Description
INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. SA-007 ISSUED FOR BOND ADJUSTMENT.
Base award description: INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA.
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-24+$4,324,937= $4,324,937
- Mod SA0012009-07-09+$130,076= $4,455,013
- Mod SA0022009-11-06+$197,506= $4,652,519
- Mod SA0042011-04-05+$239,818= $4,892,337
- Mod SA0062011-11-28+$226,285= $5,118,622
- Mod SA0072011-12-21+$7,546= $5,126,168
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-24 | +$4,324,937 | $4,324,937 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-09 | +$130,076 | $4,455,013 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-06 | +$197,506 | $4,652,519 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-05 | +$239,818 | $4,892,337 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. SA-004 ISSUED FOR PIP… |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-28 | +$226,285 | $5,118,622 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-21 | +$7,546 | $5,126,168 | INTERIM POLYTRAUMA RENOVATION 5-WEST AT THE JAMES A. HALEY VA HOSPITAL IN TAMPA FLORIDA. SA-007 ISSUED FOR BON… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MQTRV3XU9LZ3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA673C10244 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $37,667 | FY2011 |
| VA673C00325 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $1,000 | FY2010 |
| VA248C1359 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $0 | FY2010 |
| V598C95448 | 598S-NORTH LITTLE ROCK SMALL PURCHASE · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $11,627 | FY2009 |
| VA248C0939 | 548-WEST PALM · Z119 · MAINT-REP-ALT/OTHER ADMIN BLDGS | $3,019,751 | FY2009 |
| VA248C0534 | 673-TAMPA · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $162,799 | FY2008 |
Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0167 | THE R.E.M. ENGINEERING CO INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $384,303 | FY2011 |
| VA101CFMC0130 | TTL ASSOCIATES INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $101,742 | FY2011 |
| VA101CFMC0111 | WALSH CONSTRUCTION PUERTO RICO | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $52,457,646 | FY2010 |
| VA101CFMC0085 | ARCHER WESTERN/DEMARIA JOINT VENTURE III | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $58,427,947 | FY2010 |
| VACFM05I0064 | N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $114,946 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0006_3600_-NONE-_-NONE- · retrieved 2026-09-26.