Award recordCONTRACT

NATIONAL SERVICES AND HERITAGE CONTRACTING AND K & K INDUSTRIES

PIID VA101CFMC0007· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y199 · CONSTRUCT/MISC BLDGS· FY2008· $15,060,101 net obligations· UEI MA1RQVWDQEH9· MI

Description

BOND PREMIUM ADJUSTMENT FOR CONTRACT CLOSE OUT.

Base award description: PHASE 1B CEMETERY EXPANSION AT GREAT LAKES NATIONAL CEMETERY.

First action · last action
2008-09-23 · 2010-11-23
Transactions
94
First transaction's obligation
$14,565,000
Base + all options value (sum of deltas)
$15,060,101
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
8
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 94 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$15,060,101$0Base award · 2008-09-23 · this action $14,565,000 · running total $14,565,000Modification 1 · 2009-03-13 · this action $16,143 · running total $14,581,143Modification 2 · 2009-03-20 · this action $3,961 · running total $14,585,104Modification 3 · 2009-06-10 · this action $9,598 · running total $14,594,702Modification 10 · 2009-07-09 · this action $2,251 · running total $14,596,952Modification 11 · 2009-07-09 · this action $3,505 · running total $14,600,457Modification 4 · 2009-07-09 · this action $10,544 · running total $14,611,000Modification 5 · 2009-07-09 · this action $9,359 · running total $14,620,360Modification 6 · 2009-07-09 · this action $39,748 · running total $14,660,108Modification 7 · 2009-07-09 · this action $12,773 · running total $14,672,881Modification 8 · 2009-07-09 · this action $6,914 · running total $14,679,794Modification 9 · 2009-07-09 · this action $11,695 · running total $14,691,489Modification 12 · 2009-07-20 · this action $2,530 · running total $14,694,019Modification 13 · 2009-07-20 · this action $1,958 · running total $14,695,977Modification 14 · 2009-07-20 · this action $13,272 · running total $14,709,248Modification 15 · 2009-07-20 · this action -$424 · running total $14,708,824Modification 16 · 2009-07-21 · this action $5,196 · running total $14,714,020Modification 17 · 2009-07-24 · this action $12,307 · running total $14,726,327Modification 18 · 2009-07-24 · this action $5,458 · running total $14,731,785Modification 19 · 2009-07-24 · this action $5,320 · running total $14,737,105Modification 20 · 2009-07-24 · this action $4,085 · running total $14,741,190Modification 21 · 2009-08-03 · this action $16,370 · running total $14,757,559Modification 22 · 2009-08-03 · this action $7,795 · running total $14,765,354Modification 23 · 2009-08-04 · this action $3,053 · running total $14,768,406Modification 24 · 2009-08-04 · this action $10,230 · running total $14,778,636Modification 25 · 2009-09-01 · this action $2,497 · running total $14,781,133Modification 26 · 2009-09-01 · this action $2,258 · running total $14,783,392Modification 27 · 2009-09-01 · this action $4,741 · running total $14,788,133Modification 28 · 2009-09-01 · this action $6,572 · running total $14,794,704Modification 29 · 2009-10-15 · this action $446 · running total $14,795,150Modification 30 · 2009-10-15 · this action $488 · running total $14,795,638Modification 31 · 2009-10-15 · this action $982 · running total $14,796,620Modification 32 · 2009-10-15 · this action $3,130 · running total $14,799,750Modification 33 · 2009-10-28 · this action $9,174 · running total $14,808,924Modification 34 · 2009-10-28 · this action $2,228 · running total $14,811,151Modification 35 · 2009-10-28 · this action $400 · running total $14,811,551Modification 36 · 2009-10-28 · this action $3,190 · running total $14,814,741Modification 37 · 2009-10-28 · this action $29,688 · running total $14,844,429Modification 38 · 2009-10-28 · this action $11,697 · running total $14,856,126Modification 39 · 2009-11-05 · this action $4,031 · running total $14,860,157Modification 40 · 2009-11-05 · this action $10,995 · running total $14,871,151Modification 41 · 2009-11-10 · this action $1,485 · running total $14,872,636Modification 42 · 2009-11-10 · this action $169 · running total $14,872,805Modification 43 · 2009-11-10 · this action $1,650 · running total $14,874,455Modification 44 · 2009-11-10 · this action $308 · running total $14,874,763Modification 45 · 2009-11-10 · this action $1,319 · running total $14,876,082Modification 46 · 2009-11-10 · this action $1,403 · running total $14,877,485Modification 47 · 2009-11-25 · this action $1,910 · running total $14,879,395Modification 48 · 2009-11-25 · this action $715 · running total $14,880,110Modification 49 · 2009-11-25 · this action $4,044 · running total $14,884,154Modification 50 · 2009-11-25 · this action $8,408 · running total $14,892,563Modification 51 · 2009-12-23 · this action $5,070 · running total $14,897,633Modification 52 · 2009-12-23 · this action $5,280 · running total $14,902,913Modification 53 · 2009-12-23 · this action $1,713 · running total $14,904,625Modification 54 · 2009-12-23 · this action $5,630 · running total $14,910,255Modification 55 · 2009-12-23 · this action $6,339 · running total $14,916,594Modification 56 · 2009-12-23 · this action $215 · running total $14,916,809Modification 57 · 2010-01-12 · this action $9,444 · running total $14,926,253Modification 58 · 2010-01-12 · this action $403 · running total $14,926,656Modification 59 · 2010-01-21 · this action $239 · running total $14,926,894Modification 60 · 2010-01-21 · this action $2,414 · running total $14,929,308Modification CO01A · 2010-02-24 · this action $2,000 · running total $14,931,308Modification 61 · 2010-03-10 · this action $239 · running total $14,931,547Modification 62 · 2010-03-10 · this action $6,470 · running total $14,938,017Modification 63 · 2010-03-10 · this action $1,832 · running total $14,939,849Modification 64 · 2010-03-11 · this action $3,135 · running total $14,942,984Modification 65 · 2010-03-15 · this action $2,572 · running total $14,945,555Modification 66 · 2010-03-23 · this action -$1,042 · running total $14,944,514Modification 67 · 2010-04-14 · this action $1,603 · running total $14,946,116Modification 68 · 2010-04-14 · this action -$2,500 · running total $14,943,616Modification 69 · 2010-04-14 · this action $743 · running total $14,944,359Modification 70 · 2010-04-29 · this action $2,024 · running total $14,946,383Modification 71 · 2010-04-29 · this action $2,250 · running total $14,948,632Modification 72 · 2010-04-29 · this action $0 · running total $14,948,632Modification 73 · 2010-05-13 · this action $568 · running total $14,949,200Modification 74 · 2010-05-18 · this action $9,789 · running total $14,958,989Modification 75 · 2010-05-19 · this action $374 · running total $14,959,363Modification 76 · 2010-05-19 · this action $495 · running total $14,959,858Modification 77 · 2010-06-07 · this action $3,762 · running total $14,963,620Modification 78 · 2010-06-07 · this action $616 · running total $14,964,236Modification 79 · 2010-06-16 · this action $897 · running total $14,965,133Modification 80 · 2010-06-16 · this action $1,752 · running total $14,966,885Modification 81 · 2010-06-28 · this action $4,367 · running total $14,971,252Modification 82 · 2010-07-08 · this action $3,366 · running total $14,974,618Modification 84 · 2010-07-08 · this action $75 · running total $14,974,693Modification 83 · 2010-07-19 · this action $11,534 · running total $14,986,226Modification 85 · 2010-07-20 · this action $419 · running total $14,986,645Modification 86 · 2010-08-04 · this action $16,561 · running total $15,003,206Modification 87 · 2010-08-23 · this action $2,558 · running total $15,005,763Modification 88 · 2010-08-23 · this action $3,135 · running total $15,008,898Modification SA089 · 2010-10-25 · this action -$578 · running total $15,008,321Modification SA090 · 2010-10-25 · this action $3,135 · running total $15,011,456Modification SA091 · 2010-11-23 · this action $46,428 · running total $15,057,884Modification SA092 · 2010-11-23 · this action $2,218 · running total $15,060,101
  • Base2008-09-23+$14,565,000= $14,565,000
  • Mod 12009-03-13+$16,143= $14,581,143
  • Mod 22009-03-20+$3,961= $14,585,104
  • Mod 32009-06-10+$9,598= $14,594,702
  • Mod 102009-07-09+$2,251= $14,596,952
  • Mod 112009-07-09+$3,505= $14,600,457
  • Mod 42009-07-09+$10,544= $14,611,000
  • Mod 52009-07-09+$9,359= $14,620,360
  • Mod 62009-07-09+$39,748= $14,660,108
  • Mod 72009-07-09+$12,773= $14,672,881
  • Mod 82009-07-09+$6,914= $14,679,794
  • Mod 92009-07-09+$11,695= $14,691,489
  • Mod 122009-07-20+$2,530= $14,694,019
  • Mod 132009-07-20+$1,958= $14,695,977
  • Mod 142009-07-20+$13,272= $14,709,248
  • Mod 152009-07-20-$424= $14,708,824
  • Mod 162009-07-21+$5,196= $14,714,020
  • Mod 172009-07-24+$12,307= $14,726,327
  • Mod 182009-07-24+$5,458= $14,731,785
  • Mod 192009-07-24+$5,320= $14,737,105
  • Mod 202009-07-24+$4,085= $14,741,190
  • Mod 212009-08-03+$16,370= $14,757,559
  • Mod 222009-08-03+$7,795= $14,765,354
  • Mod 232009-08-04+$3,053= $14,768,406
  • Mod 242009-08-04+$10,230= $14,778,636
  • Mod 252009-09-01+$2,497= $14,781,133
  • Mod 262009-09-01+$2,258= $14,783,392
  • Mod 272009-09-01+$4,741= $14,788,133
  • Mod 282009-09-01+$6,572= $14,794,704
  • Mod 292009-10-15+$446= $14,795,150
  • Mod 302009-10-15+$488= $14,795,638
  • Mod 312009-10-15+$982= $14,796,620
  • Mod 322009-10-15+$3,130= $14,799,750
  • Mod 332009-10-28+$9,174= $14,808,924
  • Mod 342009-10-28+$2,228= $14,811,151
  • Mod 352009-10-28+$400= $14,811,551
  • Mod 362009-10-28+$3,190= $14,814,741
  • Mod 372009-10-28+$29,688= $14,844,429
  • Mod 382009-10-28+$11,697= $14,856,126
  • Mod 392009-11-05+$4,031= $14,860,157
  • Mod 402009-11-05+$10,995= $14,871,151
  • Mod 412009-11-10+$1,485= $14,872,636
  • Mod 422009-11-10+$169= $14,872,805
  • Mod 432009-11-10+$1,650= $14,874,455
  • Mod 442009-11-10+$308= $14,874,763
  • Mod 452009-11-10+$1,319= $14,876,082
  • Mod 462009-11-10+$1,403= $14,877,485
  • Mod 472009-11-25+$1,910= $14,879,395
  • Mod 482009-11-25+$715= $14,880,110
  • Mod 492009-11-25+$4,044= $14,884,154
  • Mod 502009-11-25+$8,408= $14,892,563
  • Mod 512009-12-23+$5,070= $14,897,633
  • Mod 522009-12-23+$5,280= $14,902,913
  • Mod 532009-12-23+$1,713= $14,904,625
  • Mod 542009-12-23+$5,630= $14,910,255
  • Mod 552009-12-23+$6,339= $14,916,594
  • Mod 562009-12-23+$215= $14,916,809
  • Mod 572010-01-12+$9,444= $14,926,253
  • Mod 582010-01-12+$403= $14,926,656
  • Mod 592010-01-21+$239= $14,926,894
  • Mod 602010-01-21+$2,414= $14,929,308
  • Mod CO01A2010-02-24+$2,000= $14,931,308
  • Mod 612010-03-10+$239= $14,931,547
  • Mod 622010-03-10+$6,470= $14,938,017
  • Mod 632010-03-10+$1,832= $14,939,849
  • Mod 642010-03-11+$3,135= $14,942,984
  • Mod 652010-03-15+$2,572= $14,945,555
  • Mod 662010-03-23-$1,042= $14,944,514
  • Mod 672010-04-14+$1,603= $14,946,116
  • Mod 682010-04-14-$2,500= $14,943,616
  • Mod 692010-04-14+$743= $14,944,359
  • Mod 702010-04-29+$2,024= $14,946,383
  • Mod 712010-04-29+$2,250= $14,948,632
  • Mod 722010-04-29+$0= $14,948,632
  • Mod 732010-05-13+$568= $14,949,200
  • Mod 742010-05-18+$9,789= $14,958,989
  • Mod 752010-05-19+$374= $14,959,363
  • Mod 762010-05-19+$495= $14,959,858
  • Mod 772010-06-07+$3,762= $14,963,620
  • Mod 782010-06-07+$616= $14,964,236
  • Mod 792010-06-16+$897= $14,965,133
  • Mod 802010-06-16+$1,752= $14,966,885
  • Mod 812010-06-28+$4,367= $14,971,252
  • Mod 822010-07-08+$3,366= $14,974,618
  • Mod 842010-07-08+$75= $14,974,693
  • Mod 832010-07-19+$11,534= $14,986,226
  • Mod 852010-07-20+$419= $14,986,645
  • Mod 862010-08-04+$16,561= $15,003,206
  • Mod 872010-08-23+$2,558= $15,005,763
  • Mod 882010-08-23+$3,135= $15,008,898
  • Mod SA0892010-10-25-$578= $15,008,321
  • Mod SA0902010-10-25+$3,135= $15,011,456
  • Mod SA0912010-11-23+$46,428= $15,057,884
  • Mod SA0922010-11-23+$2,218= $15,060,101
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2008-09-23+$14,565,000$14,565,000PHASE 1B CEMETERY EXPANSION AT GREAT LAKES NATIONAL CEMETERY.
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-03-13+$16,143$14,581,143A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $16,14…
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-03-20+$3,961$14,585,104A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $3,961…
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-10+$9,598$14,594,702TOTAL CONTRACT PRICE IS INCREASED BY $9,597.50 AND 0 DAY(S) ADDITIONAL CONTRACT TIME. PRESERVATION OF ARCHEOLO…
Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$2,251$14,596,952A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,250.60…
Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$3,505$14,600,457A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $3,504.59…
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$10,544$14,611,000A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $10,543.6…
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$9,359$14,620,360A. GREAT LAKES NATIONAL CEMETERY,PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $9,359.35 AND 0 D…
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$39,748$14,660,108A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $39,747.9…
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$12,773$14,672,881A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $12,773.2…
Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$6,914$14,679,794A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $6,913.50…
Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-09+$11,695$14,691,489A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $11,694.5…
Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-20+$2,530$14,694,019A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,530.00…
Mod 13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-20+$1,958$14,695,977A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $1,958.00…
Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-20+$13,272$14,709,248A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $13,271.5…
Mod 15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-20−$424$14,708,824A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY -424.00 A…
Mod 16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-21+$5,196$14,714,020A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,195.85…
Mod 17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-24+$12,307$14,726,327A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $12,307.0…
Mod 18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-24+$5,458$14,731,785A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,458.20…
Mod 19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-24+$5,320$14,737,105A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,319.60…
Mod 20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-24+$4,085$14,741,190A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $4,084.75…
Mod 21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-03+$16,370$14,757,559A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $16,369.6…
Mod 22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-03+$7,795$14,765,354A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $7,794.60…
Mod 23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-04+$3,053$14,768,406A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $3,052.50…
Mod 24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-04+$10,230$14,778,636A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $10,230.0…
Mod 25· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-01+$2,497$14,781,133A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,497.00…
Mod 26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-01+$2,258$14,783,392A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,258.30…
Mod 27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-01+$4,741$14,788,133A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $4,741.00…
Mod 28· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-01+$6,572$14,794,704A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $6,571.66…
Mod 29· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-15+$446$14,795,150ADD TILE IN ADMIN BUILDING
Mod 30· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-15+$488$14,795,638NEW SIGN PANEL FOR EXISTING VISITORS SIGN
Mod 31· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-15+$982$14,796,620CHANGE LOCK CORE HOUSING - ADMIN BLDG
Mod 32· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-15+$3,130$14,799,750MONUMENTS IN SECTION 4
Mod 33· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$9,174$14,808,924SOD ADMIN BUILDING
Mod 34· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$2,228$14,811,151ADD'S FENCING
Mod 35· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$400$14,811,551EXTEND IRRIGATION SYSTEM
Mod 36· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$3,190$14,814,741ADD CONCRETE PADS
Mod 37· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$29,688$14,844,429TRENCH DRAIN REVISIONS
Mod 38· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-10-28+$11,697$14,856,126ADDITION OF SOD AND SEED
Mod 39· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-05+$4,031$14,860,157BARRIER FREE MODIFICATIONS AT ASSEMBLY AREA CROSSWALK FROM THE PARKING LOT.
Mod 40· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-05+$10,995$14,871,151ADD INSULATION FOR MAINTENANCE GARAGE ROOF
Mod 41· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$1,485$14,872,636ADD GRAVEL STRIP AT ASSISTANT DIRECTOR'S OFFICE
Mod 42· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$169$14,872,805ADD TWO EMERGENCY EXIST SIGNS AT ADMINISTRATION BUILDING
Mod 43· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$1,650$14,874,455CAULK EXPANSION JOINTS NOT SHOWN ON PLANS AT THE MAINTENANCE GARAGE
Mod 44· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$308$14,874,763ADD PLANTS AT ADMINISTRATION BUILDING
Mod 45· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$1,319$14,876,082ADD GLASS GLOBES AND BREAKER TO PIC/MAINT. BLDG.
Mod 46· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-10+$1,403$14,877,485FURNISH AND INSTALL 2 MONITORS @ ADMIN. BLDG.
Mod 47· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-25+$1,910$14,879,395INSTALL PULL STRING TO CARILLON TOWER
Mod 48· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-25+$715$14,880,110RAISE EXISTING STRUCTURES @ ADMIN BLDG.
Mod 49· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-25+$4,044$14,884,154ADD WINDOW FLASHING AT ADMIN BLDG
Mod 50· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-11-25+$8,408$14,892,563NEW GAS PIPING & WATER IN MAINT OFFICE
Mod 51· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$5,070$14,897,633FENCE RELOCATION AND ADDITION AT MAINTENANCE AREA.
Mod 52· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$5,280$14,902,913REMOVE AND INSTALL FENCING AT CONTRACTOR STORAGE PARKING LOT.
Mod 53· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$1,713$14,904,625ADD DIRECTIONAL SIGN TO THE MAIN DRIVE DIRECTLY SOUTH OF THE CORTEGE DRIVE
Mod 54· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$5,630$14,910,255VOICE/DATA CONNECTION FOR MAINTENANCE BLDG. TO ADMIN. BLDG
Mod 55· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$6,339$14,916,594SEPTIC TANK PUMPING AT ADMIN BLDG
Mod 56· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-12-23+$215$14,916,809REWORK DOOR HARDWARE IN ADMIN BLDG @P100
Mod 57· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-01-12+$9,444$14,926,253WINTER CONSTRUCTION - COLUMBARIUM COURT 2
Mod 58· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-01-12+$403$14,926,656PHONE SYSTEM CONFIGURATION CHANGES
Mod 59· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-01-21+$239$14,926,894TROUBLESHOOT PHONE LINES TO FIRE ALARM SYSTEM
Mod 60· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-01-21+$2,414$14,929,308SUPPLY NEW POWER WASHER FOR MAINT BUILDING.
Mod CO01A· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-02-24+$2,000$14,931,308SNOW PLOWING - NORTHWEST ROAD & COLUMBARIUM DRIVE.
Mod 61· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-10+$239$14,931,547TROUBLESHOOT VOICE/DATA CONNECTION
Mod 62· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-10+$6,470$14,938,017ADDED TESTING SERVICES FOR ROAD UNDERCUT
Mod 63· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-10+$1,832$14,939,849ADD IRRIGATION AT COLUMBARIUM
Mod 64· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-11+$3,135$14,942,984SEPTIC TANK PUMPING AT ADMINISTRATION BLDG.
Mod 65· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-15+$2,572$14,945,555MISC SURVEY/LAYOUT CHARGES
Mod 66· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-03-23−$1,042$14,944,514CREDIT FOR MC CABLE USE IN ADMIN BLDG
Mod 67· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-04-14+$1,603$14,946,116SNOW PLOWING - NW ROAD & COLUMBARIUM
Mod 68· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-04-14−$2,500$14,943,616NEOPRENE WASHER CREDIT @ COLUMBARIUM
Mod 69· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-04-14+$743$14,944,359CORTEGE DRIVE LANE STRIPING
Mod 70· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-04-29+$2,024$14,946,383ADDITIONAL IRRIGATION AT MAINTENANCE AREA
Mod 71· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-04-29+$2,250$14,948,632RESTORATION OF FORMER ADMIN TRAILER AREA
Mod 72· CHANGE ORDER2010-04-29+$0$14,948,632ASPHALT PAVING MIX CHANGE
Mod 73· CHANGE ORDER2010-05-13+$568$14,949,200ADD ASTRAGALS TO TWO ADMIN BLDG DOORS
Mod 74· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-05-18+$9,789$14,958,989ELECTRICAL POWER FOR IRRIGATION @ COLUMBARIUM
Mod 75· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-05-19+$374$14,959,363RELOCATE MOTION SENOSRS IN MAINT. GARAGE
Mod 76· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-05-19+$495$14,959,858SCATTERING GARDEN REPAIRS
Mod 77· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-06-07+$3,762$14,963,620SEPTIC TANK PUMPING
Mod 78· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-06-07+$616$14,964,236MODIFY EXISTING SIGN FOUNDATIONS
Mod 79· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-06-16+$897$14,965,133TOILET TRAILER REPAIR
Mod 80· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-06-16+$1,752$14,966,885TV/CLEANOUT ADMIN BLDG SANITARY LINE
Mod 81· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-06-28+$4,367$14,971,252ADD STONE TO GRAVEL HAUL ROAD
Mod 82· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-07-08+$3,366$14,974,618MISC. LANDSCAPE ITEMS
Mod 84· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-07-08+$75$14,974,693PROVIDE LOCKSMITH SERVICES @ CONT STORAGE
Mod 83· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-07-19+$11,534$14,986,226ADDITIONS OF GATES AND FENCING
Mod 85· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-07-20+$419$14,986,645REPLACE BRUSH SWEEPS AT ADMIN DOORS
Mod 86· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-08-04+$16,561$15,003,206ADDITIONAL DRAINAGE STRUCTURES IN SECTION 11 AND 12
Mod 87· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-08-23+$2,558$15,005,763GRADE REVISION AND RESTORATION @ SIGNS
Mod 88· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2010-08-23+$3,135$15,008,898SEPTIC TANK PUMPING
Mod SA089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-10-25−$578$15,008,321CREDIT ADJUSTMENT FOR SA-086 TO ACCOUNT FOR THE ELIMINATION OF ONE CATCH BASIN.
Mod SA090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-10-25+$3,135$15,011,456PUMP THE SEPTIC TANKS AT THE ADMINISTRATION BUILDING FROM 8/31/10 TO 10/19/10 (5 EVENTS TOTAL).
Mod SA091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-23+$46,428$15,057,884SA-091 IS WRITTEN TO RESOLVE THE FINAL THREE REMAINING CONTRACTOR ITEMS THAT HAVE BEEN SUBMITTED FOR REIMBURSE…
Mod SA092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-23+$2,218$15,060,101BOND PREMIUM ADJUSTMENT FOR CONTRACT CLOSE OUT.

Related awards · 2

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y199 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0144IMPERIAL CONSTRUCTION & ELECTRIC INC.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$827,752FY2011
VA101CFMC0075AFFILIATED WESTERN, INC.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$0FY2009

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0007_3600_-NONE-_-NONE- · retrieved 2026-09-26.