Description
BOND PREMIUM ADJUSTMENT FOR CONTRACT CLOSE OUT.
Base award description: PHASE 1B CEMETERY EXPANSION AT GREAT LAKES NATIONAL CEMETERY.
Modification chain · 94 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-23+$14,565,000= $14,565,000
- Mod 12009-03-13+$16,143= $14,581,143
- Mod 22009-03-20+$3,961= $14,585,104
- Mod 32009-06-10+$9,598= $14,594,702
- Mod 102009-07-09+$2,251= $14,596,952
- Mod 112009-07-09+$3,505= $14,600,457
- Mod 42009-07-09+$10,544= $14,611,000
- Mod 52009-07-09+$9,359= $14,620,360
- Mod 62009-07-09+$39,748= $14,660,108
- Mod 72009-07-09+$12,773= $14,672,881
- Mod 82009-07-09+$6,914= $14,679,794
- Mod 92009-07-09+$11,695= $14,691,489
- Mod 122009-07-20+$2,530= $14,694,019
- Mod 132009-07-20+$1,958= $14,695,977
- Mod 142009-07-20+$13,272= $14,709,248
- Mod 152009-07-20-$424= $14,708,824
- Mod 162009-07-21+$5,196= $14,714,020
- Mod 172009-07-24+$12,307= $14,726,327
- Mod 182009-07-24+$5,458= $14,731,785
- Mod 192009-07-24+$5,320= $14,737,105
- Mod 202009-07-24+$4,085= $14,741,190
- Mod 212009-08-03+$16,370= $14,757,559
- Mod 222009-08-03+$7,795= $14,765,354
- Mod 232009-08-04+$3,053= $14,768,406
- Mod 242009-08-04+$10,230= $14,778,636
- Mod 252009-09-01+$2,497= $14,781,133
- Mod 262009-09-01+$2,258= $14,783,392
- Mod 272009-09-01+$4,741= $14,788,133
- Mod 282009-09-01+$6,572= $14,794,704
- Mod 292009-10-15+$446= $14,795,150
- Mod 302009-10-15+$488= $14,795,638
- Mod 312009-10-15+$982= $14,796,620
- Mod 322009-10-15+$3,130= $14,799,750
- Mod 332009-10-28+$9,174= $14,808,924
- Mod 342009-10-28+$2,228= $14,811,151
- Mod 352009-10-28+$400= $14,811,551
- Mod 362009-10-28+$3,190= $14,814,741
- Mod 372009-10-28+$29,688= $14,844,429
- Mod 382009-10-28+$11,697= $14,856,126
- Mod 392009-11-05+$4,031= $14,860,157
- Mod 402009-11-05+$10,995= $14,871,151
- Mod 412009-11-10+$1,485= $14,872,636
- Mod 422009-11-10+$169= $14,872,805
- Mod 432009-11-10+$1,650= $14,874,455
- Mod 442009-11-10+$308= $14,874,763
- Mod 452009-11-10+$1,319= $14,876,082
- Mod 462009-11-10+$1,403= $14,877,485
- Mod 472009-11-25+$1,910= $14,879,395
- Mod 482009-11-25+$715= $14,880,110
- Mod 492009-11-25+$4,044= $14,884,154
- Mod 502009-11-25+$8,408= $14,892,563
- Mod 512009-12-23+$5,070= $14,897,633
- Mod 522009-12-23+$5,280= $14,902,913
- Mod 532009-12-23+$1,713= $14,904,625
- Mod 542009-12-23+$5,630= $14,910,255
- Mod 552009-12-23+$6,339= $14,916,594
- Mod 562009-12-23+$215= $14,916,809
- Mod 572010-01-12+$9,444= $14,926,253
- Mod 582010-01-12+$403= $14,926,656
- Mod 592010-01-21+$239= $14,926,894
- Mod 602010-01-21+$2,414= $14,929,308
- Mod CO01A2010-02-24+$2,000= $14,931,308
- Mod 612010-03-10+$239= $14,931,547
- Mod 622010-03-10+$6,470= $14,938,017
- Mod 632010-03-10+$1,832= $14,939,849
- Mod 642010-03-11+$3,135= $14,942,984
- Mod 652010-03-15+$2,572= $14,945,555
- Mod 662010-03-23-$1,042= $14,944,514
- Mod 672010-04-14+$1,603= $14,946,116
- Mod 682010-04-14-$2,500= $14,943,616
- Mod 692010-04-14+$743= $14,944,359
- Mod 702010-04-29+$2,024= $14,946,383
- Mod 712010-04-29+$2,250= $14,948,632
- Mod 722010-04-29+$0= $14,948,632
- Mod 732010-05-13+$568= $14,949,200
- Mod 742010-05-18+$9,789= $14,958,989
- Mod 752010-05-19+$374= $14,959,363
- Mod 762010-05-19+$495= $14,959,858
- Mod 772010-06-07+$3,762= $14,963,620
- Mod 782010-06-07+$616= $14,964,236
- Mod 792010-06-16+$897= $14,965,133
- Mod 802010-06-16+$1,752= $14,966,885
- Mod 812010-06-28+$4,367= $14,971,252
- Mod 822010-07-08+$3,366= $14,974,618
- Mod 842010-07-08+$75= $14,974,693
- Mod 832010-07-19+$11,534= $14,986,226
- Mod 852010-07-20+$419= $14,986,645
- Mod 862010-08-04+$16,561= $15,003,206
- Mod 872010-08-23+$2,558= $15,005,763
- Mod 882010-08-23+$3,135= $15,008,898
- Mod SA0892010-10-25-$578= $15,008,321
- Mod SA0902010-10-25+$3,135= $15,011,456
- Mod SA0912010-11-23+$46,428= $15,057,884
- Mod SA0922010-11-23+$2,218= $15,060,101
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-23 | +$14,565,000 | $14,565,000 | PHASE 1B CEMETERY EXPANSION AT GREAT LAKES NATIONAL CEMETERY. |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-03-13 | +$16,143 | $14,581,143 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $16,14… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-03-20 | +$3,961 | $14,585,104 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $3,961… |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-10 | +$9,598 | $14,594,702 | TOTAL CONTRACT PRICE IS INCREASED BY $9,597.50 AND 0 DAY(S) ADDITIONAL CONTRACT TIME. PRESERVATION OF ARCHEOLO… |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$2,251 | $14,596,952 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,250.60… |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$3,505 | $14,600,457 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $3,504.59… |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$10,544 | $14,611,000 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $10,543.6… |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$9,359 | $14,620,360 | A. GREAT LAKES NATIONAL CEMETERY,PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE IS INCREASED BY $9,359.35 AND 0 D… |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$39,748 | $14,660,108 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $39,747.9… |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$12,773 | $14,672,881 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $12,773.2… |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$6,914 | $14,679,794 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $6,913.50… |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$11,695 | $14,691,489 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $11,694.5… |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-20 | +$2,530 | $14,694,019 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,530.00… |
| Mod 13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-20 | +$1,958 | $14,695,977 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $1,958.00… |
| Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-20 | +$13,272 | $14,709,248 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $13,271.5… |
| Mod 15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-20 | −$424 | $14,708,824 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY -424.00 A… |
| Mod 16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-21 | +$5,196 | $14,714,020 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,195.85… |
| Mod 17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-24 | +$12,307 | $14,726,327 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $12,307.0… |
| Mod 18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-24 | +$5,458 | $14,731,785 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,458.20… |
| Mod 19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-24 | +$5,320 | $14,737,105 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $5,319.60… |
| Mod 20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-24 | +$4,085 | $14,741,190 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $4,084.75… |
| Mod 21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-03 | +$16,370 | $14,757,559 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $16,369.6… |
| Mod 22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-03 | +$7,795 | $14,765,354 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $7,794.60… |
| Mod 23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-04 | +$3,053 | $14,768,406 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $3,052.50… |
| Mod 24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-04 | +$10,230 | $14,778,636 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $10,230.0… |
| Mod 25· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-01 | +$2,497 | $14,781,133 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,497.00… |
| Mod 26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-01 | +$2,258 | $14,783,392 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $2,258.30… |
| Mod 27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-01 | +$4,741 | $14,788,133 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $4,741.00… |
| Mod 28· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-01 | +$6,572 | $14,794,704 | A. GREAT LAKES NATIONAL CEMETERY EXPANSION, PHASE 1B, HOLLY, MI B. TOTAL CONTRACT PRICE INCREASED BY $6,571.66… |
| Mod 29· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-15 | +$446 | $14,795,150 | ADD TILE IN ADMIN BUILDING |
| Mod 30· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-15 | +$488 | $14,795,638 | NEW SIGN PANEL FOR EXISTING VISITORS SIGN |
| Mod 31· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-15 | +$982 | $14,796,620 | CHANGE LOCK CORE HOUSING - ADMIN BLDG |
| Mod 32· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-15 | +$3,130 | $14,799,750 | MONUMENTS IN SECTION 4 |
| Mod 33· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$9,174 | $14,808,924 | SOD ADMIN BUILDING |
| Mod 34· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$2,228 | $14,811,151 | ADD'S FENCING |
| Mod 35· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$400 | $14,811,551 | EXTEND IRRIGATION SYSTEM |
| Mod 36· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$3,190 | $14,814,741 | ADD CONCRETE PADS |
| Mod 37· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$29,688 | $14,844,429 | TRENCH DRAIN REVISIONS |
| Mod 38· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-28 | +$11,697 | $14,856,126 | ADDITION OF SOD AND SEED |
| Mod 39· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-05 | +$4,031 | $14,860,157 | BARRIER FREE MODIFICATIONS AT ASSEMBLY AREA CROSSWALK FROM THE PARKING LOT. |
| Mod 40· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-05 | +$10,995 | $14,871,151 | ADD INSULATION FOR MAINTENANCE GARAGE ROOF |
| Mod 41· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$1,485 | $14,872,636 | ADD GRAVEL STRIP AT ASSISTANT DIRECTOR'S OFFICE |
| Mod 42· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$169 | $14,872,805 | ADD TWO EMERGENCY EXIST SIGNS AT ADMINISTRATION BUILDING |
| Mod 43· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$1,650 | $14,874,455 | CAULK EXPANSION JOINTS NOT SHOWN ON PLANS AT THE MAINTENANCE GARAGE |
| Mod 44· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$308 | $14,874,763 | ADD PLANTS AT ADMINISTRATION BUILDING |
| Mod 45· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$1,319 | $14,876,082 | ADD GLASS GLOBES AND BREAKER TO PIC/MAINT. BLDG. |
| Mod 46· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-10 | +$1,403 | $14,877,485 | FURNISH AND INSTALL 2 MONITORS @ ADMIN. BLDG. |
| Mod 47· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-25 | +$1,910 | $14,879,395 | INSTALL PULL STRING TO CARILLON TOWER |
| Mod 48· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-25 | +$715 | $14,880,110 | RAISE EXISTING STRUCTURES @ ADMIN BLDG. |
| Mod 49· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-25 | +$4,044 | $14,884,154 | ADD WINDOW FLASHING AT ADMIN BLDG |
| Mod 50· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-11-25 | +$8,408 | $14,892,563 | NEW GAS PIPING & WATER IN MAINT OFFICE |
| Mod 51· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$5,070 | $14,897,633 | FENCE RELOCATION AND ADDITION AT MAINTENANCE AREA. |
| Mod 52· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$5,280 | $14,902,913 | REMOVE AND INSTALL FENCING AT CONTRACTOR STORAGE PARKING LOT. |
| Mod 53· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$1,713 | $14,904,625 | ADD DIRECTIONAL SIGN TO THE MAIN DRIVE DIRECTLY SOUTH OF THE CORTEGE DRIVE |
| Mod 54· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$5,630 | $14,910,255 | VOICE/DATA CONNECTION FOR MAINTENANCE BLDG. TO ADMIN. BLDG |
| Mod 55· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$6,339 | $14,916,594 | SEPTIC TANK PUMPING AT ADMIN BLDG |
| Mod 56· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-12-23 | +$215 | $14,916,809 | REWORK DOOR HARDWARE IN ADMIN BLDG @P100 |
| Mod 57· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-12 | +$9,444 | $14,926,253 | WINTER CONSTRUCTION - COLUMBARIUM COURT 2 |
| Mod 58· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-12 | +$403 | $14,926,656 | PHONE SYSTEM CONFIGURATION CHANGES |
| Mod 59· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-21 | +$239 | $14,926,894 | TROUBLESHOOT PHONE LINES TO FIRE ALARM SYSTEM |
| Mod 60· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-21 | +$2,414 | $14,929,308 | SUPPLY NEW POWER WASHER FOR MAINT BUILDING. |
| Mod CO01A· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-02-24 | +$2,000 | $14,931,308 | SNOW PLOWING - NORTHWEST ROAD & COLUMBARIUM DRIVE. |
| Mod 61· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-10 | +$239 | $14,931,547 | TROUBLESHOOT VOICE/DATA CONNECTION |
| Mod 62· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-10 | +$6,470 | $14,938,017 | ADDED TESTING SERVICES FOR ROAD UNDERCUT |
| Mod 63· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-10 | +$1,832 | $14,939,849 | ADD IRRIGATION AT COLUMBARIUM |
| Mod 64· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-11 | +$3,135 | $14,942,984 | SEPTIC TANK PUMPING AT ADMINISTRATION BLDG. |
| Mod 65· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-15 | +$2,572 | $14,945,555 | MISC SURVEY/LAYOUT CHARGES |
| Mod 66· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-23 | −$1,042 | $14,944,514 | CREDIT FOR MC CABLE USE IN ADMIN BLDG |
| Mod 67· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-14 | +$1,603 | $14,946,116 | SNOW PLOWING - NW ROAD & COLUMBARIUM |
| Mod 68· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-14 | −$2,500 | $14,943,616 | NEOPRENE WASHER CREDIT @ COLUMBARIUM |
| Mod 69· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-14 | +$743 | $14,944,359 | CORTEGE DRIVE LANE STRIPING |
| Mod 70· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-29 | +$2,024 | $14,946,383 | ADDITIONAL IRRIGATION AT MAINTENANCE AREA |
| Mod 71· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-29 | +$2,250 | $14,948,632 | RESTORATION OF FORMER ADMIN TRAILER AREA |
| Mod 72· CHANGE ORDER | 2010-04-29 | +$0 | $14,948,632 | ASPHALT PAVING MIX CHANGE |
| Mod 73· CHANGE ORDER | 2010-05-13 | +$568 | $14,949,200 | ADD ASTRAGALS TO TWO ADMIN BLDG DOORS |
| Mod 74· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-18 | +$9,789 | $14,958,989 | ELECTRICAL POWER FOR IRRIGATION @ COLUMBARIUM |
| Mod 75· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-19 | +$374 | $14,959,363 | RELOCATE MOTION SENOSRS IN MAINT. GARAGE |
| Mod 76· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-05-19 | +$495 | $14,959,858 | SCATTERING GARDEN REPAIRS |
| Mod 77· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-07 | +$3,762 | $14,963,620 | SEPTIC TANK PUMPING |
| Mod 78· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-07 | +$616 | $14,964,236 | MODIFY EXISTING SIGN FOUNDATIONS |
| Mod 79· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-16 | +$897 | $14,965,133 | TOILET TRAILER REPAIR |
| Mod 80· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-16 | +$1,752 | $14,966,885 | TV/CLEANOUT ADMIN BLDG SANITARY LINE |
| Mod 81· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-28 | +$4,367 | $14,971,252 | ADD STONE TO GRAVEL HAUL ROAD |
| Mod 82· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-08 | +$3,366 | $14,974,618 | MISC. LANDSCAPE ITEMS |
| Mod 84· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-08 | +$75 | $14,974,693 | PROVIDE LOCKSMITH SERVICES @ CONT STORAGE |
| Mod 83· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-19 | +$11,534 | $14,986,226 | ADDITIONS OF GATES AND FENCING |
| Mod 85· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-20 | +$419 | $14,986,645 | REPLACE BRUSH SWEEPS AT ADMIN DOORS |
| Mod 86· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-04 | +$16,561 | $15,003,206 | ADDITIONAL DRAINAGE STRUCTURES IN SECTION 11 AND 12 |
| Mod 87· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-23 | +$2,558 | $15,005,763 | GRADE REVISION AND RESTORATION @ SIGNS |
| Mod 88· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-23 | +$3,135 | $15,008,898 | SEPTIC TANK PUMPING |
| Mod SA089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-25 | −$578 | $15,008,321 | CREDIT ADJUSTMENT FOR SA-086 TO ACCOUNT FOR THE ELIMINATION OF ONE CATCH BASIN. |
| Mod SA090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-25 | +$3,135 | $15,011,456 | PUMP THE SEPTIC TANKS AT THE ADMINISTRATION BUILDING FROM 8/31/10 TO 10/19/10 (5 EVENTS TOTAL). |
| Mod SA091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-23 | +$46,428 | $15,057,884 | SA-091 IS WRITTEN TO RESOLVE THE FINAL THREE REMAINING CONTRACTOR ITEMS THAT HAVE BEEN SUBMITTED FOR REIMBURSE… |
| Mod SA092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-23 | +$2,218 | $15,060,101 | BOND PREMIUM ADJUSTMENT FOR CONTRACT CLOSE OUT. |
Related awards · 2
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y199 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0144 | IMPERIAL CONSTRUCTION & ELECTRIC INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $827,752 | FY2011 |
| VA101CFMC0075 | AFFILIATED WESTERN, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $0 | FY2009 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0007_3600_-NONE-_-NONE- · retrieved 2026-09-26.