Description
THIS CHANGE PROVIDES A LOWER COST ALTERNATIVE FOR WATER PROTECTION WHILE GIVING THE FACILITY A SYSTEM WITH WHICH THEY ARE ALREADY FAMILLIAR
Base award description: CONSTRUCTION OF ATLANTA PEDESTRIAN BRIDGE
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-05-04+$3,903,564= $3,903,564
- Mod CO01A2009-08-28+$27,000= $3,930,564
- Mod SA0012009-11-19+$6,474= $3,937,038
- Mod SA0022010-06-01+$8,862= $3,945,899
- Mod SA0062010-06-01+$11,913= $3,957,812
- Mod SA0082010-06-23+$1,414= $3,959,226
- Mod SA0072010-06-30+$8,361= $3,967,587
- Mod SA0032010-08-13+$8,055= $3,975,643
- Mod SA0042010-08-13+$2,414= $3,978,056
- Mod SA0052010-08-13+$1,533= $3,979,589
- Mod SA0092010-08-13-$27,000= $3,952,589
- Mod SA0112010-08-23+$2,355= $3,954,945
- Mod SA0102010-12-29-$6,258= $3,948,687
- Mod SA0122011-09-23-$32,477= $3,916,210
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-05-04 | +$3,903,564 | $3,903,564 | CONSTRUCTION OF ATLANTA PEDESTRIAN BRIDGE |
| Mod CO01A· CHANGE ORDER | 2009-08-28 | +$27,000 | $3,930,564 | PEDSETRIAN BRIDGE |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-19 | +$6,474 | $3,937,038 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-01 | +$8,862 | $3,945,899 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-01 | +$11,913 | $3,957,812 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-23 | +$1,414 | $3,959,226 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA SA-008 |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-30 | +$8,361 | $3,967,587 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-13 | +$8,055 | $3,975,643 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA SA-003 |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-13 | +$2,414 | $3,978,056 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA SA-004 |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-13 | +$1,533 | $3,979,589 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA SA-005 |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-13 | −$27,000 | $3,952,589 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-23 | +$2,355 | $3,954,945 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA, SA-011 |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | −$6,258 | $3,948,687 | PHASE 2, PEDESTRAIN BRIDGE, DECATUR, GA, SA-010 |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-23 | −$32,477 | $3,916,210 | THIS CHANGE PROVIDES A LOWER COST ALTERNATIVE FOR WATER PROTECTION WHILE GIVING THE FACILITY A SYSTEM WITH WHI… |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI L4FUJ4JYDAJ8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24824N0183 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $151,370 | FY2024 |
| 36C24823P1483 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F107 · ENVIRONMENTAL SYSTEMS PROTECTION- TOXIC AND HAZARDOUS SUBSTANCE ANALYSIS | $56,160 | FY2023 |
| 36C24823N0507 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $103,770 | FY2023 |
| 36C24822N0355 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F108 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL REMEDIATION | $115,000 | FY2022 |
| 36C24722P0324 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · N045 · INSTALLATION OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $0 | FY2022 |
| 36C24822N0183 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $54,345 | FY2022 |
Other recipients under AD64 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VACFM05A0054 | CANNON CORPORATION, THE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $25,116 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0040_3600_-NONE-_-NONE- · retrieved 2026-09-26.