Description
SA-039 ISSUED FOR BOND ADJUSTMENT
Base award description: CONSTRUCTION OF MARTINSBURG, WV DATA CENTER
Modification chain · 47 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-30+$32,288,785= $32,288,785
- Mod CO01B2009-04-08+$21,430= $32,310,215
- Mod CO01D2009-05-08+$10,959= $32,321,174
- Mod CO01I2009-09-05+$10,000= $32,331,174
- Mod SA0112009-09-17+$260,049= $32,591,223
- Mod CO01F2009-09-25+$19,800= $32,611,023
- Mod CO01H2009-09-25-$73,000= $32,538,023
- Mod SA0012009-09-25+$2,200= $32,540,223
- Mod SA0022009-09-25+$26,419= $32,566,642
- Mod SA0032009-09-25+$98,133= $32,664,775
- Mod SA0042009-09-25+$92,237= $32,757,012
- Mod SA0052009-09-25+$91,564= $32,848,576
- Mod SA0062009-09-25+$75,649= $32,924,225
- Mod SA0072009-09-25+$3,317= $32,927,542
- Mod SA0082009-09-25+$1,859= $32,929,401
- Mod SA0092009-09-25+$73,844= $33,003,245
- Mod SA0102009-09-25+$3,980= $33,007,225
- Mod SA0142009-09-28-$52,590= $32,954,635
- Mod SA0122009-10-13-$178,197= $32,776,438
- Mod SA0182009-12-30+$38,493= $32,814,931
- Mod SA0192009-12-30+$941= $32,815,872
- Mod SA0202009-12-30+$11,690= $32,827,562
- Mod SA0222010-01-29+$8,830= $32,836,392
- Mod SA0232010-02-25+$23,036= $32,859,428
- Mod SA0242010-04-01+$41,794= $32,901,222
- Mod SA0252010-04-01+$218,191= $33,119,413
- Mod SA0272010-05-27+$35,090= $33,154,503
- Mod CO01J2010-06-01+$20,000= $33,174,503
- Mod CO01A2010-09-13+$14,418= $33,188,921
- Mod SA0152010-09-13+$74,536= $33,263,457
- Mod SA0162010-09-13+$49,867= $33,313,324
- Mod SA0212010-09-13+$10,531= $33,323,855
- Mod SA0172010-09-30+$99,990= $33,423,845
- Mod SA0262010-09-30+$32,226= $33,456,071
- Mod SA0282010-09-30-$2,334= $33,453,737
- Mod SA0292010-09-30+$49,246= $33,502,983
- Mod SA0302010-09-30+$4,500= $33,507,483
- Mod SA0312011-01-14+$1,090,130= $34,597,613
- Mod SA0322011-03-15+$18,064= $34,615,677
- Mod SA0332011-04-08+$79,331= $34,695,008
- Mod SA0342011-05-02-$19,834= $34,675,174
- Mod SA0352011-05-20+$22,581= $34,697,755
- Mod SA0362011-06-02-$36,014= $34,661,741
- Mod SA0372011-06-06+$22,263= $34,684,004
- Mod SA0382011-06-06+$2,300= $34,686,304
- Mod SA0392012-10-01+$8,283= $34,694,587
- Mod P000012016-03-02-$3,620= $34,690,967
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-30 | +$32,288,785 | $32,288,785 | CONSTRUCTION OF MARTINSBURG, WV DATA CENTER |
| Mod CO01B· CHANGE ORDER | 2009-04-08 | +$21,430 | $32,310,215 | CO-01B |
| Mod CO01D· CHANGE ORDER | 2009-05-08 | +$10,959 | $32,321,174 | CO-01D |
| Mod CO01I· CHANGE ORDER | 2009-09-05 | +$10,000 | $32,331,174 | CO-01I, ISSUED FOR ADDITIONAL CONCRETE WORK |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-17 | +$260,049 | $32,591,223 | SA-010 |
| Mod CO01F· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$19,800 | $32,611,023 | CO-01F |
| Mod CO01H· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | −$73,000 | $32,538,023 | CO-01H |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$2,200 | $32,540,223 | SA-001 |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$26,419 | $32,566,642 | SA-002 |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$98,133 | $32,664,775 | SA-003 |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$92,237 | $32,757,012 | SA-004 |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$91,564 | $32,848,576 | SA-005 |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$75,649 | $32,924,225 | SA-006 |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$3,317 | $32,927,542 | SA-007 |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$1,859 | $32,929,401 | SA-008 |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$73,844 | $33,003,245 | SA-009 |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-25 | +$3,980 | $33,007,225 | SA-010 |
| Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-28 | −$52,590 | $32,954,635 | SA-014 |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-13 | −$178,197 | $32,776,438 | SA-012 |
| Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-30 | +$38,493 | $32,814,931 | SA-018 |
| Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-30 | +$941 | $32,815,872 | SA-019 |
| Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-30 | +$11,690 | $32,827,562 | SA-020 |
| Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-29 | +$8,830 | $32,836,392 | CAPITAL REGION READINESS CENTER, MARTINSBURG, WV SA-022 |
| Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-25 | +$23,036 | $32,859,428 | SA-023 |
| Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-01 | +$41,794 | $32,901,222 | SA-024, ISSUED FOR SCIF MODIFICATIONS |
| Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-01 | +$218,191 | $33,119,413 | CAPITAL REGIONAL READINESS CENTER, MARTINSBURG, WV SA-025 |
| Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-27 | +$35,090 | $33,154,503 | SA-027 |
| Mod CO01J· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-01 | +$20,000 | $33,174,503 | CO-01J |
| Mod CO01A· CHANGE ORDER | 2010-09-13 | +$14,418 | $33,188,921 | CONSTRUCTION OF MARTINSBURG, WV DATA CENTER |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-13 | +$74,536 | $33,263,457 | SA-015 |
| Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-13 | +$49,867 | $33,313,324 | SA-016 |
| Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-13 | +$10,531 | $33,323,855 | SA-021 |
| Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$99,990 | $33,423,845 | SA-017 |
| Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$32,226 | $33,456,071 | SA-026 |
| Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | −$2,334 | $33,453,737 | SA-028 |
| Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$49,246 | $33,502,983 | SA-029 |
| Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-30 | +$4,500 | $33,507,483 | SA-030 |
| Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-14 | +$1,090,130 | $34,597,613 | SA-031 ISSUED FOR ELECTRICAL AND OTHER BUILD OUT ITEMS |
| Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-15 | +$18,064 | $34,615,677 | SA-032 ISSUED FOR ADDITIONAL DESIGN FOR AV EQUIPMENT |
| Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$79,331 | $34,695,008 | SA-033 ISSUED FOR ADDITIONAL ELECTRICAL WORK |
| Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-02 | −$19,834 | $34,675,174 | SA-034 ISSUED FOR ADDITIONAL ELECTRICAL WORK AND DELETE SOME ELECTRICAL WORK |
| Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-20 | +$22,581 | $34,697,755 | SA-035 ISSUED TO INSTALL DRAIN FROM DATA MANHOLE |
| Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-02 | −$36,014 | $34,661,741 | SA-036 ISSUED TO DELETE LANDSCAPING |
| Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-06 | +$22,263 | $34,684,004 | SA-037 ISSUED FOR ADDITIONAL WORK IN ROOM 133 |
| Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-06 | +$2,300 | $34,686,304 | SA-038 ISSUED TO CORRECT ACCOUNTING ERROR |
| Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-01 | +$8,283 | $34,694,587 | SA-039 ISSUED FOR BOND ADJUSTMENT |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2016-03-02 | −$3,620 | $34,690,967 | SA-039 ISSUED FOR BOND ADJUSTMENT |
Related awards · 1
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y119 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0244 | SDVE, L.L.C. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $3,139,209 | FY2009 |