SA-050 |
| Mod SA051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$28,912 | $54,523,561 | LEE COUNTY OUTPATIENT CLINIC SA-051 |
| Mod SA052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$9,834 | $54,533,395 | LEE COUNTY OUTPATIENT CLINIC SA-052 |
| Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$6,688 | $54,540,083 | LEE COUNTY OUTPATIENT CLINIC SA-053 |
| Mod SA061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-14 | +$4,392 | $54,544,475 | LEE COUNTY OUTPATIENT CLINIC SA-061 |
| Mod SA063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-14 | +$1,982 | $54,546,457 | LEE COUNTY OUTPATIENT CLINIC SA-063 |
| Mod SA064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-14 | +$6,266 | $54,552,723 | LEE COUNTY OUTPATIENT CLINIC SA-064 |
| Mod SA056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$32,805 | $54,585,528 | TO RELOCATE THERMOSTAT LOCATIONS THAT WERE IN CONFLICT WITH OTHER WORK SHOWN ON THE CONTRACT DOCUMENTS. SA-056 |
| Mod SA057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$70,775 | $54,656,303 | THE VA MEDICAL CENTER INFORMATION TECHNOLOGY REQUESTED ADDITIONAL NEEDS FOR ADDITIONAL DATA, POWER AND TELEPHO… |
| Mod SA058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$4,321 | $54,660,624 | THE CONTRACT DOCUMENTS DID NOT INCLUDE A COLOR FOR THE STANDING SEAM METAL ROOF AND IT WAS DETERMINED TO SELEC… |
| Mod SA065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$13,050 | $54,673,674 | TO REPLACE EXAM ROOM SINKS SO AS TO MEET UFAS AND ADA REQUIREMENTS. SA-065 |
| Mod SA066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$3,991 | $54,677,665 | TO INCREASES THE SIZE OF A STRUCTURAL STEEL ANGLE AT THE HEAD OF WALL OF THE CURTAIN WALL LOCATED AT THE SECON… |
| Mod SA067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$3,698 | $54,681,363 | TO REVISE WALL LOCATIONS, TYPES AND PARTITION HEIGHTS DUE TO DESIGN ERRORS. MODIFY LEAD LINED PARTITIONS AND… |
| Mod SA068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$4,925 | $54,686,288 | RELOCATE ELECTRICAL BOXES, DEVICES; CHANGE QUADS TO DUPLEX. SA-068 |
| Mod SA069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$14,000 | $54,700,288 | SA-069 TO REPLACE DENTAL LIGHT BRACING IN-WALL WITH BRACING IN-CEILING PER THE REQUEST OF THE VAMC. |
| Mod SA070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$8,320 | $54,708,608 | SA-070 THE CONTRACT DOCUMENTS STATE WATER IS AVAILABLE AT NO COST TO THE CONTRACTOR AND IS IN ERROR. DUE TO T… |
| Mod SA071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$44,825 | $54,753,433 | SA-071 THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR AND IS IN ERROR. DU… |
| Mod SA072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$1,308 | $54,754,741 | SA-072 TO MODIFY GLAZING DUE TO ERRORS IN THE DESIGN. |
| Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-10 | +$64,063 | $54,818,804 | SA-026 TO PROVIDE ADDITIONAL PHOTOGRAPHIC DOCUMENTATION FOR THE PROJECT TO AIDE THE GOVERNMENT IN THE DOCUMENT… |
| Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-10 | +$938 | $54,819,742 | SA-028 THE CONTRACT DRAWINGS NEEDED TO BE REVISED TO REVISE AN ELEVATOR SHAFT DAMPERS TO REFLECT THE CLEARANCE… |
| Mod SA045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-10 | +$13,408 | $54,833,150 | SA-045 TO ADD PLUMBING DRAIN MODIFICATIONS TO ROOM 2B-169 AS WELL AS ADD ADDITIONAL UTILITIES TO THE FUTURE MO… |
| Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-18 | +$1,317 | $54,834,467 | SA-028 TO REMOVE DIFFICULT MAINTENANCE ITEMS FROM THE OR AREAS AND INSTALL AS MUCH HVAC EQUIPMENT AS POSSIBLE… |
| Mod SA081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$20,900 | $54,855,367 | SUBSTITUTE WALL AND CEILING FINISH MATERIALS IN SPECIFIC ROOMS TO COMPLY WITH VACFM DESIGN GUIDES AS WELL AS P… |
| Mod SA083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$36,321 | $54,891,688 | TO MODIFY LANDSCAPING TO INCLUDE LANDSCAPING ADDITIONS FOR THE ADD SMOKING SHELTERS, RELOCATE SMOKING SHELTERS… |
| Mod SA086· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$14,717 | $54,906,405 | DURING THE INSTALLATION OF THE WATER MAIN CONNECTION TO DIPLOMAT PARKWAY, THE CONTRACTOR WAS NOT ABLE TO LOCAT… |
| Mod SA087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$22,733 | $54,929,138 | THE RELOCATE STORM PIPE AND OUTLET STRUCTURE TO GOVERNMENT PROPERTY IN LIEU OF ADJACENT PROPERTY THAT IS OWNED… |
| Mod SA089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$31,514 | $54,960,652 | THE CITY OF CAPE CORAL EXISTING STORM DRAINAGE SYSTEM ALONG DIPLOMAT PARKWAY MUST BE RELOCATED SINCE THE REVIS… |
| Mod SA091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$385 | $54,961,037 | TO MODIFY THE GENERATOR, ATS AND SWITCHGEAR SPECIFICATIONS TO ACHIEVE COMPATIBLE FAULT CURRENT AND PROTECTIVE… |
| Mod SA092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$5,333 | $54,966,370 | TO ADD ADDITIONAL VOICE/DATA OUTLETS FOR THE PRINTER SHOWN IN TWO LOCATIONS PER THE EQUIPMENT DRAWINGS BUT NOT… |
| Mod SA093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$1,711 | $54,968,081 | TO ADD CONCRETE STEPS TO THE 2ND FLOOR ROOF ACCESS DOOR AND TO PAINT THE CEP CONTROL ROOM NOT SHOWN ON THE CON… |
| Mod SA094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$385 | $54,968,466 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA095· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$5,749 | $54,974,215 | TO ADD STAINLESS STEEL SHELVES AND TOWEL BARS TO SEVERAL RESTROOMS THROUGHOUT THE FACILITY. |
| Mod SA096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$10,654 | $54,984,869 | THE IRRIGATION WATER WELL WAS DRILLED IN A DIFFERENT LOCATION THAN SHOWN ON AMENDED PLANS CAUSING THE LAYOUT O… |
| Mod SA098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$22,439 | $55,007,308 | THE VAMC REQUESTED FOR A DOOR TO BE ADDED TO ROOM 1B-168 TO THE LOBBY SIDE OF THE ROOM AT PHARMACY FOR IMPROVE… |
| Mod SA099· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$8,900 | $55,016,208 | TO CONVERT STANDARD PARKING SPACES IN THE STAFF PARKING LOT INTO 9 ADA/UFAS PARKING STALLS FOR STAFF HANDICAP… |
| Mod SA100· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$2,074 | $55,018,282 | TO MODIFY THE EXTERIOR LUMINAIRES/FIXTURES IN THE CEP YARD FIXTURE TYPE TO A MORE ARE MORE APPROPRIATE, ARCHIT… |
| Mod SA101· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$1,715 | $55,019,997 | TO MODIFY THE GYPSUM WALL BOARD HEADERS TO ACCEPT THE FULL HEIGHT ACCORDION DOORS IN THE CONFERENCE ROOMS. |
| Mod SA102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$5,900 | $55,025,897 | TO REVISE AND STRENGTHEN THE CANOPY EXPANSION JOINT DETAILS SINCE THE JOINT ARE REQUIRED FOR SECURITY PER THE… |
| Mod SA103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-20 | +$25,036 | $55,050,933 | TO CHANGE COUNTER TOPS IN SPECIFIC HIGH-USE AREAS FROM PLASTIC LAMINATE TO SOLID SURFACE FOR INCREASED DURABIL… |
| Mod CO01F· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$97,079 | $55,148,012 | TO PROVIDE A NEW IRRIGATION WELL TO PROVIDE A 100% WATER SUPPLIED IRRIGATION TO THE SITE SINCE THE CONNECTION… |
| Mod SA097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$604 | $55,148,616 | TO MODIFY THE CERAMIC TILE COLOR SELECTION DUE TO CONTRACT ERRORS AND OMISSIONS. |
| Mod SA104· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$4,069 | $55,152,685 | TO MODIFY THE PAVEMENT TAT THE OXYGEN SERVICE YARD FROM ASHPALT TO CONCRETE DUE TO CODE/AUTHORITY OF JURISDICT… |
| Mod SA105· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$18,931 | $55,171,616 | TO ADD SUB-AQUEOUS PLANTINGS IN THE RETENTION PONDS AS REQUIRED BY THE SFWMD (SOUTH FLORIDA WATER MANAGEMENT… |
| Mod SA106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$8,091 | $55,179,707 | THE VAMC REQUESTED FOR ALL TOILET STALLS/COMPARTMENTS TO BE PLASTIC IN LIEU OF METAL FROM A DURABILITY STANDPO… |
| Mod SA107· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$9,532 | $55,189,239 | CHILLED WATER PIPING FOR THE WALK-IN REFRIGERATOR IN ROOM 1B-106 IS NOT SHOWN ON THE CONTRACT DRAWINGS AND MU… |
| Mod SA108· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$20,540 | $55,209,779 | THE VAMC REQUESTED FOR THE MOPS STATION TO BE MONITORED BY THE BUILDING MANAGEMENT SYSTEM SINCE THE CONTRACT… |
| Mod SA109· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$1,867 | $55,211,646 | A CONCRETE ELECTRIC VAULT AND A STORM SEWER OUT FALL STRUCTURE WERE CONSTRUCTED CLOSE TO THE NORTH PROPERTY LI… |
| Mod SA110· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$7,432 | $55,219,078 | THE CONTRACT DOCUMENTS SHOW FOR THE COOLING TOWER DRAIN TO BE CONNECTED TO THE STORM SEWER SYSTEM BUT THE AUTH… |
| Mod SA111· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$2,305 | $55,221,383 | TO INSTALL A WALL BEHIND THE SPANDREL GLASS IN CORRIDOR C1-27 AND INSTALL AN ACCESS DOOR TO CONCEAL THE RAIN W… |
| Mod SA112· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$1,419 | $55,222,802 | TO REVISE THE CONCRETE CURB DETAIL AT THE INTERSESCTION OF THE EXPANSION JOINTS AT THE SECOND LEVEL ROOF/EXTER… |
| Mod SA113· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$72,295 | $55,295,097 | THE VAMC REQUESTED A CHANGE TO MODIFY THE COOLING TOWER YARD TO ADD AN ADDITIONAL DRIVEWAY AND ENTRY WAY INTO… |
| Mod SA114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$47,429 | $55,342,526 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA115· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$11,509 | $55,354,035 | TO PROVIDE A RAIN KEY/DRIP EDGE ON THE EXTERIOR WALL PRECAST CAP TO PREVENT WATER DAMAGE TO THE WALL. |
| Mod SA118· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$10,521 | $55,364,556 | THE VAMC POLICE REQUESTED CHANGES TO THE LOCKER ROOM AND HOLDING CELL TO BETTER MEET THEIR SECURITY NEEDS FOR… |
| Mod SA120· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-25 | +$30,279 | $55,394,835 | TO MODIFY THE ACOUSTICAL TILE CEILING (ACT) PERFORATION PATTERN TO INCREASE THE NOISE REDUCTION COEFFICIENT (N… |
| Mod SA119· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-26 | +$39,289 | $55,434,124 | THE VA MEDICAL CENTER PERSONNEL REQUESTS PERMANENT ACCESS TO THE LEVEL 2 ROOF AREAS CURRENTLY NOT SHOWN ON THE… |
| Mod SA130· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$4,840 | $55,438,964 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA131· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$11,334 | $55,450,298 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA132· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$25,021 | $55,475,319 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA133· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$2,124 | $55,477,443 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA134· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$21,322 | $55,498,765 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA135· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$2,821 | $55,501,586 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA136· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$17,024 | $55,518,610 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA137· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$12,222 | $55,530,832 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA138· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$3,000 | $55,533,832 | ADJUST DETAILS OF THE CURTAIN WALL DETAILS TO COORDINATE WITH STRUCTURAL STEEL DOCUMENTS. |
| Mod SA139· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$12,848 | $55,546,680 | TO CHANGE CEILINGS PER THE ARCHITECT'S RECOMMENDATIONS ON THE LEVELS 3 AND 4. ALSO, TO CHANGE ACCENT PAINT IN… |
| Mod SA079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$385 | $55,547,065 | LEE COUNTY OUTPATIENT CLINIC SA-079 |
| Mod SA080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$20,723 | $55,567,788 | LEE COUNTY OUTPATIENT CLINIC SA-080 |
| Mod SA084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$2,353 | $55,570,141 | LEE COUNTY OUTPATIENT CLINIC SA-084 |
| Mod SA085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$2,818 | $55,572,959 | LEE COUNTY OUTPATIENT CLINIC SA-085 |
| Mod SA088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$1,382 | $55,574,341 | LEE COUNTY OUTPATIENT CLINIC SA-088 |
| Mod SA090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$6,332 | $55,580,673 | LEE COUNTY OUTPATIENT CLINIC SA-090 |
| Mod SA122· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-23 | +$4,285 | $55,584,958 | LEE COUNTY OUTPATIENT CLINIC, FORT MEYERS, FL SA-122 |
| Mod SA123· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-23 | +$98,118 | $55,683,076 | LEE COUNTY OUTPATIENT CLINIC, FORT MEYERS, FL SA-123 |
| Mod SA124· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-23 | +$8,000 | $55,691,076 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-124 |
| Mod SA142· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$87,975 | $55,779,051 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-142 |
| Mod SA144· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$13,031 | $55,792,082 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-144 |
| Mod SA145· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$10,332 | $55,802,414 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-145 |
| Mod SA146· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$7,350 | $55,809,764 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-146 |
| Mod SA147· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$1,460 | $55,811,224 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-147 |
| Mod SA148· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-30 | +$14,042 | $55,825,266 | CONSTRUCTION OF COMMUNITY BASED OUTPATIENT CLINIC SA-148 |
| Mod CO01G· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$33,962 | $55,859,228 | LEE COUNTY OUTPATIENT, FORT MEYERS, FL CO-01G |
| Mod CO01H· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$11,550 | $55,870,778 | LEE COUNTY OUTPATIENT, FORT MEYERS, FL |
| Mod SA121· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$5,817 | $55,876,595 | LEE COUNTY OUTPATIENT CLINIC, FORT MEYERS, FL |
| Mod SA125· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$9,492 | $55,886,087 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-125 |
| Mod SA127· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | −$37,636 | $55,848,451 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-127 |
| Mod SA128· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$7,581 | $55,856,032 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-128 |
| Mod SA129· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$50,776 | $55,906,808 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-129 |
| Mod SA140· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$2,694 | $55,909,502 | LEE COUNTY OUTPATIENT CLINIC, FORT MEYERS, FL |
| Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$22,086 | $55,931,588 | TO ADD AND DELETE VARIOUS MECHANICAL WORK ITEMS TO CLARIFY THE CONTRACT DOCUMENTS AND PROVIDE A MORE USEFUL F… |
| Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$15,825 | $55,947,413 | IMPROVE ARCHITECTURAL AESTHETICS BY RAISING TOP ELEVATION OF SOUTH SITE WALL AND WINDOW SILL AT STAIR 3 BY 6 I… |
| Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$16,350 | $55,963,763 | TO MODIFY THE AIR TERMINAL UNITS HEATING COIL IN THE OPERATING ROOMS TO PROVIDE PROPER FLOW OF CONDITIONED AIR… |
| Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | −$13,237 | $55,950,526 | TO DELETE THE PURCHASE AND INSTALLATION OF GE EQUIPMENT FROM THE CONTRACT SINCEIT DOES NOT MEET THE BUY AMERIC… |
| Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$15,289 | $55,965,815 | A DESIGN ERROR REVEALED STRUCTURAL STEEL PLATES MUST BE ADDED TO THE STRUCTURAL STEEL ROOF FRAMING OVER THE PU… |
| Mod SA073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$12,047 | $55,977,862 | ADD ELECTRICAL CIRCUITS AND OUTLETS AS DESCRIBED IN RFI'S 137, 138, 139, 140, 141, 142, 143&144 DUE TO DESIGN… |
| Mod SA074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$3,740 | $55,981,602 | TO ADD EMPTY CONDUIT SLEEVES IN FLOOR FOR THE VAMC TO INSTALL WATER LINE FROM DENTAL CHAIRS FLOOR BOX TO WATER… |
| Mod SA075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$8,628 | $55,990,230 | MODIFICATION TO INTERIOR PARTITIONS TO EXTEND ALL THE WAY ABOVE CEILING TO THE BOTTOM OF FLOOR DECK IN LIEU OF… |
| Mod SA076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$9,183 | $55,999,413 | MODIFY SEVERAL INTERIOR PARTITIONS TO EXTEND FROM STRUCTUTE TO STRUCTURE FOR INCREASED SOUND CONTROL AND CONST… |
| Mod SA077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$1,500 | $56,000,913 | ADD A 18" X 10" X 24" CONCRETE CURB AT THE BASE OF THE ACCESS LADDER AT THE PASSENGER ELEVATOR MACHINE ROOM DU… |
| Mod SA082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$33,782 | $56,034,695 | THE VAMC REQUESTED THAT A BARRIER BE INSTALLED BETWEEN THE AUTOMOBILE PARKING LOTS AND THE WET RETENTION PONDS… |
| Mod SA117· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$34,257 | $56,068,952 | TO ADD CONCRETE SLABS AND FOOTINGS FOR THE BUS SHELTERS TO MET CODE COMPLIANCE AND TO MODIFY THE ROOF SHELTER… |
| Mod SA126· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$1,746 | $56,070,698 | LEE COUNTY OUTPATIENT CLINIC, FT MEYERS, FL SA-126 |
| Mod SA141· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$27,314 | $56,098,012 | TO REVISE THE SITE CONCRETE AT THE BUILDING ENTRIES TO SIMPLIFY CONSTRUCTION, ENHANCE AESTHETICS AND INCREASE… |
| Mod SA151· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$56,661 | $56,154,673 | TO PROVIDE POWER, CONTROL, LIGHTING AND COMMUNICATION EQUIPMENT THAT WAS NOT SHOWN ON THE CONTRACT DOCUMENTS F… |
| Mod SA152· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$21,915 | $56,176,588 | TO PROVIDE ADDITIONAL ELECTRICAL WORK NOT SHOWN ON THE CONTRACT DRAWINGS FOR INSTALLATION OF THE VAMC DENTAL X… |
| Mod SA153· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$5,508 | $56,182,096 | TO MODIFY LOCATIONS AND EXTENTS OF CEILING AND WALL EXPANSION JOINTS AND TO REVISE THE INTERIOR EXPANSION JOIN… |
| Mod SA154· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | −$37,547 | $56,144,549 | THE ORIGINAL IRRIGATION WATER WELL PERMITTED AT 30 GPM AND DRILLED DOES NOT MEET THE FLOW REQUIREMENTS OF THE… |
| Mod SA156· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$86,071 | $56,230,620 | THE VAMC PERSONNEL REQUESTED ADDITIONAL NATURAL GAS AND OXYGEN LINES TO VARIOUS ROOMS IN THE DENTAL CLINIC TO… |
| Mod SA157· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$3,388 | $56,234,008 | THE A/E CONTRACT REQUIRED FINAL INSPECTION OF THE SIX ELEVATORS ON THE PROJECT AND THE A/E ELEVATOR INSPECTOR… |
| Mod SA158· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$36,186 | $56,270,194 | THE VAMC REQUESTED THE CHANGE IN UTILITIES FOR THE SCOPE CLEANING AREA SINCE THE ACTUAL EQUIPMENT TO BE INSTAL… |
| Mod SA159· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$6,229 | $56,276,423 | COORDINATION OF ELECTRICAL AND TELECOMMUNICATIONS INSTALLATION DETAILS BASED ON VAMC CURRENT INFORMATION RESUL… |
| Mod SA160· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$92,713 | $56,369,136 | A LOCATION FOR THE FUEL MAINTENANCE SYSTEM WAS NOT INCLUDED ON THE CONTRACT DRAWINGS AND A FINAL LOCATION WAS… |
| Mod SA161· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$4,822 | $56,373,958 | THE EXISTING FORCE MAIN ALONG DIPLOMAT PARKWAY HAD TO BE RELOCATED DUE TO A CONFLICT WITH THE RELOCATED STORM… |
| Mod SA162· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-12 | +$5,017 | $56,378,975 | TO MODIFY AND REPAIR GYPSUM WALL BOARD DUE TO THE RELOCATION OF ELECTRICAL RECEPTACLES, RELOCATED THERMOSTATS… |
| Mod SA164· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-23 | +$14,640 | $56,393,615 | THE ARCHITECT ENGINEER RECOMMEND CHANGING THE STONE VENEER VAPOR BARRIER FROM A TWO COATS OF A FLUID APPLIED,… |
| Mod SA168· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-23 | +$1,782 | $56,395,397 | THE ELECTRICAL CONNECTION TO AN EXAM ROOM LIGHT IN ROOM 1A-104 WAS MISSING FROM THE ORIGINAL DOCUMENTS, AND WA… |
| Mod SA169· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-06 | +$8,726 | $56,404,123 | TO MODIFY THE CONDENSER WATER PUMP CONTROL SEQUENCE DUE TO A DESIGN ERROR. |
| Mod SA170· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-06 | +$21,094 | $56,425,217 | TO ADD A FOURTH LIGHT FOR TWO EXTERIOR SIGNS, AND TO ADD FOUR LUMINAIRES AT EACH OF THE OTHER TWO EXTERIOR SIG… |
| Mod SA176· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-06 | +$35,458 | $56,460,675 | VARIOUS OWNER-FURNISHED EQUIPMENT REQUIRED MODIFICATIONS OF THE POWER. THE URINALYSIS AREA OF ROOM 1B-106 WAS… |
| Mod SA171· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$10,996 | $56,471,671 | TO RELOCATE THE FIRE SPRINKLER SYSTEM DUE TO THE MODIFICATIONS TO THE CANTEEN SKYLIGHTS AS WELL AS MODIFY THE… |
| Mod SA172· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$14,670 | $56,486,341 | THE CONTRACT DOCUMENTS STATE WATER IS AVAILABLE AT NO COST TO THE CONTRACTOR AND IS IN ERROR. DUE TO THIS FAC… |
| Mod SA173· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$19,713 | $56,506,054 | THE IRRIGATION SYSTEM TIMER/CONTROLLER WAS DESIGNED TO BE INSTALLED INSIDE THE CENTRAL ENERGY PLANT CONTROL RO… |
| Mod SA174· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$10,918 | $56,516,972 | THE THICKNESS OF STONE VENEER MATERIAL STATED IN THE CONTRACT DOCUMENTS WAS LESS AND SURFACE FINISH WAS ROUGHE… |
| Mod SA175· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$15,457 | $56,532,429 | SEVERAL PLUMBING INSTALLATION AND THE HVAC INSTALLATION MODIFICATIONS REQUIRED ADDITIONAL WORK BY THE GENERAL… |
| Mod SA177· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-11 | +$9,877 | $56,542,306 | THE CEILING-MOUNTED EXIT SIGNS AT CORRIDOR INTERSECTIONS WERE SHOWN TO BE LOCATED SUCH THAT THEY PARTIALLY BLO… |
| Mod SA178· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-11 | +$15,638 | $56,557,944 | THE CONTRACT DRAWINGS SHOW THE BOILER STACKS TERMINATING AT 4'-0" ABOVE THE ROOF. THIS SECTION OF ROOF IS INT… |
| Mod SA116· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-14 | −$275,000 | $56,282,944 | TO PROVIDE RESTITUTION FOR NON-COMPLIANT/FOREIGN ELECTRICAL FITTINGS TO BE INSTALLED IN THE BUILDING OF THE NE… |
| Mod SA166· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-24 | +$6,557 | $56,289,501 | THE GOVERNMENT'S RETAINED ARCHITECT ENGINEER MODIFIED SEVERAL DETAILS TO THE CURTAIN WALL DUE TO DESIGN ERRORS… |
| Mod SA149· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-25 | +$15,083 | $56,304,584 | THE GOVERNMENT'S ARCHITECT ENGINEER REQUESTED EXPOSED COLORED CONCRETE FOR SITE PLANTERS AND EXTERIOR COLUMN B… |
| Mod SA150· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-25 | +$16,295 | $56,320,879 | THE GOVERNMENT'S RETAINED ARCHITECT CHANGED THE TRAVERTINE STONE PANEL TO GRANITE DUE TO LIMITED COLOR SELECTI… |
| Mod SA163· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-25 | +$31,874 | $56,352,753 | THE VAMC REQUESTED FOR THE CANTEEN BE MODIFIED TO INCLUDE A COFFEE DISTRIBUTION AREA FOR PATIENT CARE. |
| Mod SA179· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-25 | +$59,050 | $56,411,803 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA180· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-01 | +$52,051 | $56,463,854 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA181· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-01 | +$54,254 | $56,518,108 | THE VAMC REQUESTED A CHANGE TO THE CONTRACT DOCUMENTS TO SUPPORT THE GOVERNMENT PURCHASED AND INSTALLED RADIO… |
| Mod SA078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-08 | +$25,000 | $56,543,108 | TO DELETE CONCRETE SEALER AND ADD TRAFFIC COATING TO PENTHOUSE FLOORS. DELETE AND SIMPLIFY SPECIFIC INTERIOR… |
| Mod SA167· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-08 | +$27,579 | $56,570,687 | DOOR VISION PANELS WERE ADDED IN SOME DOORS FOR OCCUPANT SAFE EXITING. DOOR VISION PANELS WERE DELETED FOR PR… |
| Mod CO01J· CHANGE ORDER | 2011-12-14 | +$50,000 | $56,620,687 | THE RADIOLOGY ROOMS WERE ORIGINALLY DESIGNED AND BID WITHOUT THE DETAILS REQUIRED FOR INSTALLING AND INTERFACI… |
| Mod CO01L· CHANGE ORDER | 2011-12-14 | +$15,000 | $56,635,687 | DURESS ALARMS WERE REQUESTED PRIMARILY IN ADDITIONAL AREAS OF THE MENTAL HEALTH DEPARTMENT BY VA POLICE BASED… |
| Mod CO01O· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-20 | +$1,129 | $56,636,816 | NECESSARY HVAC WORK INCLUDING ADDRESSING VARIOUS MECHANICAL REBALANCING IN THE SPD AREA AND RF HVAC ADJUSTMENT… |
| Mod SA155· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-23 | +$205,569 | $56,842,385 | THE VAMC PERSONNEL QUESTIONED ROOM SIZE FOR THE SPD STEAM GENERATION EQUIPMENT ROOM WAS NOT ADEQUATELY SIZED F… |
| Mod SA165· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-28 | +$23,457 | $56,865,842 | TO ADD CONTOURS/BERMS NOT SHOWN ON THE GRADING DRAWINGS, TO RAISE ELEVATION OF ROYAL PALM TREES' ROOT BALLS AB… |
| Mod CO01I· CHANGE ORDER | 2012-01-03 | +$95,424 | $56,961,266 | DURING A REVIEW OF THE GOVERNMENT PURCHASED CONTRACTOR INSTALLED BIOLOGICAL CABINET IN ROOM 1B-107A, IT WAS NO… |
| Mod SA182· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-03 | +$10,825 | $56,972,091 | THE MDF ROOM THAT WAS DESIGNED TO HOUSE THE PBX TELEPHONE EQUIPMENT WAS DESIGNED WITH POWER REQUIREMENTS FOR T… |
| Mod CO01M· CHANGE ORDER | 2012-01-16 | +$35,000 | $57,007,091 | ADDITIONAL SECURITY CAMERAS FOR VIDEO SURVEILLANCE WERE REQUESTED IN ADDITIONAL AREAS OF THE MENTAL HEALTH ARE… |
| Mod CO01N· CHANGE ORDER | 2012-01-16 | +$40,000 | $57,047,091 | ADDITIONAL ACCESS CONTROL DEVICES, CARDREADERS, AND ASSOCIATED HARDWARD WERE REQUESTED IN ADDITIONAL AREAS OF… |
| Mod SA183· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-16 | +$14,440 | $57,061,531 | THE FIRE ALARM MESSAGE THAT IS ANNOUNCED WHEN AN INCIDENT OCCURS WAS SPECIFIED TO ANNOUNCE ONLY THE "BUILDING,… |
| Mod CO01K· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-20 | −$49,033 | $57,012,498 | VAMC PREFERS TO INSTALL SPECIFIC EQUIPMENT THAT WAS INCLUDED IN THE GC CONTRACT. |
| Mod CO01P· CHANGE ORDER | 2012-01-20 | +$3,421 | $57,015,919 | VERTICAL SURFACED MOUNTED, EXPOSED CONDUIT IS SHOWN INSIDE DATA CLOSET 1A-208 ON SHEET TJ-101D; IT IS ACCEPTAB… |
| Mod CO01Q· CHANGE ORDER | 2012-01-20 | +$11,227 | $57,027,146 | FIELD MODIFICATION OF THE LIGHTING WAS REQUESTED BY THE VA ARCHITECT TO INCREASE LIGHTING IN AREAS OF PUBLIC R… |
| Mod CO01R· CLOSE OUT | 2012-01-20 | +$12,538 | $57,039,684 | THE CONTRACTOR PROPOSED SUBSTITUTING PLASTIC COVER PLATES FOR ELECTRICAL DEVICES SUCH AS LIGHT SWITCHES AND EL… |
| Mod CO01S· CHANGE ORDER | 2012-02-03 | +$1,841 | $57,041,525 | THE EMERGENCY OVERFLOW ROOF DRAINS ON THE CLINIC AND D&T ROOFS HAVE A TOP ELEVATION THAT IS NOT SUFFICIENTLY H… |
| Mod CO01T· CHANGE ORDER | 2012-02-13 | +$20,459 | $57,061,984 | THE VAMC REQUESTED THAT THE WALK-IN REFRIGERATOR AND SIX OTHER REFRIGERATORS USED FOR STORAGE OF PHARMACEUTICA… |
| Mod CO01U· CHANGE ORDER | 2012-02-17 | +$3,780 | $57,065,764 | CABLE BARRIERS TO RESTRAIN AUTOMOBILES FROM ROLLING INTO THE DEEP RETENTION PONDS WERE REQUESTED BY THE VA POL… |
| Mod CO01V· CHANGE ORDER | 2012-02-17 | +$1,898 | $57,067,662 | ADDITIONAL ROOF COPING DETAILS WERE PROVIDED BY THE VA ARCHITECT DURING CONSTRUCTION TO CLARIFY AND SUPPLEMENT… |
| Mod CO01W· CHANGE ORDER | 2012-02-17 | +$17,560 | $57,085,222 | DURING INITIAL TRAINING AND TESTING OF THE CHILLED WATER SYSTEM IT WAS NOTICED THERE WAS NO ACCESS TO CHILLER… |
| Mod CO01X· CHANGE ORDER | 2012-02-17 | +$25,454 | $57,110,676 | THE HEAT LOADINGS AND HVAC SYSTEM IN THE CT AND MRI ROOMS OF RADIOLOGY AREA CHANGED FROM THE DESIGN ASSUMPTION… |
| Mod CO01Y· CHANGE ORDER | 2012-02-17 | +$5,265 | $57,115,941 | THE CORBETT ROAD ENTRANCE DRIVEWAY INTERSECTION FLOODS THE ROADWAY DURING RAINY CONDITIONS, PRESENTING A DRIVI… |
| Mod CO01Z· CHANGE ORDER | 2012-02-17 | +$3,646 | $57,119,587 | NECESSARY ADDITIONAL HVAC WORK INCLUDING ADDRESSING VARIOUS MECHANICAL REBALANCING IN THE SPD AREA AND RF HVAC… |
| Mod CO02A· CHANGE ORDER | 2012-02-17 | +$3,569 | $57,123,156 | TWO FIRE ALARM EQUIPMENT PANELS WERE ORIGINALLY LOCATED IN THE OPERATING ROOMS WORK CORE AND WERE SURFACE-MOUN… |
| Mod SA184· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-17 | +$4,964 | $57,128,120 | THE VA MEDICAL CENTER PERSONNEL REQUESTED A DROP FOR COMPRESSED AIR AND DI WATER BE ADDED TO ROOM 2B-182. |
| Mod SA185· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-17 | +$1,802 | $57,129,922 | THE VA REQUESTED A FLOOD LIGHT TO ILLUMINATE THE FLAGS DURING PERIODS OF LIMITED DAYLIGHT, TO REPLACE THE POLE… |
| Mod SA143· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-29 | +$73,709 | $57,203,631 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA186· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-29 | +$8,408 | $57,212,039 | THE CONTRACT DOCUMENTS STATE WATER IS AVAILABLE AT NO COST TO THE CONTRACTOR AND IS IN ERROR. DUE TO THIS FAC… |
| Mod SA187· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-29 | +$59,947 | $57,271,986 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod CO02B· CHANGE ORDER | 2012-03-06 | +$2,910 | $57,274,896 | MAKEUP AIR IS REQUIRED IN THE CEP CHILLER ROOM IF THE REFRIGERANT EXHAUST SYSTEM IS EVER ACTIVATED, AND THE A/… |
| Mod SA188· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-07 | +$46,475 | $57,321,371 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA189· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$7,641 | $57,329,012 | THE CONTRACT DOCUMENTS STATE WATER IS AVAILABLE AT NO COST TO THE CONTRACTOR AND IS IN ERROR. DUE TO THIS FAC… |
| Mod SA190· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$79,589 | $57,408,601 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA191· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$2,068 | $57,410,669 | THE SOUTH FLORID WATER AMANAGEMENT DISTRICT (SFWMD) INSPECTED THE SITE STORM WATER DRAINAGE SYSTEMS AND ADVISE… |
| Mod SA192· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$56,832 | $57,467,501 | THE CONTRACT DOCUMENTS STATE ELECTRICITY IS AVAILABLE AT NO COST TO THE CONTRACTOR IS IN ERROR. THE FACILITY… |
| Mod SA193· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$1,994 | $57,469,495 | THE GENERAL CONTRACTOR AND SUBCONTRACTOR ADDED ISOLATION VALVES IN THE IRRIGATION SYSTEM PIPING TO AID IN THEI… |
| Mod SA194· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-08 | +$3,185 | $57,472,680 | THE GENERAL CONTRACTOR AGREED TO PURCHASE ON VA'S BEHALF SOME IMMEDIATELY-REQUIRED PUNCHLIST INSPECTION SUPPLI… |
| Mod CO02C· CHANGE ORDER | 2012-04-11 | +$19,984 | $57,492,664 | THE MICROBIOLOGY HOOD EXHAUST SYSTEM IS REQUIRED TO EXHAUST AT THE HIGHEST POINT OF THE CLINIC ROOFS, AND TO P… |
| Mod SA196· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-11 | +$6,021 | $57,498,685 | ADDITIONAL CEILING ACCESS DOORS (12) MADE OF STAINLESS STEEL ARE REQUIRED IN THE OPERATING ROOM CEILINGS TO PR… |
| Mod CO02E· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-12 | +$4,939 | $57,503,624 | PROVIDE RESPONSES AND COMPENSATION FOR UNSOLICITED REQUESTS FOR MINOR WORK DESCRIBED IN RFI REPSONSES #583 AND… |
| Mod CO02D· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-16 | +$19,297 | $57,522,921 | THE ELECTRICAL DISTRIBUTION CIRCUIT DESIGNED TO SUPPLY ELECTRICAL POWER TO THE UNINTERRUPTIBLE POWER SUPPLY (U… |
| Mod CO02F· CHANGE ORDER | 2012-04-18 | +$40,689 | $57,563,610 | BED DOCKER CIRCUITS WERE INITIALLY DETERMINED TO BE DESIGNED IN ACCORDANCE WITH FLORIDA BUILDING CODE, BUT WER… |
| Mod CO02G· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-18 | +$14,138 | $57,577,748 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod CO02H· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$9,220 | $57,586,968 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod CO02I· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$19,844 | $57,606,812 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod CO02J· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$16,959 | $57,623,771 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod CO02K· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$15,027 | $57,638,798 | PROVIDE ELECTRICAL COORDINATION DETAILS AND INSTRUCTIONS FOR INSTALLING VARIOUS MISCELLANEOUS SINKS, WATER TRE… |
| Mod CO02L· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$8,246 | $57,647,044 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod CO02M· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$15,065 | $57,662,109 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod SA198· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-14 | +$9,005 | $57,671,114 | THE ORIGINALLY-PERMITTED AND DRILLED WELL DID NOT PROVIDE WATER AT AN ADEQUATE RATE TO SATISFY THE IRRIGATION… |
| Mod SA195· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-16 | +$3,691 | $57,674,805 | THE GENERAL CONTRACTOR SUBMITTED AN UNSOLICITED REQUEST FOR PAYMENT FOR WORK ALREADY COMPLETED FOR TWO UNANTIC… |
| Mod SA197· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-16 | +$7,814 | $57,682,619 | CLEAR ANODIZED PARAPET COPING MATERIAL WAS SELECTED DURING THE SUBMITTAL PROCESS TO MATCH THE CURTAIN WALL AT… |
| Mod CO02N· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-24 | +$11,061 | $57,693,680 | FOLLOWING BUILDING CUSTODY TRANSFER TO THE VAMC, ADDITIONAL TIME WAS REQUIRED FOR THE VAMC VISN 8 CONTRACTING… |
| Mod CO02O· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-24 | +$8,075 | $57,701,755 | FOLLOWING BUILDING CUSTODY TRANSFER TO THE VAMC, ADDITIONAL TIME WAS REQUIRED FOR THE VAMC TO POST AND SOLICIT… |
| Mod CO02P· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-25 | +$3,914 | $57,705,669 | DURING FUNCTIONAL TESTING OF THE FIRE ALARM SYSTEM, THE VAMC NOTED A LIMITATION OF THE INSTALLED FIRE ALARM PA… |
| Mod SA199· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-31 | +$385 | $57,706,054 | THE EMERGENCY OVERFLOW ROOF DRAINS ON THE CLINIC AND D&T ROOFS HAVE A TOP ELEVATION THAT IS NOT SUFFICIENTLY H… |
| Mod CO02Q· CHANGE ORDER | 2012-06-11 | +$2,054 | $57,708,108 | DURING A BUILDING WALK THROUGH WITH THE LOCAL VA PERSONNEL IT WAS NOTICED THAT THE ROOM PRESSURE MONITOR FOR N… |
| Mod SA200· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$4,569 | $57,712,677 | NECESSARY HVAC WORK INCLUDING ADDRESSING VARIOUS MECHANICAL REBALANCING IN THE SPD AREA AND RF HVAC ADJUSTMENT… |
| Mod SA201· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$17,339 | $57,730,016 | THE VAMC REQUESTED THAT THE WALK-IN REFRIGERATOR AND SIX OTHER REFRIGERATORS USED FOR STORAGE OF PHARMACEUTICA… |
| Mod SA204· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$298 | $57,730,314 | ADDITIONAL ROOF COPING DETAILS WERE PROVIDED BY THE VA ARCHITECT DURING CONSTRUCTION TO CLARIFY AND SUPPLEMENT… |
| Mod SA205· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$4,525 | $57,734,839 | BED DOCKER CIRCUITS WERE INITIALLY DETERMINED TO BE DESIGNED IN ACCORDANCE WITH FLORIDA BUILDING CODE, BUT WER… |
| Mod SA206· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$1,080 | $57,735,919 | A SECTION OF WALL ON LEVEL 2 WAS NEEDED TO INFILL A SPACE BETWEEN THE DOUBLE CORRIDOR DOORS AND AN EXTERIOR CO… |
| Mod SA207· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-19 | +$2,841 | $57,738,760 | THE VAMC DENTAL STAFF REQUESTED ADDITIONAL OXYGEN AND DENTAL VACUUM LINES BE INSTALLED IN VARIOUS ROOMS OF THE… |
| Mod SA203· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-20 | +$1,586 | $57,740,346 | OFFICE SUPPLIES TO SUPPORT THE PUNCH LIST INSPECTION AND RE-INSPECTION PROCESS WERE REQUIRED ON SHORT NOTICE A… |
| Mod SA212· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-22 | +$2,538 | $57,742,884 | FOLLOWING BUILDING CUSTODY TRANSFER TO THE VAMC, ADDITIONAL TIME WAS REQUIRED FOR THE VAMC CONTRACTING OFFICE… |
| Mod SA215· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-22 | −$141 | $57,742,743 | THE MICROBIOLOGY HOOD EXHAUST SYSTEM IS REQUIRED TO EXHAUST AT THE HIGHEST POINT OF THE CLINIC ROOFS, AND TO P… |
| Mod SA202· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-19 | −$3,424 | $57,739,319 | THE CITY OF CAPE CORAL DOES NOT REQUIRED CATHODIC PROTECTION FOR THEIR WATER LINES. THEREFORE CATHODIC PROTEC… |
| Mod CO02R· CHANGE ORDER | 2012-07-20 | +$8,469 | $57,747,788 | THE VAMC REQUESTED A PERSON LIFT FOR A TOILET ROOM (ROOM 1A-143) TOWARDS THE END OF THE PROJECT AS ACCOMMODATI… |
| Mod SA210· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-20 | +$4,500 | $57,752,288 | THE ORIGINAL PLANS AND SPECIFICATIONS DID NOT INDICATE ANY SILLS TO FINISH THREE EXTERIOR DOORS. THE SILL DET… |
| Mod SA221· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-20 | +$25,966 | $57,778,254 | THE PACKAGE CHILLER UNIT ON THE D&T ROOF SERVING THE ORS IS LACKING AN ACCESS PLATFORM AROUND THE PERIMETER AN… |
| Mod SA209· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-23 | +$1,342 | $57,779,596 | REIMBURSE THE CONTRACTOR FOR THE COST TO PURCHASE THE COPYRIGHT OF THE CUSTOM DIGITAL IMAGES FROM ISTOCKPHOTO… |
| Mod SA218· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-23 | +$9,637 | $57,789,233 | THE AIR FLOWS AND COOLING REQUIRED IN THE CT WAS NOT ADEQUATE IN THE ORIGINAL DESIGN. ASI #177 REVISES THE HV… |
| Mod SA219· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-23 | −$252 | $57,788,981 | DURING FUNCTIONAL TESTING OF THE FIRE ALARM SYSTEM, THE VAMC NOTED A LIMITATION OF THE INSTALLED FIRE ALARM PA… |
| Mod SA211· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-25 | +$2,805 | $57,791,786 | THE ELECTRICAL DISTRIBUTION CIRCUIT DESIGNED TO SUPPLY ELECTRICAL POWER TO THE UNINTERRUPTIBLE POWER SUPPLY (U… |
| Mod SA216· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-25 | +$6,000 | $57,797,786 | GRADING RESULTED IN AN ELEVATION DIFFERENCE BETWEEN THE BOTTOM OF THE STONE VENEER ON THE BARRIER WALLS AND TH… |
| Mod SA220· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$13,192 | $57,810,978 | VAMC WAS UNABLE TO GET NEW LANDSCAPE MAINTENANCE CONTRACT THROUGH VAMC CONTRACTING OFFICE IN TIME, AND REQUEST… |
| Mod SA222· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$7,055 | $57,818,033 | DURESS ALARMS WERE REQUESTED PRIMARILY IN ADDITIONAL AREAS OF THE MENTAL HEALTH DEPARTMENT BY VA POLICE BASED… |
| Mod SA223· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$8,845 | $57,826,878 | AFTER REVIEW OF THE SECURITY DRAWINGS WITH THE VA POLICE, THE VA POLICE REQUESTED ADDITIONAL CAMERA, RELOCATED… |
| Mod SA224· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$6,478 | $57,833,356 | DURING CONSTRUCTION OF THIS BUILDING, THE VA CHANGED ACCESS CARD READER REQUIREMENTS. |
| Mod SA225· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-26 | +$16,704 | $57,850,060 | THE VAMC REQUESTED ADDITIONAL BOOM SUPPORT IN ROOM 2B-174 TO ACCOMMODATE ADDITIONAL EQUIPMENT. |
| Mod CO02S· CLOSE OUT | 2012-07-27 | +$2,000 | $57,852,060 | DURING THE INSTALLATION OF THE TEMPORARY SECURITY DESK AND AGAIN FOR THE PERMANENT SECURITY CONSOLE IN THE VA… |
| Mod SA226· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-08 | +$31,730 | $57,883,790 | SEVEN OPERATING ROOMS EACH HAVE TWO ELECTRICAL PANELBOARD COVERS (14 TOTAL COVERS) THAT ARE PAINTED STEEL AND… |
| Mod SA227· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-22 | −$11,465 | $57,872,325 | THE EXTERIOR LIGHTING WAS REVISED AT ALL BUILDING ENTRANCES TO REMOVE BOLLARD TOP LIGHTING AND ADD POLE MOUNTE… |
| Mod SA230· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-22 | +$1,608 | $57,873,933 | DURING BUILDING CONSTRUCTION NUMEROUS ELECTRICAL ISSUES WERE ASKED BY THE GENERAL CONTRACTOR. THE ANSWERS GEN… |
| Mod SA231· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-22 | +$8,450 | $57,882,383 | DURING THE COURSE OF CONSTRUCTION THE GENERAL CONTRACTOR ISSUED SEVERAL RFIS RELATING TO ELECTRICAL WORK. THE… |
| Mod SA232· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-22 | +$13,192 | $57,895,575 | VAMC WAS UNABLE TO GET NEW LANDSCAPE MAINTENANCE CONTRACT THROUGH VAMC CONTRACTING OFFICE IN TIME, AND REQUEST… |
| Mod SA233· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-22 | +$14,971 | $57,910,546 | DURING THE COURSE OF THE PROJECT, THE GENERAL CONTRACTOR (GC) ISSUED SEVERAL RFI'S REQUESTING CLARIFICATION OF… |
| Mod SA234· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-27 | +$19,213 | $57,929,759 | DURING CONSTRUCTION IT WAS NOTICED THAT THE LENGTH OF RUNS FOR CAT 6 CABLING EXCEEDED THE DISTANCE LIMITATION… |
| Mod SA235· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-27 | +$18,952 | $57,948,711 | THE DESIGN DRAWINGS FOR ELECTRICAL WERE NOT PROPERLY COORDINATED RESULTING IN ADDITIONAL WORK BY THE ELECTRICA… |
| Mod SA237· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-27 | +$9,853 | $57,958,564 | THE ELECTRICAL DRAWINGS WERE MISSING SEVERAL LOCATIONS FOR POWER. THE VARIOUS RFI RESPONSES HEREIN PROVIDED T… |
| Mod SA239· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-07 | +$39,054 | $57,997,618 | DURING CONSTRUCTION, THE VAMC SUSPECTED THAT SOME OF THE HVAC DUCTS MIGHT HAVE HAD DUST OR DEBRIS GET INSIDE.… |
| Mod SA214· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-17 | +$14,074 | $58,011,692 | POTABLE WATER IS REQUIRED FOR THE CONSTRUCTION TRAILERS AND FOR STARTUP AND INITIAL OPERATION OF THE NEW CLINI… |
| Mod SA217· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-17 | +$40,015 | $58,051,707 | THE FACILITY IS NOT CURRENTLY FULLY STAFFED AND REQUESTED THE GC CONTINUE ROUTINE MECHANICAL MAINTENANCE ON MA… |
| Mod CO02T· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-24 | +$95,518 | $58,147,225 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod SA213· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-29 | +$140,827 | $58,288,052 | ELECTRIC POWER IS REQUIRED FOR THE CONSTRUCTION TRAILERS AND FOR STARTUP AND INITIAL OPERATION OF THE NEW CLIN… |
| Mod SA228· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-04 | +$75,354 | $58,363,406 | THE EXTERIOR LIGHTING WAS REVISED AT ALL BUILDING ENTRANCES TO REMOVE BOLLARD TOP LIGHTING AND ADD POLE MOUNTE… |
| Mod CO02W· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$6,855 | $58,370,261 | THE A&E REVISED SEVERAL AIR FLOWS IN THE RADIOLOGY AREA. THE A&E DID NOT REVISE THE FAN SIZE OR TOTAL AIR FLO… |
| Mod SA229· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$25,177 | $58,395,438 | A REVIEW OF ELECTRICAL DRAWINGS BY THE GENERAL CONTRACTOR GENERATED SEVERAL ELECTRICAL RELATED RFI'S TO ADD EL… |
| Mod SA240· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$1,770 | $58,397,208 | THE APPROVED SUBMITTAL FOR PROSTHETICS STORAGE CABINETS INDICATES THEY SHOULD BE MECHANICALLY ASSISTED. |
| Mod SA241· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$17,213 | $58,414,421 | CONTRACTOR RECEIVED COORDINATION INSTRUCTIONS FROM THE VA FROM A/E FOR ELECTRICAL WORK, SOME OF WHICH REPRESEN… |
| Mod SA242· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$18,978 | $58,433,399 | PROVIDE ELECTRICAL COORDINATION DETAILS AND INSTRUCTIONS FOR INSTALLING VARIOUS MISCELLANEOUS SINKS, WATER TRE… |
| Mod SA243· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$5,665 | $58,439,064 | DURING INSTALLATION OF THE TEMPORARY SECURITY DESK AND AGAIN FOR THE PERMANENT SECURITY CONSOLE IN THE VA POLI… |
| Mod SA244· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$16,322 | $58,455,386 | OVER THE COURSE OF THE PROJECT, THE GENERAL CONTRACTOR ISSUED SEVERAL ELECTRICAL RELATED RFI'S. THE RESPONSE… |
| Mod SA245· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$1,708 | $58,457,094 | THE LOCKER ROOMS 1B-186 AND 1B-187 WERE NOT SIZED TO MATCH THE INSTALLED LOCKERS. REVISIONS TO THE WALLS WERE… |
| Mod SA246· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$2,830 | $58,459,924 | THE A&E ISSUED MULTIPLE ASI'S, IN WHICH THE REO ISSUED MULTIPLE D#S 037-144 TO THE GENERAL CONTRACTOR TO PROVI… |
| Mod SA247· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$2,346 | $58,462,270 | DURING A BUILDING WALK THROUGH WITH THE LOCAL VA PERSONNEL IT WAS NOTICED THAT THE ROOM PRESSURE MONITOR FOR N… |
| Mod SA249· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-06 | +$10,650 | $58,472,920 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod SA248· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-10 | +$4,793 | $58,477,713 | DURING A BUILDING WALK THROUGH WITH THE LOCAL VA PERSONNEL IT WAS NOTICED THAT THE ROOM PRESSURE MONITOR FOR N… |
| Mod SA251· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-17 | +$1,551 | $58,479,264 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod SA253· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-17 | +$2,047 | $58,481,311 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod SA254· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-17 | +$6,720 | $58,488,031 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod SA256· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-22 | +$2,882 | $58,490,913 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01U DATED 02/17/2012 AND ISSUED FOR $3,780.00; THIS DEFINIZATION INC… |
| Mod SA257· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-22 | +$17,735 | $58,508,648 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01U DATED 02/17/2012 AND ISSUED FOR $3,780.00; THIS DEFINIZATION INC… |
| Mod SA258· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-22 | +$10,269 | $58,518,917 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01U DATED 02/17/2012 AND ISSUED FOR $3,780.00; THIS DEFINIZATION INC… |
| Mod SA238· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-24 | +$21,610 | $58,540,527 | THE ELECTRICAL DRAWINGS WERE MISSING SEVERAL LOCATIONS FOR POWER. THE VARIOUS RFI RESPONSES HEREIN PROVIDED T… |
| Mod SA259· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-25 | +$28,277 | $58,568,804 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01U DATED 02/17/2012 AND ISSUED FOR $3,780.00; THIS DEFINIZATION INC… |
| Mod SA255· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-02 | +$14,865 | $58,583,669 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01U DATED 02/17/2012 AND ISSUED FOR $3,780.00; THIS DEFINIZATION INC… |
| Mod SA260· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-02 | +$12,291 | $58,595,960 | THIS CONTRACT MODIFICATION DEFINITIZES CO-02A DATED 02/17/2012 AND ISSUED FOR $3,569.00; THIS DEFINIZATION INC… |
| Mod SA261· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-02 | +$8,552 | $58,604,512 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01D DATED 03/31/2012 AND ISSUED FOR $2,445.00; THIS DEFINIZATION INC… |
| Mod SA263· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-27 | +$12,500 | $58,617,012 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01D DATED 03/31/2012 AND ISSUED FOR $2,445.00; THIS DEFINIZATION INC… |
| Mod SA264· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-27 | +$37,210 | $58,654,222 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01D DATED 03/31/2012 AND ISSUED FOR $2,445.00; THIS DEFINIZATION INC… |
| Mod CO02V· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-28 | +$5,660 | $58,659,882 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod CO02X· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-28 | +$25,000 | $58,684,882 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod SA266· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-05 | +$7,589 | $58,692,471 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod SA269· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-05 | +$2,863 | $58,695,334 | SEVERAL ASLS WERE ISSUED CHANGING AIR FLOWS IN THE RADIALOGY AREA. HOWEVER, THESE RFIS DID NOT ACCOUNT FOR RES… |
| Mod CO02Z· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-21 | +$20,000 | $58,715,334 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod CO02Y· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-28 | +$19,000 | $58,734,334 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod SA271· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-07 | +$2,621 | $58,736,955 | SEVERAL ASLS WERE ISSUED CHANGING AIR FLOWS IN THE RADIALOGY AREA. HOWEVER, THESE RFIS DID NOT ACCOUNT FOR RES… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-16 | +$3,411 | $58,740,366 | SA-272 INSTALL SOFTWARE ON CODE BLUE COMPUTER - AT VA LEE COUNTY OPC, CAPE CORAL, FL - THE VAMC PROVIDED A COD… |
| Mod CO03A· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-17 | +$5,351 | $58,745,717 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
| Mod SA267· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-28 | +$20,631 | $58,766,348 | LEE COUNTY OUTPATIENT CLINIC, FORT MEYERS, FL TOTAL CONTRACT PRICE IS INCREASED BY $20,631.00 AND 0 CALENDAR… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-31 | +$2,206 | $58,768,554 | SA-270 ADD MED GAS SAFETY SIGNS - VA LEE COUNTY OPC, FL - THE VAMC REQUESTED ADDITIONAL MEDICAL GAS DANGER AND… |
| Mod P00004· CHANGE ORDER | 2013-02-14 | +$15,000 | $58,783,554 | CO-03B - DOOR HARDWARE COORDINATION LEVEL - VA LEE COUNTY OPC, CAPE CORAL, FL - A/E REVIEW REVEALED DEFICIENCI… |
| Mod P00007· CHANGE ORDER | 2013-02-14 | +$16,321 | $58,799,875 | CO-03B - DOOR HARDWARE COORDINATION LEVEL - VA LEE COUNTY OPC, CAPE CORAL, FL - A/E REVIEW REVEALED DEFICIENCI… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-19 | +$38,751 | $58,838,626 | SA-250 DEF CO-01J RADIOLOGY ROOMS, ELECTRICAL&NON-ARCHITECTURAL MODIFICATIONS |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-20 | +$19,171 | $58,857,797 | SA-277 ERV ADDITION TO RADIOLOGY - AT VA LEE COUNTY OUTPATIENT CLINIC, CAPE CORAL, FL |
| Mod P00005· CHANGE ORDER | 2013-02-22 | +$1,366 | $58,859,163 | CO-03B - SIDEWALK EXTENSION FOR IBC EGRESS COMPLIANCE - VA LEE COUNTY OPC, CAPE CORAL, FL - A STATEMENT OF CON… |
| Mod P00013· CHANGE ORDER | 2013-03-12 | +$10,000 | $58,869,163 | CO-03D - SIDEWALK SETTLEMENT REMEDIATION - VA LEE COUNTY OPC, CAPE CORAL, FL - THE PEDESTRIAN SIDEWALK ALONG T… |
| Mod SA262· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-21 | +$615 | $58,869,778 | THIS CONTRACT MODIFICATION DEFINITIZES CO-01D DATED 03/31/2012 AND ISSUED FOR $2,445.00; THIS DEFINIZATION INC… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-05 | −$1,064 | $58,868,714 | SA-265 DEF CO-02V ROOM 1A-219 COOLING - BADGING SECURITY AT VALC OPC AT CAPE CORAL, FL |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-15 | −$1,650 | $58,867,064 | SA-265 DEF CO-02V ROOM 1A-219 COOLING - BADGING SECURITY AT VALC OPC AT CAPE CORAL, FL |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-15 | +$6,370 | $58,873,434 | SA-265 DEF CO-02V ROOM 1A-219 COOLING - BADGING SECURITY AT VALC OPC AT CAPE CORAL, FL |
| Mod P00018· CHANGE ORDER | 2013-04-24 | +$2,325 | $58,875,759 | SA-276 ELECTRICAL HARDWARE FOR D-070 AT LEE COUNTY OUTPATIENT CLINIC, CAPE CORAL, FL |
| Mod P00019· CHANGE ORDER | 2013-04-24 | −$549 | $58,875,210 | SA-278 DELETE UNDERCOUNTER ICE MAKER - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00023· CHANGE ORDER | 2013-04-29 | +$5,400 | $58,880,610 | SA-285 - INSTALL DX A/C UNIT FOR ELEVATOR ROOM COOLING - VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-30 | +$98,000 | $58,978,610 | SA-282 VARIOUS NEGOTIATED COR'S AT VALC OPC AT CAPE CORAL, FL - A GROUP OF 14 MISCELLANEOUS CORS THAT WERE SET… |
| Mod P00020· CHANGE ORDER | 2013-04-30 | −$7,699 | $58,970,911 | SA-280 DEF CO-02R AT LEE COUNTY OUTPATIENT CLINIC, CAPE CORAL, FL THIS CONTRACT MODIFICATION DEFINITIZES CO-02… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-30 | +$1,007 | $58,971,918 | SA-281 DEF CO-03A - SECURITY SYSTEM INDEPENDENT REVIEW TO CONFIRM COMPLIANCES AND IDENTIFY NON-COMPLIANCES WIT… |
| Mod P00022· CHANGE ORDER | 2013-04-30 | −$6,406 | $58,965,512 | SA-284 DEF CO-03B DOOR HARDWARE COORDINATION LEVEL 4 AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00017· CHANGE ORDER | 2013-05-02 | +$0 | $58,965,512 | SA-283 LIGHTING CONTROLS AT VALC OPC AT CAPE CORAL, FL. PROVIDE ALL WORK RELATED TO DOL-008&DOL-021. |
| Mod P00024· CHANGE ORDER | 2013-05-03 | +$7,454 | $58,972,966 | SA-275 STONE VENEER, XRAY DISCONNECT SWITCH, RE OFFICE SUPPLIES - MISCELLANEOUS FIELD ISSUES - AT VA LEE COUN… |
| Mod P00025· CHANGE ORDER | 2013-05-20 | +$5,767 | $58,978,733 | SA-288 REPLACE MED GAS AIR COMPRESSOR #3 - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00026· CHANGE ORDER | 2013-05-31 | +$81,895 | $59,060,628 | SA-287 DEFINITIZE CO-03D, SIDEWALK REPLACEMENT AT FRONT - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00031· CHANGE ORDER | 2013-05-31 | +$24,000 | $59,084,628 | CO-03E - LIGHTING CONTROL SYSTEM SUPPORT LEE COUNTY OUTPATIENT CLINIC, CAPE CORAL, FL |
| Mod P00028· CHANGE ORDER | 2013-06-03 | +$2,539 | $59,087,167 | SA-286 ADDITIONAL SIDEWALKS FOR EMERGENCY EGRESS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00029· CHANGE ORDER | 2013-06-04 | +$3,686 | $59,090,853 | SA-290 REPROGRAM MDF CRAC UNITS LEE COUNTY OUTPATIENT CLINIC, CAPE CORAL, FL |
| Mod P00030· CHANGE ORDER | 2013-06-04 | +$3,905 | $59,094,758 | SA-291 CANTEEN DOOR 1A-215B LOCKING MECHANISM - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00027· CHANGE ORDER | 2013-06-06 | +$13,712 | $59,108,470 | SA-289 ADD WET FIRE SPRINKLERS TO IT MDF ROOM - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00032· CHANGE ORDER | 2013-06-06 | −$10,634 | $59,097,836 | SA-293 DEF CO-02Y EXTRA SECURITY TRAINING - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00033· CHANGE ORDER | 2013-06-06 | −$5,000 | $59,092,836 | SA-294 DEF CO-02X RECERTIFY FIRE AND SMOKE SEALS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00034· CHANGE ORDER | 2013-06-06 | +$4,241 | $59,097,077 | SA-295 FINAL ELECTRIC BILL FOR RE OFFICE TRAILERS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00036· CHANGE ORDER | 2013-06-06 | +$8,936 | $59,106,013 | SA-292 INSTALL WIDER DOOR FOR VETERAN WITH OVERSIZE WHEELCHAIR ACCESS AT ATRIUM CORRIDOR TO TRAVEL CLERK - AT… |
| Mod P00037· CHANGE ORDER | 2013-06-06 | +$28,533 | $59,134,546 | SA-297 DEF CO-01K DELETE INSTALLATION OF VC EQUIPMENT FROM GC SCOPE OF WORK - AT VA LEE COUNTY OPC, CAPE CORAL… |
| Mod P00035· CHANGE ORDER | 2013-06-07 | +$11,534 | $59,146,080 | SA-296 REPLACE (2) MED GAS AIR COMPRESSORS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod SA273· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-17 | +$12,786 | $59,158,866 | SEVERAL ASLS WERE ISSUED CHANGING AIR FLOWS IN THE RADIALOGY AREA. HOWEVER, THESE RFIS DID NOT ACCOUNT FOR RES… |
| Mod P00039· CHANGE ORDER | 2013-07-19 | +$30,645 | $59,189,511 | SA-298 BOND PREMIUM - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00040· CHANGE ORDER | 2013-07-19 | +$0 | $59,189,511 | SA-299 MISC. ELECTRICAL RFIS # 504 THROUGH 568 - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00041· CHANGE ORDER | 2013-07-19 | +$27,227 | $59,216,738 | SA-300 BOND PREMIUM ADJUSTMENT FOR SUB CONTRACTOR - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00042· CHANGE ORDER | 2013-07-19 | +$0 | $59,216,738 | SA-301 REVISED SIGNAGE - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00043· CHANGE ORDER | 2013-07-19 | +$3,453 | $59,220,191 | SA-302 DEF CO-01Q RESTROOM LIGHT MODIFICATION - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00044· CHANGE ORDER | 2013-08-01 | +$3,678 | $59,223,869 | SA-303 SHOWER TILE SLOPING - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00045· CHANGE ORDER | 2013-08-14 | +$2,321 | $59,226,190 | SA-305 DEF CO-03E LIGHTING CONTROL SYSTEM TECH SUPPORT - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00046· CHANGE ORDER | 2013-08-14 | −$1,627 | $59,224,563 | SA-304 ADD MED GAS SIGNS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod P00038· CHANGE ORDER | 2013-09-20 | +$14,482 | $59,239,045 | SA-274 SPS-SPD RENOVATIONS&HVAC MODS - AT VA LEE COUNTY OPC, CAPE CORAL, FL |
| Mod SA252· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-17 | +$9,543 | $59,248,588 | THE GENERAL CONTRACTOR ISSUED SEVERAL RFI'S ELECTRICAL IN NATURE, THE RESPONSE TO WHICH CAUSED A CHANGE ON THE… |
| Mod CO02U· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-22 | +$1,977 | $59,250,565 | SEVERAL AREAS OF THE CLINIC HAVE BEEN IDENTIFIED THAT ARE NOT DESIGNED OR INSTALLED PER VA HVAC DESIGN MANUALS… |
Related awards · 2
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CLMLAQA7UR59)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA516C01082 | 516-BAY PINES · N054 · INSTALL OF PREFAB STRUCTURES | $6,790 | FY2010 |
Other recipients under Y142 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0060 | HOAR CONSTRUCTION, LLC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $1,056,046 | FY2009 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0058_3600_-NONE-_-NONE- · retrieved 2026-09-26.