Award recordCONTRACT

P.J. DICK INCORPORATED

PIID VA101CFMC0014· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2009· $78,412,168 net obligations· UEI NNNAEYQXKJ35· PA

Description

P00004/SA-232 - ADJUST VENT PIPING, CHECK ALL STEAM TRAPS, ADJUST RE-SET THE TANK FLOATS, REPAIR DAMAGED PUMP CONTROLLER.

Base award description: CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING

First action · last action
2008-11-12 · 2013-11-26
Transactions
268
First transaction's obligation
$75,802,000
Base + all options value (sum of deltas)
$78,412,208
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
3
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 268 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$78,412,168$0Base award · 2008-11-12 · this action $75,802,000 · running total $75,802,000Modification SA035 · 2010-01-11 · this action -$164,502 · running total $75,637,498Modification CO01R · 2010-03-04 · this action $276,000 · running total $75,913,498Modification SA054 · 2010-04-12 · this action -$32,000 · running total $75,881,498Modification SA058 · 2010-04-19 · this action -$875 · running total $75,880,623Modification SA062 · 2010-04-29 · this action -$164 · running total $75,880,459Modification SA064 · 2010-04-30 · this action -$3,000 · running total $75,877,459Modification CO02A · 2010-06-17 · this action $38,000 · running total $75,915,459Modification CO02B · 2010-06-17 · this action $14,100 · running total $75,929,559Modification CO02C · 2010-06-22 · this action $2,800 · running total $75,932,359Modification SA078 · 2010-06-30 · this action -$50,000 · running total $75,882,359Modification SA077 · 2010-07-01 · this action -$4,400 · running total $75,877,959Modification CO01M · 2010-09-18 · this action $47,395 · running total $75,925,354Modification CO01Q · 2010-09-18 · this action $6,129 · running total $75,931,483Modification CO01S · 2010-09-18 · this action $32,720 · running total $75,964,203Modification CO01T · 2010-09-18 · this action $18,200 · running total $75,982,403Modification CO01U · 2010-09-18 · this action $18,075 · running total $76,000,478Modification CO01V · 2010-09-18 · this action $59,700 · running total $76,060,178Modification CO01W · 2010-09-18 · this action $10,611 · running total $76,070,789Modification CO01X · 2010-09-18 · this action $11,888 · running total $76,082,677Modification CO01Y · 2010-09-18 · this action $39,886 · running total $76,122,563Modification CO01Z · 2010-09-18 · this action $6,325 · running total $76,128,888Modification CO02D · 2010-09-18 · this action $1,628 · running total $76,130,516Modification CO02E · 2010-09-18 · this action $5,000 · running total $76,135,516Modification CO02F · 2010-09-18 · this action $1,367 · running total $76,136,883Modification SA023 · 2010-09-18 · this action $2,782 · running total $76,139,665Modification SA025 · 2010-09-18 · this action $330 · running total $76,139,995Modification SA027 · 2010-09-18 · this action $5,500 · running total $76,145,495Modification SA028 · 2010-09-18 · this action $3,177 · running total $76,148,672Modification SA029 · 2010-09-18 · this action $3,313 · running total $76,151,985Modification SA030 · 2010-09-18 · this action $50,000 · running total $76,201,985Modification SA031 · 2010-09-18 · this action $550 · running total $76,202,535Modification SA032 · 2010-09-18 · this action $5,000 · running total $76,207,535Modification SA033 · 2010-09-18 · this action $0 · running total $76,207,535Modification SA034 · 2010-09-18 · this action $0 · running total $76,207,535Modification SA036 · 2010-09-18 · this action $1,169 · running total $76,208,704Modification SA037 · 2010-09-18 · this action $20,475 · running total $76,229,179Modification SA038 · 2010-09-18 · this action $14,823 · running total $76,244,002Modification SA039 · 2010-09-18 · this action $9,880 · running total $76,253,882Modification SA040 · 2010-09-18 · this action $8,000 · running total $76,261,882Modification SA041 · 2010-09-18 · this action $1,574 · running total $76,263,456Modification SA042 · 2010-09-18 · this action $2,367 · running total $76,265,823Modification SA043 · 2010-09-18 · this action $1,533 · running total $76,267,356Modification SA044 · 2010-09-18 · this action $2,919 · running total $76,270,275Modification SA045 · 2010-09-18 · this action $7,700 · running total $76,277,975Modification SA046 · 2010-09-18 · this action $19,446 · running total $76,297,421Modification SA047 · 2010-09-18 · this action $5,674 · running total $76,303,095Modification SA048 · 2010-09-18 · this action $57,800 · running total $76,360,895Modification SA049 · 2010-09-18 · this action $3,360 · running total $76,364,255Modification SA050 · 2010-09-18 · this action $7,805 · running total $76,372,060Modification SA051 · 2010-09-18 · this action $3,290 · running total $76,375,350Modification SA052 · 2010-09-18 · this action $18,400 · running total $76,393,750Modification SA053 · 2010-09-18 · this action $32,000 · running total $76,425,750Modification SA055 · 2010-09-18 · this action $1,400 · running total $76,427,150Modification SA056 · 2010-09-18 · this action $10,589 · running total $76,437,739Modification SA057 · 2010-09-18 · this action $28,488 · running total $76,466,227Modification SA059 · 2010-09-18 · this action $6,600 · running total $76,472,827Modification SA060 · 2010-09-18 · this action $2,846 · running total $76,475,673Modification SA061 · 2010-09-18 · this action $3,581 · running total $76,479,254Modification SA063 · 2010-09-18 · this action $4,000 · running total $76,483,254Modification SA065 · 2010-09-18 · this action $3,529 · running total $76,486,783Modification SA066 · 2010-09-18 · this action $0 · running total $76,486,783Modification SA067 · 2010-09-18 · this action $13,007 · running total $76,499,790Modification SA068 · 2010-09-18 · this action $0 · running total $76,499,790Modification SA069 · 2010-09-18 · this action $4,378 · running total $76,504,168Modification SA070 · 2010-09-18 · this action $1,150 · running total $76,505,318Modification SA071 · 2010-09-18 · this action $1,900 · running total $76,507,218Modification SA072 · 2010-09-18 · this action $3,771 · running total $76,510,989Modification SA073 · 2010-09-18 · this action $252 · running total $76,511,241Modification SA074 · 2010-09-18 · this action $3,790 · running total $76,515,031Modification SA075 · 2010-09-18 · this action $8,000 · running total $76,523,031Modification SA076 · 2010-09-18 · this action $17,000 · running total $76,540,031Modification SA079 · 2010-09-18 · this action $2,605 · running total $76,542,636Modification SA080 · 2010-09-18 · this action $35,000 · running total $76,577,636Modification SA081 · 2010-09-18 · this action $64,911 · running total $76,642,547Modification SA082 · 2010-09-18 · this action $0 · running total $76,642,547Modification SA083 · 2010-09-18 · this action $1,714 · running total $76,644,261Modification SA084 · 2010-09-18 · this action $3,500 · running total $76,647,761Modification SA085 · 2010-09-18 · this action $300 · running total $76,648,061Modification SA086 · 2010-09-18 · this action $4,153 · running total $76,652,214Modification SA087 · 2010-09-18 · this action $4,500 · running total $76,656,714Modification SA088 · 2010-09-18 · this action $20,932 · running total $76,677,646Modification SA089 · 2010-09-18 · this action $0 · running total $76,677,646Modification SA090 · 2010-09-18 · this action $3,187 · running total $76,680,833Modification SA091 · 2010-09-18 · this action $12,314 · running total $76,693,147Modification SA092 · 2010-09-18 · this action $10,000 · running total $76,703,147Modification SA093 · 2010-09-18 · this action $0 · running total $76,703,147Modification SA094 · 2010-09-18 · this action $1,725 · running total $76,704,872Modification SA095 · 2010-09-18 · this action $1,092 · running total $76,705,964Modification SA096 · 2010-09-18 · this action $11,000 · running total $76,716,964Modification SA097 · 2010-09-18 · this action $1,755 · running total $76,718,719Modification SA098 · 2010-09-21 · this action $15,500 · running total $76,734,219Modification SA099 · 2010-09-21 · this action $29,175 · running total $76,763,394Modification SA100 · 2010-09-21 · this action $3,251 · running total $76,766,645Modification CO01N · 2010-09-22 · this action $30,600 · running total $76,797,245Modification CO01P · 2010-09-30 · this action $98,000 · running total $76,895,245Modification CO02H · 2010-09-30 · this action $3,600 · running total $76,898,845Modification SA101 · 2010-09-30 · this action $15,467 · running total $76,914,312Modification SA102 · 2010-09-30 · this action $4,102 · running total $76,918,414Modification SA104 · 2010-12-15 · this action $4,750 · running total $76,923,164Modification SA106 · 2010-12-20 · this action $1,914 · running total $76,925,078Modification SA107 · 2010-12-20 · this action $990 · running total $76,926,068Modification SA108 · 2010-12-20 · this action $15,580 · running total $76,941,648Modification SA109 · 2010-12-20 · this action $17,000 · running total $76,958,648Modification SA112 · 2010-12-20 · this action $1,100 · running total $76,959,748Modification SA113 · 2010-12-22 · this action $6,800 · running total $76,966,548Modification SA103 · 2010-12-29 · this action $4,899 · running total $76,971,447Modification SA114 · 2011-01-27 · this action $56,855 · running total $77,028,302Modification SA116 · 2011-01-27 · this action $8,605 · running total $77,036,907Modification SA118 · 2011-01-27 · this action -$1,450 · running total $77,035,457Modification SA120 · 2011-01-27 · this action -$499 · running total $77,034,958Modification SA122 · 2011-01-27 · this action -$442 · running total $77,034,516Modification CO02K · 2011-02-06 · this action $2,200 · running total $77,036,716Modification CO02N · 2011-02-06 · this action $2,500 · running total $77,039,216Modification SA105 · 2011-02-06 · this action $14,614 · running total $77,053,830Modification SA129 · 2011-02-07 · this action -$300 · running total $77,053,530Modification CO02M · 2011-02-08 · this action $16,000 · running total $77,069,530Modification CO02P · 2011-02-08 · this action $4,900 · running total $77,074,430Modification SA143 · 2011-03-18 · this action $4,280 · running total $77,078,710Modification CO02Q · 2011-03-22 · this action $16,700 · running total $77,095,410Modification CO02X · 2011-03-22 · this action $1,200 · running total $77,096,610Modification SA131 · 2011-03-22 · this action $518,000 · running total $77,614,610Modification SA132 · 2011-03-22 · this action $1,984 · running total $77,616,594Modification SA133 · 2011-03-22 · this action $3,346 · running total $77,619,940Modification SA134 · 2011-03-22 · this action $2,000 · running total $77,621,940Modification CO02Y · 2011-04-11 · this action -$6,321 · running total $77,615,619Modification SA138 · 2011-04-11 · this action -$25,708 · running total $77,589,911Modification SA139 · 2011-04-11 · this action -$232 · running total $77,589,679Modification SA140 · 2011-04-11 · this action $5,898 · running total $77,595,577Modification SA141 · 2011-04-11 · this action $2,767 · running total $77,598,344Modification SA146 · 2011-04-11 · this action $384 · running total $77,598,728Modification SA148 · 2011-04-11 · this action $6,165 · running total $77,604,893Modification SA144 · 2011-04-13 · this action $783 · running total $77,605,676Modification SA145 · 2011-04-13 · this action $2,519 · running total $77,608,195Modification CO02O · 2011-05-03 · this action $4,536 · running total $77,612,731Modification CO02T · 2011-05-03 · this action $2,030 · running total $77,614,761Modification CO02U · 2011-05-03 · this action $7,000 · running total $77,621,761Modification CO03A · 2011-05-03 · this action $16,900 · running total $77,638,661Modification SA149 · 2011-05-03 · this action -$10,515 · running total $77,628,146Modification SA150 · 2011-05-03 · this action $2,500 · running total $77,630,646Modification SA153 · 2011-05-09 · this action $426 · running total $77,631,072Modification SA154 · 2011-05-09 · this action $3,374 · running total $77,634,446Modification SA155 · 2011-05-09 · this action $1,650 · running total $77,636,096Modification SA151 · 2011-05-10 · this action $1,019 · running total $77,637,115Modification SA152 · 2011-05-10 · this action $2,365 · running total $77,639,480Modification CO02L · 2011-05-16 · this action $21,895 · running total $77,661,375Modification CO02R · 2011-05-16 · this action $22,000 · running total $77,683,375Modification CO02S · 2011-05-16 · this action $19,580 · running total $77,702,955Modification SA115 · 2011-05-16 · this action $13,602 · running total $77,716,557Modification SA117 · 2011-05-16 · this action $6,981 · running total $77,723,538Modification SA123 · 2011-05-16 · this action $19,800 · running total $77,743,338Modification SA127 · 2011-05-16 · this action $2,000 · running total $77,745,338Modification SA130 · 2011-05-16 · this action $766 · running total $77,746,104Modification SA135 · 2011-05-16 · this action $14,419 · running total $77,760,523Modification SA136 · 2011-05-16 · this action $1,473 · running total $77,761,996Modification SA137 · 2011-05-16 · this action $4,074 · running total $77,766,070Modification CO02V · 2011-05-18 · this action $22,216 · running total $77,788,286Modification SA170 · 2011-06-22 · this action -$88,200 · running total $77,700,086Modification CO03E · 2011-07-25 · this action -$9,200 · running total $77,690,886Modification SA164 · 2011-07-25 · this action $8,159 · running total $77,699,045Modification SA166 · 2011-07-25 · this action $3,410 · running total $77,702,455Modification SA167 · 2011-07-25 · this action $36,294 · running total $77,738,749Modification SA168 · 2011-07-25 · this action $1,164 · running total $77,739,913Modification SA169 · 2011-07-26 · this action -$6,153 · running total $77,733,760Modification CO03N · 2011-08-02 · this action $4,699 · running total $77,738,459Modification CO03F · 2011-08-15 · this action $11,492 · running total $77,749,951Modification CO03G · 2011-08-15 · this action $300 · running total $77,750,251Modification CO02Z · 2011-08-17 · this action $1,010 · running total $77,751,261Modification CO03D · 2011-08-17 · this action $35,000 · running total $77,786,261Modification SA162 · 2011-08-17 · this action $1,224 · running total $77,787,485Modification SA163 · 2011-08-17 · this action $7,453 · running total $77,794,938Modification SA157 · 2011-08-18 · this action -$6,154 · running total $77,788,784Modification SA158 · 2011-08-18 · this action $2,850 · running total $77,791,634Modification SA159 · 2011-08-18 · this action -$15,000 · running total $77,776,634Modification SA160 · 2011-08-18 · this action $3,312 · running total $77,779,946Modification CO03H · 2011-08-23 · this action $9,862 · running total $77,789,808Modification SA173 · 2011-08-23 · this action $2,866 · running total $77,792,674Modification SA174 · 2011-08-23 · this action -$24 · running total $77,792,650Modification CO03I · 2011-08-30 · this action $3,400 · running total $77,796,050Modification CO03J · 2011-08-30 · this action $6,000 · running total $77,802,050Modification CO03K · 2011-08-30 · this action $6,213 · running total $77,808,263Modification CO03O · 2011-08-30 · this action $950 · running total $77,809,213Modification CO03P · 2011-08-30 · this action $3,500 · running total $77,812,713Modification CO03Q · 2011-08-30 · this action $1,200 · running total $77,813,913Modification CO03R · 2011-08-30 · this action $13,550 · running total $77,827,463Modification SA172 · 2011-08-30 · this action -$19,031 · running total $77,808,432Modification SA175 · 2011-08-30 · this action $1,449 · running total $77,809,881Modification SA176 · 2011-08-30 · this action $13,515 · running total $77,823,396Modification SA178 · 2011-08-30 · this action $5,018 · running total $77,828,414Modification SA179 · 2011-08-30 · this action $9,376 · running total $77,837,790Modification SA184 · 2011-08-31 · this action $2,036 · running total $77,839,826Modification CO02I · 2011-09-06 · this action $2,950 · running total $77,842,776Modification CO02W · 2011-09-06 · this action $41,337 · running total $77,884,113Modification CO03B · 2011-09-06 · this action $9,894 · running total $77,894,007Modification CO03C · 2011-09-06 · this action $2,500 · running total $77,896,507Modification CO03L · 2011-09-06 · this action $6,099 · running total $77,902,606Modification CO03M · 2011-09-06 · this action $617 · running total $77,903,223Modification SA171 · 2011-09-06 · this action -$79 · running total $77,903,144Modification SA177 · 2011-09-06 · this action $723 · running total $77,903,867Modification SA180 · 2011-09-06 · this action $1,905 · running total $77,905,772Modification SA181 · 2011-09-06 · this action $1,073 · running total $77,906,845Modification SA182 · 2011-09-06 · this action $6,784 · running total $77,913,629Modification SA110 · 2011-09-12 · this action -$1,724 · running total $77,911,905Modification SA111 · 2011-09-12 · this action -$17,813 · running total $77,894,092Modification SA119 · 2011-09-12 · this action -$11,475 · running total $77,882,617Modification SA121 · 2011-09-12 · this action $24,061 · running total $77,906,678Modification SA124 · 2011-09-12 · this action $0 · running total $77,906,678Modification SA125 · 2011-09-12 · this action $1,797 · running total $77,908,475Modification SA161 · 2011-09-12 · this action $2,666 · running total $77,911,141Modification SA165 · 2011-09-12 · this action $897 · running total $77,912,038Modification SA183 · 2011-09-12 · this action $4,321 · running total $77,916,359Modification SA126 · 2011-09-13 · this action $2,454 · running total $77,918,813Modification SA128 · 2011-09-13 · this action $887 · running total $77,919,700Modification SA142 · 2011-09-15 · this action $2,500 · running total $77,922,200Modification SA147 · 2011-09-15 · this action $920 · running total $77,923,120Modification SA156 · 2011-09-15 · this action $43,216 · running total $77,966,336Modification SA185 · 2011-09-15 · this action $2,778 · running total $77,969,114Modification SA186 · 2011-09-15 · this action $2,000 · running total $77,971,114Modification SA187 · 2011-09-21 · this action $3,824 · running total $77,974,938Modification SA188 · 2011-09-27 · this action $2,000 · running total $77,976,938Modification SA189 · 2011-09-27 · this action $0 · running total $77,976,938Modification SA191 · 2011-09-29 · this action $11,236 · running total $77,988,174Modification SA192 · 2011-09-29 · this action $645 · running total $77,988,819Modification SA193 · 2011-09-29 · this action $1,884 · running total $77,990,703Modification SA194 · 2011-09-29 · this action $2,195 · running total $77,992,898Modification SA190 · 2011-09-30 · this action -$46,955 · running total $77,945,943Modification SA195 · 2011-09-30 · this action $4,787 · running total $77,950,730Modification SA196 · 2011-09-30 · this action $674 · running total $77,951,404Modification SA197 · 2011-09-30 · this action $45,000 · running total $77,996,404Modification SA198 · 2011-10-12 · this action $1,652 · running total $77,998,056Modification SA200 · 2011-10-13 · this action $0 · running total $77,998,056Modification SA201 · 2011-10-14 · this action $17,493 · running total $78,015,549Modification SA199 · 2011-10-21 · this action $1,275 · running total $78,016,824Modification SA203 · 2011-10-21 · this action -$19,486 · running total $77,997,338Modification SA204 · 2011-10-21 · this action $20,323 · running total $78,017,661Modification SA205 · 2011-10-21 · this action $964 · running total $78,018,625Modification SA206 · 2011-10-26 · this action $10,120 · running total $78,028,745Modification SA208 · 2011-10-28 · this action $4,388 · running total $78,033,133Modification SA207 · 2011-11-21 · this action $3,336 · running total $78,036,469Modification SA209 · 2011-11-22 · this action $1,808 · running total $78,038,277Modification SA210 · 2011-11-22 · this action $763 · running total $78,039,040Modification CO03S · 2011-11-29 · this action $67,735 · running total $78,106,775Modification SA211 · 2011-11-29 · this action $3,764 · running total $78,110,539Modification CO03T · 2011-11-30 · this action $10,530 · running total $78,121,069Modification CO03U · 2011-11-30 · this action $61,000 · running total $78,182,069Modification SA212 · 2011-11-30 · this action $6,135 · running total $78,188,204Modification SA213 · 2011-11-30 · this action $10,440 · running total $78,198,644Modification SA214 · 2011-12-13 · this action $2,097 · running total $78,200,741Modification SA215 · 2011-12-21 · this action $6,000 · running total $78,206,741Modification SA216 · 2011-12-21 · this action $2,970 · running total $78,209,711Modification SA217 · 2011-12-21 · this action $1,001 · running total $78,210,712Modification SA218 · 2011-12-21 · this action $0 · running total $78,210,712Modification SA219 · 2011-12-21 · this action $1,138 · running total $78,211,850Modification SA220 · 2011-12-21 · this action $18,000 · running total $78,229,850Modification SA221 · 2011-12-21 · this action $26,000 · running total $78,255,850Modification SA222 · 2011-12-21 · this action $23,864 · running total $78,279,714Modification SA202 · 2012-01-09 · this action $14,200 · running total $78,293,914Modification SA223 · 2012-01-19 · this action $5,714 · running total $78,299,628Modification SA224 · 2012-02-09 · this action $1,000 · running total $78,300,628Modification SA225 · 2012-02-13 · this action $27,764 · running total $78,328,392Modification SA227 · 2012-05-04 · this action $495 · running total $78,328,887Modification CO03V · 2012-05-11 · this action $39,084 · running total $78,367,971Modification CO03W · 2012-07-20 · this action $2,962 · running total $78,370,933Modification SA228 · 2012-11-02 · this action -$17,403 · running total $78,353,530Modification SA229 · 2012-11-02 · this action $29,251 · running total $78,382,781Modification SA230 · 2012-11-20 · this action $15,123 · running total $78,397,904Modification P00003 · 2013-07-25 · this action $6,635 · running total $78,404,539Modification P00004 · 2013-11-26 · this action $7,629 · running total $78,412,168
  • Base2008-11-12+$75,802,000= $75,802,000
  • Mod SA0352010-01-11-$164,502= $75,637,498
  • Mod CO01R2010-03-04+$276,000= $75,913,498
  • Mod SA0542010-04-12-$32,000= $75,881,498
  • Mod SA0582010-04-19-$875= $75,880,623
  • Mod SA0622010-04-29-$164= $75,880,459
  • Mod SA0642010-04-30-$3,000= $75,877,459
  • Mod CO02A2010-06-17+$38,000= $75,915,459
  • Mod CO02B2010-06-17+$14,100= $75,929,559
  • Mod CO02C2010-06-22+$2,800= $75,932,359
  • Mod SA0782010-06-30-$50,000= $75,882,359
  • Mod SA0772010-07-01-$4,400= $75,877,959
  • Mod CO01M2010-09-18+$47,395= $75,925,354
  • Mod CO01Q2010-09-18+$6,129= $75,931,483
  • Mod CO01S2010-09-18+$32,720= $75,964,203
  • Mod CO01T2010-09-18+$18,200= $75,982,403
  • Mod CO01U2010-09-18+$18,075= $76,000,478
  • Mod CO01V2010-09-18+$59,700= $76,060,178
  • Mod CO01W2010-09-18+$10,611= $76,070,789
  • Mod CO01X2010-09-18+$11,888= $76,082,677
  • Mod CO01Y2010-09-18+$39,886= $76,122,563
  • Mod CO01Z2010-09-18+$6,325= $76,128,888
  • Mod CO02D2010-09-18+$1,628= $76,130,516
  • Mod CO02E2010-09-18+$5,000= $76,135,516
  • Mod CO02F2010-09-18+$1,367= $76,136,883
  • Mod SA0232010-09-18+$2,782= $76,139,665
  • Mod SA0252010-09-18+$330= $76,139,995
  • Mod SA0272010-09-18+$5,500= $76,145,495
  • Mod SA0282010-09-18+$3,177= $76,148,672
  • Mod SA0292010-09-18+$3,313= $76,151,985
  • Mod SA0302010-09-18+$50,000= $76,201,985
  • Mod SA0312010-09-18+$550= $76,202,535
  • Mod SA0322010-09-18+$5,000= $76,207,535
  • Mod SA0332010-09-18+$0= $76,207,535
  • Mod SA0342010-09-18+$0= $76,207,535
  • Mod SA0362010-09-18+$1,169= $76,208,704
  • Mod SA0372010-09-18+$20,475= $76,229,179
  • Mod SA0382010-09-18+$14,823= $76,244,002
  • Mod SA0392010-09-18+$9,880= $76,253,882
  • Mod SA0402010-09-18+$8,000= $76,261,882
  • Mod SA0412010-09-18+$1,574= $76,263,456
  • Mod SA0422010-09-18+$2,367= $76,265,823
  • Mod SA0432010-09-18+$1,533= $76,267,356
  • Mod SA0442010-09-18+$2,919= $76,270,275
  • Mod SA0452010-09-18+$7,700= $76,277,975
  • Mod SA0462010-09-18+$19,446= $76,297,421
  • Mod SA0472010-09-18+$5,674= $76,303,095
  • Mod SA0482010-09-18+$57,800= $76,360,895
  • Mod SA0492010-09-18+$3,360= $76,364,255
  • Mod SA0502010-09-18+$7,805= $76,372,060
  • Mod SA0512010-09-18+$3,290= $76,375,350
  • Mod SA0522010-09-18+$18,400= $76,393,750
  • Mod SA0532010-09-18+$32,000= $76,425,750
  • Mod SA0552010-09-18+$1,400= $76,427,150
  • Mod SA0562010-09-18+$10,589= $76,437,739
  • Mod SA0572010-09-18+$28,488= $76,466,227
  • Mod SA0592010-09-18+$6,600= $76,472,827
  • Mod SA0602010-09-18+$2,846= $76,475,673
  • Mod SA0612010-09-18+$3,581= $76,479,254
  • Mod SA0632010-09-18+$4,000= $76,483,254
  • Mod SA0652010-09-18+$3,529= $76,486,783
  • Mod SA0662010-09-18+$0= $76,486,783
  • Mod SA0672010-09-18+$13,007= $76,499,790
  • Mod SA0682010-09-18+$0= $76,499,790
  • Mod SA0692010-09-18+$4,378= $76,504,168
  • Mod SA0702010-09-18+$1,150= $76,505,318
  • Mod SA0712010-09-18+$1,900= $76,507,218
  • Mod SA0722010-09-18+$3,771= $76,510,989
  • Mod SA0732010-09-18+$252= $76,511,241
  • Mod SA0742010-09-18+$3,790= $76,515,031
  • Mod SA0752010-09-18+$8,000= $76,523,031
  • Mod SA0762010-09-18+$17,000= $76,540,031
  • Mod SA0792010-09-18+$2,605= $76,542,636
  • Mod SA0802010-09-18+$35,000= $76,577,636
  • Mod SA0812010-09-18+$64,911= $76,642,547
  • Mod SA0822010-09-18+$0= $76,642,547
  • Mod SA0832010-09-18+$1,714= $76,644,261
  • Mod SA0842010-09-18+$3,500= $76,647,761
  • Mod SA0852010-09-18+$300= $76,648,061
  • Mod SA0862010-09-18+$4,153= $76,652,214
  • Mod SA0872010-09-18+$4,500= $76,656,714
  • Mod SA0882010-09-18+$20,932= $76,677,646
  • Mod SA0892010-09-18+$0= $76,677,646
  • Mod SA0902010-09-18+$3,187= $76,680,833
  • Mod SA0912010-09-18+$12,314= $76,693,147
  • Mod SA0922010-09-18+$10,000= $76,703,147
  • Mod SA0932010-09-18+$0= $76,703,147
  • Mod SA0942010-09-18+$1,725= $76,704,872
  • Mod SA0952010-09-18+$1,092= $76,705,964
  • Mod SA0962010-09-18+$11,000= $76,716,964
  • Mod SA0972010-09-18+$1,755= $76,718,719
  • Mod SA0982010-09-21+$15,500= $76,734,219
  • Mod SA0992010-09-21+$29,175= $76,763,394
  • Mod SA1002010-09-21+$3,251= $76,766,645
  • Mod CO01N2010-09-22+$30,600= $76,797,245
  • Mod CO01P2010-09-30+$98,000= $76,895,245
  • Mod CO02H2010-09-30+$3,600= $76,898,845
  • Mod SA1012010-09-30+$15,467= $76,914,312
  • Mod SA1022010-09-30+$4,102= $76,918,414
  • Mod SA1042010-12-15+$4,750= $76,923,164
  • Mod SA1062010-12-20+$1,914= $76,925,078
  • Mod SA1072010-12-20+$990= $76,926,068
  • Mod SA1082010-12-20+$15,580= $76,941,648
  • Mod SA1092010-12-20+$17,000= $76,958,648
  • Mod SA1122010-12-20+$1,100= $76,959,748
  • Mod SA1132010-12-22+$6,800= $76,966,548
  • Mod SA1032010-12-29+$4,899= $76,971,447
  • Mod SA1142011-01-27+$56,855= $77,028,302
  • Mod SA1162011-01-27+$8,605= $77,036,907
  • Mod SA1182011-01-27-$1,450= $77,035,457
  • Mod SA1202011-01-27-$499= $77,034,958
  • Mod SA1222011-01-27-$442= $77,034,516
  • Mod CO02K2011-02-06+$2,200= $77,036,716
  • Mod CO02N2011-02-06+$2,500= $77,039,216
  • Mod SA1052011-02-06+$14,614= $77,053,830
  • Mod SA1292011-02-07-$300= $77,053,530
  • Mod CO02M2011-02-08+$16,000= $77,069,530
  • Mod CO02P2011-02-08+$4,900= $77,074,430
  • Mod SA1432011-03-18+$4,280= $77,078,710
  • Mod CO02Q2011-03-22+$16,700= $77,095,410
  • Mod CO02X2011-03-22+$1,200= $77,096,610
  • Mod SA1312011-03-22+$518,000= $77,614,610
  • Mod SA1322011-03-22+$1,984= $77,616,594
  • Mod SA1332011-03-22+$3,346= $77,619,940
  • Mod SA1342011-03-22+$2,000= $77,621,940
  • Mod CO02Y2011-04-11-$6,321= $77,615,619
  • Mod SA1382011-04-11-$25,708= $77,589,911
  • Mod SA1392011-04-11-$232= $77,589,679
  • Mod SA1402011-04-11+$5,898= $77,595,577
  • Mod SA1412011-04-11+$2,767= $77,598,344
  • Mod SA1462011-04-11+$384= $77,598,728
  • Mod SA1482011-04-11+$6,165= $77,604,893
  • Mod SA1442011-04-13+$783= $77,605,676
  • Mod SA1452011-04-13+$2,519= $77,608,195
  • Mod CO02O2011-05-03+$4,536= $77,612,731
  • Mod CO02T2011-05-03+$2,030= $77,614,761
  • Mod CO02U2011-05-03+$7,000= $77,621,761
  • Mod CO03A2011-05-03+$16,900= $77,638,661
  • Mod SA1492011-05-03-$10,515= $77,628,146
  • Mod SA1502011-05-03+$2,500= $77,630,646
  • Mod SA1532011-05-09+$426= $77,631,072
  • Mod SA1542011-05-09+$3,374= $77,634,446
  • Mod SA1552011-05-09+$1,650= $77,636,096
  • Mod SA1512011-05-10+$1,019= $77,637,115
  • Mod SA1522011-05-10+$2,365= $77,639,480
  • Mod CO02L2011-05-16+$21,895= $77,661,375
  • Mod CO02R2011-05-16+$22,000= $77,683,375
  • Mod CO02S2011-05-16+$19,580= $77,702,955
  • Mod SA1152011-05-16+$13,602= $77,716,557
  • Mod SA1172011-05-16+$6,981= $77,723,538
  • Mod SA1232011-05-16+$19,800= $77,743,338
  • Mod SA1272011-05-16+$2,000= $77,745,338
  • Mod SA1302011-05-16+$766= $77,746,104
  • Mod SA1352011-05-16+$14,419= $77,760,523
  • Mod SA1362011-05-16+$1,473= $77,761,996
  • Mod SA1372011-05-16+$4,074= $77,766,070
  • Mod CO02V2011-05-18+$22,216= $77,788,286
  • Mod SA1702011-06-22-$88,200= $77,700,086
  • Mod CO03E2011-07-25-$9,200= $77,690,886
  • Mod SA1642011-07-25+$8,159= $77,699,045
  • Mod SA1662011-07-25+$3,410= $77,702,455
  • Mod SA1672011-07-25+$36,294= $77,738,749
  • Mod SA1682011-07-25+$1,164= $77,739,913
  • Mod SA1692011-07-26-$6,153= $77,733,760
  • Mod CO03N2011-08-02+$4,699= $77,738,459
  • Mod CO03F2011-08-15+$11,492= $77,749,951
  • Mod CO03G2011-08-15+$300= $77,750,251
  • Mod CO02Z2011-08-17+$1,010= $77,751,261
  • Mod CO03D2011-08-17+$35,000= $77,786,261
  • Mod SA1622011-08-17+$1,224= $77,787,485
  • Mod SA1632011-08-17+$7,453= $77,794,938
  • Mod SA1572011-08-18-$6,154= $77,788,784
  • Mod SA1582011-08-18+$2,850= $77,791,634
  • Mod SA1592011-08-18-$15,000= $77,776,634
  • Mod SA1602011-08-18+$3,312= $77,779,946
  • Mod CO03H2011-08-23+$9,862= $77,789,808
  • Mod SA1732011-08-23+$2,866= $77,792,674
  • Mod SA1742011-08-23-$24= $77,792,650
  • Mod CO03I2011-08-30+$3,400= $77,796,050
  • Mod CO03J2011-08-30+$6,000= $77,802,050
  • Mod CO03K2011-08-30+$6,213= $77,808,263
  • Mod CO03O2011-08-30+$950= $77,809,213
  • Mod CO03P2011-08-30+$3,500= $77,812,713
  • Mod CO03Q2011-08-30+$1,200= $77,813,913
  • Mod CO03R2011-08-30+$13,550= $77,827,463
  • Mod SA1722011-08-30-$19,031= $77,808,432
  • Mod SA1752011-08-30+$1,449= $77,809,881
  • Mod SA1762011-08-30+$13,515= $77,823,396
  • Mod SA1782011-08-30+$5,018= $77,828,414
  • Mod SA1792011-08-30+$9,376= $77,837,790
  • Mod SA1842011-08-31+$2,036= $77,839,826
  • Mod CO02I2011-09-06+$2,950= $77,842,776
  • Mod CO02W2011-09-06+$41,337= $77,884,113
  • Mod CO03B2011-09-06+$9,894= $77,894,007
  • Mod CO03C2011-09-06+$2,500= $77,896,507
  • Mod CO03L2011-09-06+$6,099= $77,902,606
  • Mod CO03M2011-09-06+$617= $77,903,223
  • Mod SA1712011-09-06-$79= $77,903,144
  • Mod SA1772011-09-06+$723= $77,903,867
  • Mod SA1802011-09-06+$1,905= $77,905,772
  • Mod SA1812011-09-06+$1,073= $77,906,845
  • Mod SA1822011-09-06+$6,784= $77,913,629
  • Mod SA1102011-09-12-$1,724= $77,911,905
  • Mod SA1112011-09-12-$17,813= $77,894,092
  • Mod SA1192011-09-12-$11,475= $77,882,617
  • Mod SA1212011-09-12+$24,061= $77,906,678
  • Mod SA1242011-09-12+$0= $77,906,678
  • Mod SA1252011-09-12+$1,797= $77,908,475
  • Mod SA1612011-09-12+$2,666= $77,911,141
  • Mod SA1652011-09-12+$897= $77,912,038
  • Mod SA1832011-09-12+$4,321= $77,916,359
  • Mod SA1262011-09-13+$2,454= $77,918,813
  • Mod SA1282011-09-13+$887= $77,919,700
  • Mod SA1422011-09-15+$2,500= $77,922,200
  • Mod SA1472011-09-15+$920= $77,923,120
  • Mod SA1562011-09-15+$43,216= $77,966,336
  • Mod SA1852011-09-15+$2,778= $77,969,114
  • Mod SA1862011-09-15+$2,000= $77,971,114
  • Mod SA1872011-09-21+$3,824= $77,974,938
  • Mod SA1882011-09-27+$2,000= $77,976,938
  • Mod SA1892011-09-27+$0= $77,976,938
  • Mod SA1912011-09-29+$11,236= $77,988,174
  • Mod SA1922011-09-29+$645= $77,988,819
  • Mod SA1932011-09-29+$1,884= $77,990,703
  • Mod SA1942011-09-29+$2,195= $77,992,898
  • Mod SA1902011-09-30-$46,955= $77,945,943
  • Mod SA1952011-09-30+$4,787= $77,950,730
  • Mod SA1962011-09-30+$674= $77,951,404
  • Mod SA1972011-09-30+$45,000= $77,996,404
  • Mod SA1982011-10-12+$1,652= $77,998,056
  • Mod SA2002011-10-13+$0= $77,998,056
  • Mod SA2012011-10-14+$17,493= $78,015,549
  • Mod SA1992011-10-21+$1,275= $78,016,824
  • Mod SA2032011-10-21-$19,486= $77,997,338
  • Mod SA2042011-10-21+$20,323= $78,017,661
  • Mod SA2052011-10-21+$964= $78,018,625
  • Mod SA2062011-10-26+$10,120= $78,028,745
  • Mod SA2082011-10-28+$4,388= $78,033,133
  • Mod SA2072011-11-21+$3,336= $78,036,469
  • Mod SA2092011-11-22+$1,808= $78,038,277
  • Mod SA2102011-11-22+$763= $78,039,040
  • Mod CO03S2011-11-29+$67,735= $78,106,775
  • Mod SA2112011-11-29+$3,764= $78,110,539
  • Mod CO03T2011-11-30+$10,530= $78,121,069
  • Mod CO03U2011-11-30+$61,000= $78,182,069
  • Mod SA2122011-11-30+$6,135= $78,188,204
  • Mod SA2132011-11-30+$10,440= $78,198,644
  • Mod SA2142011-12-13+$2,097= $78,200,741
  • Mod SA2152011-12-21+$6,000= $78,206,741
  • Mod SA2162011-12-21+$2,970= $78,209,711
  • Mod SA2172011-12-21+$1,001= $78,210,712
  • Mod SA2182011-12-21+$0= $78,210,712
  • Mod SA2192011-12-21+$1,138= $78,211,850
  • Mod SA2202011-12-21+$18,000= $78,229,850
  • Mod SA2212011-12-21+$26,000= $78,255,850
  • Mod SA2222011-12-21+$23,864= $78,279,714
  • Mod SA2022012-01-09+$14,200= $78,293,914
  • Mod SA2232012-01-19+$5,714= $78,299,628
  • Mod SA2242012-02-09+$1,000= $78,300,628
  • Mod SA2252012-02-13+$27,764= $78,328,392
  • Mod SA2272012-05-04+$495= $78,328,887
  • Mod CO03V2012-05-11+$39,084= $78,367,971
  • Mod CO03W2012-07-20+$2,962= $78,370,933
  • Mod SA2282012-11-02-$17,403= $78,353,530
  • Mod SA2292012-11-02+$29,251= $78,382,781
  • Mod SA2302012-11-20+$15,123= $78,397,904
  • Mod P000032013-07-25+$6,635= $78,404,539
  • Mod P000042013-11-26+$7,629= $78,412,168
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2008-11-12+$75,802,000$75,802,000CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING
Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-11−$164,502$75,637,498CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-035
Mod CO01R· CHANGE ORDER2010-03-04+$276,000$75,913,498CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01R
Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-12−$32,000$75,881,498CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-054
Mod SA058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-19−$875$75,880,623CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-058
Mod SA062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-29−$164$75,880,459CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-062
Mod SA064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-30−$3,000$75,877,459CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-064
Mod CO02A· CHANGE ORDER2010-06-17+$38,000$75,915,459CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02A
Mod CO02B· CHANGE ORDER2010-06-17+$14,100$75,929,559CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02B
Mod CO02C· CHANGE ORDER2010-06-22+$2,800$75,932,359CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02C
Mod SA078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-30−$50,000$75,882,359CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-078
Mod SA077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-01−$4,400$75,877,959CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-077
Mod CO01M· CHANGE ORDER2010-09-18+$47,395$75,925,354CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01M
Mod CO01Q· CHANGE ORDER2010-09-18+$6,129$75,931,483CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01Q
Mod CO01S· CHANGE ORDER2010-09-18+$32,720$75,964,203CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01S
Mod CO01T· CHANGE ORDER2010-09-18+$18,200$75,982,403CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01T
Mod CO01U· CHANGE ORDER2010-09-18+$18,075$76,000,478CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01U
Mod CO01V· CHANGE ORDER2010-09-18+$59,700$76,060,178CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01V
Mod CO01W· CHANGE ORDER2010-09-18+$10,611$76,070,789CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01W
Mod CO01X· CHANGE ORDER2010-09-18+$11,888$76,082,677CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01X
Mod CO01Y· CHANGE ORDER2010-09-18+$39,886$76,122,563CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01Y
Mod CO01Z· CHANGE ORDER2010-09-18+$6,325$76,128,888CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01Z
Mod CO02D· CHANGE ORDER2010-09-18+$1,628$76,130,516CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02D
Mod CO02E· CHANGE ORDER2010-09-18+$5,000$76,135,516CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02E
Mod CO02F· CHANGE ORDER2010-09-18+$1,367$76,136,883CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02F
Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$2,782$76,139,665CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-023
Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$330$76,139,995CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-025
Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$5,500$76,145,495CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-027
Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,177$76,148,672CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-028
Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,313$76,151,985CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-029
Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$50,000$76,201,985CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-030
Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$550$76,202,535CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-031
Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$5,000$76,207,535CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-032
Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,207,535CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-033
Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,207,535CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-034
Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,169$76,208,704CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-036
Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$20,475$76,229,179CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-037
Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$14,823$76,244,002CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-038
Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$9,880$76,253,882CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-039
Mod SA040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$8,000$76,261,882CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-040
Mod SA041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,574$76,263,456CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-041
Mod SA042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$2,367$76,265,823CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-042
Mod SA043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,533$76,267,356CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-043
Mod SA044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$2,919$76,270,275CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-044
Mod SA045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$7,700$76,277,975CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-045
Mod SA046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$19,446$76,297,421CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-046
Mod SA047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$5,674$76,303,095CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-047
Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$57,800$76,360,895CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-048
Mod SA049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,360$76,364,255CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-049
Mod SA050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$7,805$76,372,060CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-050
Mod SA051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,290$76,375,350CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-051
Mod SA052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$18,400$76,393,750CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-052
Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$32,000$76,425,750CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-053
Mod SA055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,400$76,427,150CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-055
Mod SA056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$10,589$76,437,739CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-056
Mod SA057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$28,488$76,466,227CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-057
Mod SA059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$6,600$76,472,827CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-059
Mod SA060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$2,846$76,475,673CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-060
Mod SA061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,581$76,479,254CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-061
Mod SA063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$4,000$76,483,254CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-063
Mod SA065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,529$76,486,783CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-065
Mod SA066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,486,783CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-066
Mod SA067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$13,007$76,499,790CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-067
Mod SA068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,499,790CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-068
Mod SA069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$4,378$76,504,168CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-069
Mod SA070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,150$76,505,318CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-070
Mod SA071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,900$76,507,218CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-071
Mod SA072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,771$76,510,989CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-072
Mod SA073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$252$76,511,241CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-073
Mod SA074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,790$76,515,031CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-074
Mod SA075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$8,000$76,523,031CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-075
Mod SA076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$17,000$76,540,031CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-076
Mod SA079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$2,605$76,542,636CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-079
Mod SA080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$35,000$76,577,636CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-080
Mod SA081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$64,911$76,642,547CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-081
Mod SA082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,642,547CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-082
Mod SA083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,714$76,644,261CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-083
Mod SA084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,500$76,647,761CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-084
Mod SA085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$300$76,648,061CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-085
Mod SA086· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$4,153$76,652,214CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-086
Mod SA087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$4,500$76,656,714CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-087
Mod SA088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$20,932$76,677,646CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-088
Mod SA089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,677,646CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-089
Mod SA090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$3,187$76,680,833CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-090
Mod SA091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$12,314$76,693,147CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-091
Mod SA092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$10,000$76,703,147CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-092
Mod SA093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$0$76,703,147CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-093
Mod SA094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,725$76,704,872CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-094
Mod SA095· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,092$76,705,964CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-095
Mod SA096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$11,000$76,716,964CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-096
Mod SA097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$1,755$76,718,719CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-097
Mod SA098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-21+$15,500$76,734,219CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-098
Mod SA099· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-21+$29,175$76,763,394CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-099
Mod SA100· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-21+$3,251$76,766,645CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-100
Mod CO01N· CHANGE ORDER2010-09-22+$30,600$76,797,245CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01N
Mod CO01P· CHANGE ORDER2010-09-30+$98,000$76,895,245CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-01P
Mod CO02H· CHANGE ORDER2010-09-30+$3,600$76,898,845CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02H
Mod SA101· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-30+$15,467$76,914,312CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-101
Mod SA102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-30+$4,102$76,918,414CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-102
Mod SA104· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-15+$4,750$76,923,164CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-104
Mod SA106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$1,914$76,925,078CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-106
Mod SA107· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$990$76,926,068CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-107
Mod SA108· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$15,580$76,941,648CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-108
Mod SA109· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$17,000$76,958,648CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-109
Mod SA112· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$1,100$76,959,748CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-112
Mod SA113· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-22+$6,800$76,966,548CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-113
Mod SA103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-29+$4,899$76,971,447CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-103
Mod SA114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-27+$56,855$77,028,302CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-114
Mod SA116· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-27+$8,605$77,036,907CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-116
Mod SA118· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-27−$1,450$77,035,457CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-114
Mod SA120· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-27−$499$77,034,958CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-120
Mod SA122· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-27−$442$77,034,516CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-122
Mod CO02K· CHANGE ORDER2011-02-06+$2,200$77,036,716CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02H
Mod CO02N· CHANGE ORDER2011-02-06+$2,500$77,039,216CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02N
Mod SA105· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-06+$14,614$77,053,830CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-105
Mod SA129· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-07−$300$77,053,530SA-129 DURING REVIEW OF RFI #879 IT WAS IDENTIFIED THAT THE DATA CABLE RUNS FROM THE EAST SIDE OFFICES OF THE…
Mod CO02M· CHANGE ORDER2011-02-08+$16,000$77,069,530CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02M
Mod CO02P· CHANGE ORDER2011-02-08+$4,900$77,074,430CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02P
Mod SA143· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-18+$4,280$77,078,710CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-143
Mod CO02Q· CHANGE ORDER2011-03-22+$16,700$77,095,410CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02Q
Mod CO02X· CHANGE ORDER2011-03-22+$1,200$77,096,610CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02X
Mod SA131· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-22+$518,000$77,614,610CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-131
Mod SA132· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-22+$1,984$77,616,594CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-132
Mod SA133· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-22+$3,346$77,619,940CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-133
Mod SA134· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-22+$2,000$77,621,940CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-134
Mod CO02Y· CHANGE ORDER2011-04-11−$6,321$77,615,619CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02Y
Mod SA138· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11−$25,708$77,589,911CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-138
Mod SA139· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11−$232$77,589,679CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-139
Mod SA140· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11+$5,898$77,595,577CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-140
Mod SA141· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11+$2,767$77,598,344CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-141
Mod SA146· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11+$384$77,598,728CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-146
Mod SA148· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11+$6,165$77,604,893CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-148
Mod SA144· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-13+$783$77,605,676CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-144
Mod SA145· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-13+$2,519$77,608,195CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-145
Mod CO02O· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$4,536$77,612,731THE DUCTWORK AND OTHER ASSOCIATED ABOVE CEILING ITEMS WOULD NOT FIT ABOVE THE CEILING IN LOBBY AREA 1M100 AT T…
Mod CO02T· CHANGE ORDER2011-05-03+$2,030$77,614,761THE SPARE CONDUIT FOR THE TELEPHONE CABLES WAS USED TO INSTALL A 300 PAIR CABLE (PER THE VAMC REQUEST). TO PR…
Mod CO02U· CHANGE ORDER2011-05-03+$7,000$77,621,761THE IDF CLOSET 1N162 CONTAINS COMPUTER EQUIPMENT CRITICAL TO THE FUNCTION OF THE HOSPITAL AND WILL NOT BE SUFF…
Mod CO03A· CHANGE ORDER2011-05-03+$16,900$77,638,661ACTUAL BUILDING EXPANSION JOINT IS AT EXISTING COLUMN LINE 33, NOT AS SHOWN ON SHT AS1-123. THIS LOCATION REQU…
Mod SA149· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03−$10,515$77,628,146THE CONTRACT DRAWINGS AND PREVIOUS RFP D#18 LIFE SAFETY DRAWINGS SHOW A NUMBER OF LOCATIONS WHERE FULLY RECESS…
Mod SA150· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$2,500$77,630,646DURING RENOVATION OF THE LOBBY A BUSS DUCT WAS IDENTIFIED INSIDE THE WALL OF THE EXISTING FIRE COMMAND ROOM, T…
Mod SA153· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-09+$426$77,631,072SA-153 THE SPARE CONDUIT FOR THE TELEPHONE CABLES WAS USED TO INSTALL A 300 PAIR CABLE. IN ORDER TO PROVIDE SP…
Mod SA154· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-09+$3,374$77,634,446SA-154 RFI 881 IDENTIFIED THE LACK OF COORDINATION OF THE TYPE OF LIGHT TO BE USED IN THE LOBBY OF THE PASSEN…
Mod SA155· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-09+$1,650$77,636,096SA-155 RFI 867 WAS ISSUED REGARDING THE HINGED FRAME FOR THE LARGE STAINED GLASS WINDOW. THE LARGE STAINED GLA…
Mod SA151· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-10+$1,019$77,637,115SA-151 THE DESIGN OF THE VIDEO STUDIO ROOM DID NOT INCORPORATE THE ELECTRICAL, HVAC, FLOORING, LIGHTING AND FI…
Mod SA152· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-10+$2,365$77,639,480CONTRACT DRAWINGS DID NOT IDENTIFY THE APPROPRIATE NUMBER OF DOOR OPERATORS. THIS CHANGE WILL INSTALL EIGHT DO…
Mod CO02L· CHANGE ORDER2011-05-16+$21,895$77,661,375CO-02L THE DESIGN OF THE VIDEO STUDIO ROOM DID NOT INCORPORATE THE ELECTRICAL, HVAC, FLOORING, LIGHTING AND FI…
Mod CO02R· CHANGE ORDER2011-05-16+$22,000$77,683,375CO-02R CONTRACT DRAWINGS FAILED TO IDENTIFY THE DOOR OPERATORS. THIS CHANGE WILL INSTALL EIGHT (8) DOOR OPERAT…
Mod CO02S· CHANGE ORDER2011-05-16+$19,580$77,702,955CO-02S DRAWING OF EAST-WEST COLONNADE LIMESTONE ELEVATION WAS NOT COORDINATED WITH THE STRUCTURAL STEEL DRAWI…
Mod SA115· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$13,602$77,716,557SA-115 SINKS WERE CHANGED FROM CENTER DRAIN SINKS TO REAR DRAIN SINKS SO ADEQUATE UNDER SINK SPACE WOULD BE AV…
Mod SA117· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$6,981$77,723,538SA-117 THE CONTRACT DOCUMENTS DID NOT INCLUDE VENTING FOR DRYERS ON LEVELS 3, 4 AND 5.
Mod SA123· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$19,800$77,743,338SA-123 THE CHINA SINK SHROUD SPECIFIED FOR THIS PROJECT WAS NOT LARGE ENOUGH TO ENCLOSE THE P-TRAP, MIXING VAL…
Mod SA127· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$2,000$77,745,338SA-127 DUE TO STRUCTURAL STEEL CONFLICTS IN THE CONTRACT DOCUMENTS, THE FINAL LOCATION OF THE DECK PENETRATION…
Mod SA130· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$766$77,746,104SA-130 THE INWALL SPACE BETWEEN ROOMS 2M249 AND 2M250 IS NOT LARGE ENOUGH TO ACCOMMODATE BACK TO BACK SINK CAR…
Mod SA135· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$14,419$77,760,523SA-135 THE CABINETS WERE SEPARATED INTO TWO CABINETS TO ACCOMMODATE THE SOLID INTERCEPTOR IN ACTIVITY ROOMS ON…
Mod SA136· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$1,473$77,761,996SA-136 CDS SHOW THE 3 WAY VALVE ON THE 3FL, HOWEVER THE 4FL AND 5FL DRAWINGS SHOW ONLY 2 WAY VALVES AT THE END…
Mod SA137· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-16+$4,074$77,766,070SA-136 DISCUSSIONS ON THE PROJECT AND A REPLY TO RFI'S #429 DIRECTED THE CONTRACTOR TO LOWER THE CEILINGS IN R…
Mod CO02V· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-18+$22,216$77,788,286THE EXISTING BATHROOMS 1C118 AND 1C119 ARE LOCATED WITHIN THE SPACE TO BE RENOVATED. THE A/E DID NOT INCLUDE…
Mod SA170· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-22−$88,200$77,700,086DURING REVIEW OF SPEC. SECTION 14210 FOR THE ELEVATORS THE VA IDENTIFIED THAT EXTENDED MAINTENANCE WAS INCLUDE…
Mod CO03E· CHANGE ORDER2011-07-25−$9,200$77,690,886RFIS #935 AND #936 ADDRESSED THE NEED TO DETERMINE ROUTING FOR DUCTWORK ABOVE THE EXISTING LOBBY SPACE IN BLDG…
Mod SA164· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-25+$8,159$77,699,045THE DRAWINGS DID NOT PROVIDE REINFORCING DETAILS FOR THE FOUNTAIN AND PLANTER.
Mod SA166· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-25+$3,410$77,702,455THE DUCTWORK AND OTHER ASSOCIATED CEILING ITEMS WOULD NOT FIT ABOVE THE CEILING IN LOBBY AREA 1M100 AT THE CEI…
Mod SA167· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-25+$36,294$77,738,749THE VAMC DIRECTOR REQUESTED A VA SEAL BE PLACED IN THE LOBBY OF THE NEW CB#29 MAIN LOBBY.
Mod SA168· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-25+$1,164$77,739,913THE VAMC REQUESTED THAT THE MAIN ACCESS DRIVE TO THE PARKING GARAGE REMAIN AS ONE WAY IN LIEU OF BEING CHANGE…
Mod SA169· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-26−$6,153$77,733,760RFI 429 ADDED A 18 X 12 SUPPLY DUCT UNDER STAIR #M5 TO SUPPLY AIR TO THE AREA OF THE LOBBY EAST OF STAIR #M5.…
Mod CO03N· CHANGE ORDER2011-08-02+$4,699$77,738,459MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03N
Mod CO03F· CHANGE ORDER2011-08-15+$11,492$77,749,951THE CAP PIECE ON THE SELF COVING SHEET RUBBER IS HELD IN PLACE BY DOUBLE FACE PAPER TAPE. SECURITY SEALANT WIL…
Mod CO03G· CHANGE ORDER2011-08-15+$300$77,750,251DURING REVIEW OF THE FUEL PIPING OF THE GENERATOR IT WAS NOTED THAT THE FUEL LINE HAS NO ISOLATION VALVE. THIS…
Mod CO02Z· CHANGE ORDER2011-08-17+$1,010$77,751,261CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02Z
Mod CO03D· CHANGE ORDER2011-08-17+$35,000$77,786,261CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-03D
Mod SA162· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-17+$1,224$77,787,485CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-162
Mod SA163· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-17+$7,453$77,794,938CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-163
Mod SA157· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18−$6,154$77,788,784CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-157
Mod SA158· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18+$2,850$77,791,634CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-158
Mod SA159· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18−$15,000$77,776,634CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-159
Mod SA160· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18+$3,312$77,779,946CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, SA-160
Mod CO03H· CHANGE ORDER2011-08-23+$9,862$77,789,808CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-03H
Mod SA173· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-23+$2,866$77,792,674MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-173
Mod SA174· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-23−$24$77,792,650MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-174
Mod CO03I· CHANGE ORDER2011-08-30+$3,400$77,796,050MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA
Mod CO03J· CHANGE ORDER2011-08-30+$6,000$77,802,050MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03J
Mod CO03K· CHANGE ORDER2011-08-30+$6,213$77,808,263MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03K
Mod CO03O· CHANGE ORDER2011-08-30+$950$77,809,213MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03O
Mod CO03P· CHANGE ORDER2011-08-30+$3,500$77,812,713MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03P
Mod CO03Q· CHANGE ORDER2011-08-30+$1,200$77,813,913MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03Q
Mod CO03R· CHANGE ORDER2011-08-30+$13,550$77,827,463MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03R
Mod SA172· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30−$19,031$77,808,432MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-172
Mod SA175· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30+$1,449$77,809,881MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-175
Mod SA176· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30+$13,515$77,823,396MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-176
Mod SA178· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30+$5,018$77,828,414MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-178
Mod SA179· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30+$9,376$77,837,790MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-179
Mod SA184· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-31+$2,036$77,839,826CONTRACT DRAWING AS1-101 IS SHOWN AS A TYPE B WALL A THE SOUTH END OF THE MEN'S LOCKER ROOM. GIVEN THE EXISTIN…
Mod CO02I· CHANGE ORDER2011-09-06+$2,950$77,842,776CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02I
Mod CO02W· CHANGE ORDER2011-09-06+$41,337$77,884,113CARES CONSOLIDATION PHASE 2 MENTAL HEALTH BUILDING, CO-02W
Mod CO03B· CHANGE ORDER2011-09-06+$9,894$77,894,007PITTSBURGH MENTAL HEALTH CLINIC CO-03B
Mod CO03C· CHANGE ORDER2011-09-06+$2,500$77,896,507PITTSBURGH MENTAL HEALTH CLINIC CO-03C
Mod CO03L· CHANGE ORDER2011-09-06+$6,099$77,902,606DURING INITIAL TESTING OF THE GENERATOR THE OUTSIDE AIR LOUVERS OF GENERATOR ROOM WERE NOT ADJUSTED TO OPEN ON…
Mod CO03M· CHANGE ORDER2011-09-06+$617$77,903,223MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA CO-03M
Mod SA171· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-06−$79$77,903,144MENTAL HEALTH PAVILLION BLDG 29, PITTSBURGH, PA
Mod SA177· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-06+$723$77,903,867MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-177
Mod SA180· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-06+$1,905$77,905,772MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-180
Mod SA181· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-06+$1,073$77,906,845MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-181
Mod SA182· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-06+$6,784$77,913,629MENTAL HEALTH PAVILLION BLDG 29 PITTSBURGH, PA SA-182
Mod SA110· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12−$1,724$77,911,905THE FLOOR PLANS SHOW HANDRAILS HR-1 ON THE 3RD, 4TH AND 5TH FLOORS SOUTH WALL OF CORRIDOR XMC104. THIS IS THE…
Mod SA111· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12−$17,813$77,894,092PER RFP D#76 ISSUED ON 8/25/10 DELETE CASEWORK IN 2ND FLOOR ROOMS 2M239, 2M240, 2M264, 2M265, 2M266, 2M269, 2M…
Mod SA119· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12−$11,475$77,882,617COORDINATE EXTERIOR COLORS.
Mod SA121· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$24,061$77,906,678ALL COUNTERTOPS IN CB #29 WERE DESIGNED TO BE SOLID SURFACE COUNTERTOPS; SEVERAL LOCATIONS WERE IDENTIFIED AS…
Mod SA124· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$0$77,906,678DURING THE REVIEW OF RFI 849 IT WAS IDENTIFIED THAT THE ROOM HAS NO LIGHTING FIXTURES SPECIFIED. THIS CHANGE W…
Mod SA125· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$1,797$77,908,475DURING REVIEW OF THE NURSE CALL STATIONS COVER PLATE SUBMITTAL IT WAS IDENTIFIED THAT THE STATIONS ARE NOT FLU…
Mod SA161· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$2,666$77,911,141RFI #802 QUESTIONED THE TOP ELEVATIONS ON A PORTION OF THE BRICK ACCENT WALL ALONG THE EAST SIDE OF THE BUILDI…
Mod SA165· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$897$77,912,038ACTUAL BUILDING EXPANSION JOINT IS AT EXISTING COLUMN LINE 33, NOT AS SHOWN ON SHT AS1-123. THIS LOCATION REQ…
Mod SA183· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-12+$4,321$77,916,359DURING REVIEW OF RFI #248 IT WAS DISCOVERED THAT SOME OF THE TOILET ACCESSORIES SPECIFIED WERE NOT SUITABLE FO…
Mod SA126· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-13+$2,454$77,918,813DURING THE REVIEW OF RFI 857 THE CONTRACTOR IDENTIFIED THE ELECTRICAL PANELS E1B, E1D AND DIS FOR PANEL C1D NO…
Mod SA128· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-13+$887$77,919,700DURING THE OWNER REVIEW OF THE CABLING PAIRS REQUIRED TO SUPPORT THE PHONE SYSTEM AT THE NEW BUILDING #29 THE…
Mod SA142· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-15+$2,500$77,922,200DURING A REVIEW OF THE VA POLICE'S SECURITY MATRIX FOR PRESCRIPTION MEDICATION DISTRIBUTION ROOMS IT WAS DISCO…
Mod SA147· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-15+$920$77,923,120DRAWING OF EAST-WEST COLONNADE LIMESTONE ELEVATION WAS NOT COORDINATED WITH THE STRUCTURAL STEEL DRAWING FOR S…
Mod SA156· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-15+$43,216$77,966,336A BENT STEEL PLATE WAS DESIGNATED TO EXTEND ABOVE FLOOR LEVEL IN FRONT OF CURTAINWALL SPANDREL GLASS AT THE "E…
Mod SA185· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-15+$2,778$77,969,114THE 1FL PUBLIC RESTROOMS DO NOT PROVIDE PRIVACY FOR USERS. AFTER REVIEW IN THE FIELD THE VA REQUESTED PRIVACY…
Mod SA186· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-15+$2,000$77,971,114ADDITIONAL HEAT DETECTORS AND TAMPER SWITCHES ARE REQUIRED FOR THE ELEVATORS FIRE PROTECTION AND SAFETY CODE C…
Mod SA187· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-21+$3,824$77,974,938RFI 941 NOTED THAT EXTERIOR 3X103 RECEIVED A 3/16" SST BENT PLATE OVER THE RAISED SILL AND THAT EXTERIOR DOORS…
Mod SA188· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-27+$2,000$77,976,938THE CONTRACTOR IDENTIFIED EXISTING MEDICAL GAS ALARM WIRING IN THE B#1 LOBBY AS AN OBSTRUCTION TO THEIR WORK I…
Mod SA189· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-27+$0$77,976,938DURING ELEVATOR INSPECTION IT WAS NOTED THAT THE LIGHT FIXTURES SPECIFIED WERE NOT NEMA 4 WEATHERPROOF TYPE FI…
Mod SA191· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-29+$11,236$77,988,174THE CONTRACT DOCUMENTS SHOWED A LEVER LOCKSET AND BUTT HINGES AT THE INPATIENT SHOWER ROOM DOORS. THIS TYPE OF…
Mod SA192· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-29+$645$77,988,819DURING INITIAL TESTING OF THE GENERATOR THE OUTSIDE AIR LOUVERS OF THE GENERATOR ROOM WERE NOT ADJUSTED TO OPE…
Mod SA193· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-29+$1,884$77,990,703THE COLUMNS IN THE EXISTING BUILDING (BLDG 1) DID NOT HAVE SPRAY ON FIRE PROOFING AT COLUMNS 34F, 34G, 35F, 37…
Mod SA194· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-29+$2,195$77,992,898DURING INSPECTION OF THE BATHROOM FLOOR SUB BASE IT WAS FOUND THAT THE EXISTING SUB BASE WAS NOT SUITABLE TO…
Mod SA190· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-30−$46,955$77,945,943CONTRACT DOCUMENTS DID NOT CORRECTLY INCORPORATE NFPA 101 LIFE SAFETY CODE REQUIREMENTS. REVISIONS WERE MADE T…
Mod SA195· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-30+$4,787$77,950,730DURING THE RE REVIEW OF THE HOLLOW METAL DOOR FRAME SUBMITTAL, IT WAS DISCOVERED THAT THE DOOR SIZES WERE 3'-0…
Mod SA196· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-30+$674$77,951,404AN EXISTING FIRE HYDRANT WAS TOO HIGH AND NOT ORIENTED CORRECTLY FOR FIRE DEPARTMENT ACCESS AFTER FINAL SIDEWA…
Mod SA197· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-30+$45,000$77,996,404THE CONTRACT DOCUMENTS INDICATE THAT THE STUDS SHALL BE INSTALLED ON 24" CENTERS. WHEN THE RE QUESTIONED THE…
Mod SA198· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-12+$1,652$77,998,056A PREVIOUS CHANGE IN CEILING HEIGHT LOWERED THE CEILING HEIGHT IN THE ATRIUM CAUSING OBSTRUCTION OF THE ACCESS…
Mod SA200· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-13+$0$77,998,056THE WINDOW BETWEEN THE NURSE WORKROOM XM160A AND THE NURSE STATION XM160 ON THE DAY SIDE OF THE INPATIENT FLOO…
Mod SA201· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-14+$17,493$78,015,549PROVIDE ADDITIONAL LIMESTONE AND BRICK VENEER AT THE PATIENT TOILET ROOM WINDOWS ON FLOORS 3,4 AND 5 AS A RESU…
Mod SA199· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21+$1,275$78,016,824THE SIZE FONT SPECIFIED BY THE CONTRACT FOR THE EXTERIOR TRI-SIGN LOCATED AT THE INTERSECTION OF BRECKENRIDGE…
Mod SA203· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21−$19,486$77,997,338CONTRACT DRAWINGS SHOW WOOD PANELING IN AREAS THAT DID NOT NEED THE PANELING.
Mod SA204· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21+$20,323$78,017,661DURING REVIEW OF THE MARLITE WALL PANELS DETAILS THE VAMC QUESTIONED THE USE OF PORCELAIN BASE ON THE FLOORS,…
Mod SA205· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21+$964$78,018,625RFI 399 ADDRESSED THE CONFLICT WITH THE TIE-IN OF THE FIRST FLOOR VESTIBULE (ADJACENT TO STAIR M4) AND STAIR 7…
Mod SA206· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-26+$10,120$78,028,745CONTRACT DRAWINGS DID NOT PROVIDE DETAILS FOR WATERPROOFING THE FOUNTAINS AT THE PLAZA.
Mod SA208· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-28+$4,388$78,033,133DURING INSTALLATION OF THE ENUNCIATOR PANELS FOR THE FIRE ALARM PANEL IT WAS NOTICED THAT THE EXISTING ENUNCIA…
Mod SA207· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-21+$3,336$78,036,469RFI 937 ADDRESSED THE LAYOUT INFO FOR THE FLAG POLE LIGHT. THE RE RESPONSE DELETED THE TYPE Y1 IN GROUND LIGHT…
Mod SA209· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-22+$1,808$78,038,277THE CAP PIECE OF THE SELF COVING SHEET RUBBER IS HELD IN PLACE BY DOUBLE FACE PAPER TAPE. AROUND THE PLUMBING…
Mod SA210· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-22+$763$78,039,040CHANGES IN FLOORING AT CORRIDOR SOUTH OF STARBUCKS WERE DONE TO ACCOMMODATE FUTURE VAMC PROJECTS THAT WOULD WI…
Mod CO03S· CHANGE ORDER2011-11-29+$67,735$78,106,775IN NOVEMBER 2010 THE VAMC INDICATED THAT THE LOBBY FLOORING WORK THAT WAS SHOWN FOR THE EXISTING B#1 1FL ON TH…
Mod SA211· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-29+$3,764$78,110,539DURING INSPECTION OF BLDG #29 IT WAS NOTED THAT THE OUTSIDE LIGHTING OF THE CONTIGUOUS BLDG #31 WAS NOT ACCEPT…
Mod CO03T· CHANGE ORDER2011-11-30+$10,530$78,121,069DURING INITIAL TESTING OF THE GENERATOR THE OUTSIDE AIR LOUVERS OF THE GENERATOR ROOM WERE NOT ADJUSTED TO OPE…
Mod CO03U· CHANGE ORDER2011-11-30+$61,000$78,182,069CONTRACT DOCUMENTS WERE INCORRECTLY DESIGNED TO COMPLY WITH IBC STANDARDS RATHER THAN NFPA STANDARDS.
Mod SA212· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-30+$6,135$78,188,204THE ADDITION OF SECURITY WALLS WERE NECESSARY IN ORDER TO ISOLATE ONGOING CONSTRUCTION ACTIVITIES AFTER TURNIN…
Mod SA213· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-30+$10,440$78,198,644OPENINGS WERE MADE FOR DOORWAYS INTO EXISTING BLDG #1 FOR CONNECTION TO THE NEW BUILDING #29. ADDITIONAL MASON…
Mod SA214· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-13+$2,097$78,200,741THE MEDICAL CENTER HAS APPROXIMATELY 1050 OCCUPANTS DURING PEAK OCCUPANCY. TO ACHIEVE LEED CERTIFICATION ADDIT…
Mod SA215· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$6,000$78,206,741THE CDS SHOW TWO LEAVES @ THE INPATIENT DOORS ON THE 3FL-5FL. THE FLUSH BOLT ON THE INACTIVE LEAF POSES A HANG…
Mod SA216· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$2,970$78,209,711DURING INITIAL TESTING OF THE GENERATOR THE OUTSIDE AIR LOUVERS OF THE GENERATOR ROOM WERE NOT ADJUSTED TO OPE…
Mod SA217· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$1,001$78,210,712DURING REVIEW OF RFI 900 THE AE FAILED TO SHOW IN THE DRAWINGS THE EMERGENCY VENTS OF THE DAY TANK FOR THE GEN…
Mod SA218· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$0$78,210,712THE VAMC INSTALLED THE AUDIO BOOTHS THAT WERE PREVIOUSLY THE RESPONSIBILITY OF THE CONTRACTOR. THE RESIDENT'…
Mod SA219· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$1,138$78,211,850VAV BOXES IN THE 1FL LOBBY OF THE EXISTING HOSPITAL WERE FOUND TO BE IN THE LOCATION SHOWN ON THE CONTRACT DOC…
Mod SA220· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$18,000$78,229,850CONTRACT DOCUMENTS WERE INCORRECTLY DESIGNED TO COMPLY WITH IBC STANDARDS RATHER THAN NFPA.
Mod SA221· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$26,000$78,255,850THE AMOUNT OF PHASES NECESSARY TO COMPLETE THE EXISTING LOBBY TERRAZZO WORK EXCEEDED THE AMOUNT INCLUDED IN TH…
Mod SA222· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-21+$23,864$78,279,714THE PROJECT CONTRACTOR SUBMITTED RFIS 796, 907 AND 925 REQUESTING DETAILS FOR CONSTRUCTING THE CROSSOVER TIE-I…
Mod SA202· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-09+$14,200$78,293,914CORRIDOR XMC102 IS 4'-0" OVER THE ALLOWABLE DEAD END CORRIDOR DIMENSIONS, THEREFORE, A WALL AND DOOR WITH A LI…
Mod SA223· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-19+$5,714$78,299,628DURING REVIEW OF RFI 818 IT WAS NOTED THAT THE CONTRACT DRAWING SHOWED THE MUFFLER THRU A WALL BUT THE MUFFLER…
Mod SA224· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-09+$1,000$78,300,628RFI 942 REQUESTED INFORMATION FROM THE OWNER TO PROVIDE EXACT LOCATION OF THE OFF NORMAL TEMPERATURE ALARM PAN…
Mod SA225· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-13+$27,764$78,328,392DUCTWORK NEEDED TO BE RECONFIGURED DUE TO EXISTING CEILING CONGESTION.
Mod SA227· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-04+$495$78,328,887DURING INSPECTION AND REVIEW OF THE SOUND READINGS OF 8 (EIGHT) OF THE AUDIOLOGY ROOMS IT WAS NOTICED THAT THE…
Mod CO03V· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-11+$39,084$78,367,971INSTALL SOUND SILENCERS AT EIGHT ROOMS AT THE SECOND FLOOR OF BUILDING 29 AUDIOLOGY AREA.
Mod CO03W· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-20+$2,962$78,370,933THE DOMESTIC HOT WATER HEATING SYSTEM IS NOT PERFORMING PROPERLY AND REQUIRES INVESTIGATION AND SERVICE FROM T…
Mod SA228· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-02−$17,403$78,353,530DEFINITIZES CO-03V = $39,084.00 DATED 5-11-2012. INSTALL SOUND DAMPENING DUCT WORK IN EIGHT HEARING AID FITT…
Mod SA229· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-02+$29,251$78,382,781DEFINITIZES CO-03W = $2,962.00 DATED 7-20-2012. PROVIDE PLUMBER RESOURCES TO DIAGNOSE AND REBALANCE THE HOT…
Mod SA230· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-20+$15,123$78,397,904FINALIZE THE BOND PREMIUM AS ADJUSTED FOR CONTRACT MODIFICATIONS PER VAAR 852.236-88.
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-25+$6,635$78,404,539P00003/SA-231 - INSTALL AN AUTO COOLER AND TRAP PRIMER IN THE CONDENSATE RECEIVER TANK OVERFLOW PIPE.
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-11-26+$7,629$78,412,168P00004/SA-232 - ADJUST VENT PIPING, CHECK ALL STEAM TRAPS, ADJUST RE-SET THE TANK FLOATS, REPAIR DAMAGED PUMP…

Related awards · 9

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI NNNAEYQXKJ35)

AwardOffice · PSC / listingNet obligationsFY
VA101CFMC0136OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y111 · CONSTRUCTION OF OFFICE BUILDINGS$28,493,376FY2011
VA245C0428688-WASHINGTON DC · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$944,731FY2010
V101BC0209OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$3,899,934FY2008
V101BC0223OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · C114 · HOSPITAL BUILDINGS$2,922,053FY2008

Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0167THE R.E.M. ENGINEERING CO INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$384,303FY2011
VA101CFMC0130TTL ASSOCIATES INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$101,742FY2011
VA101CFMC0111WALSH CONSTRUCTION PUERTO RICOOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$52,457,646FY2010
VA101CFMC0085ARCHER WESTERN/DEMARIA JOINT VENTURE IIIOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$58,427,947FY2010
VACFM05I0064N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$114,946FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0014_3600_-NONE-_-NONE- · retrieved 2026-09-26.