Award recordCONTRACT

SCHNEIDER ELECTRIC USA, INC.

PIID VA101C95132· VA Staff Offices· PCAC NATIONAL ENERGY BUSINESS CENTER· N059 · INSTALLATION OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS· FY2009· $19,537,227 net obligations· UEI S8DVLUWG7KQ5· IL

Description

ADVANCED ELECTRICAL METERING PROJECT - 59 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THROUGHOUT ALL VISN'S SO THAT ALL WORK CAN BE VERIFIED AS COMPLETE AND INVOICED

Base award description: ADVANCED ELECTRICAL METERING PROJECT

First action · last action
2009-09-28 · 2013-02-19
Transactions
33
First transaction's obligation
$18,769,956
Base + all options value (sum of deltas)
$19,537,227
Extent competed
COMPETITIVE DELIVERY ORDER
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
2
SDVOSB flag on record
No
Parent IDV
GS07F9462G
NAICS
335313 · SWITCHGEAR AND SWITCHBOARD APPARATUS MANUFACTURING

Modification chain · 33 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$19,537,227$0Base award · 2009-09-28 · this action $18,769,956 · running total $18,769,956Modification SA1 · 2010-02-18 · this action $0 · running total $18,769,956Modification SA2 · 2010-06-17 · this action $0 · running total $18,769,956Modification SA3 · 2010-07-21 · this action $1,121 · running total $18,771,077Modification SA5 · 2010-08-04 · this action $73,339 · running total $18,844,416Modification SA4 · 2010-09-16 · this action $16,536 · running total $18,860,952Modification SA6 · 2010-09-21 · this action $41,816 · running total $18,902,768Modification SA9 · 2010-09-30 · this action $2,582 · running total $18,905,349Modification SA7 · 2010-10-26 · this action $0 · running total $18,905,349Modification SA10 · 2010-11-03 · this action $0 · running total $18,905,349Modification SA11 · 2010-12-28 · this action $0 · running total $18,905,349Modification SA12 · 2010-12-28 · this action $82,895 · running total $18,988,244Modification SA13 · 2011-01-05 · this action $89,949 · running total $19,078,193Modification SA8 · 2011-01-24 · this action $0 · running total $19,078,193Modification SA14 · 2011-02-01 · this action $131,547 · running total $19,209,740Modification SA15 · 2011-02-01 · this action $13,953 · running total $19,223,693Modification SA19 · 2011-03-10 · this action $0 · running total $19,223,693Modification SA20 · 2011-04-27 · this action $4,048 · running total $19,227,741Modification SA18 · 2011-05-18 · this action $4,336 · running total $19,232,077Modification SA21 · 2011-05-24 · this action $5,675 · running total $19,237,752Modification SA22 · 2011-05-24 · this action $6,387 · running total $19,244,139Modification SA23 · 2011-05-26 · this action $2,026 · running total $19,246,165Modification SA24 · 2011-06-08 · this action $25,000 · running total $19,271,165Modification SA25 · 2011-06-08 · this action $11,892 · running total $19,283,057Modification SA17 · 2011-07-21 · this action $254,170 · running total $19,537,227Modification SA16 · 2011-08-02 · this action $0 · running total $19,537,227Modification SA26 · 2011-10-14 · this action $0 · running total $19,537,227Modification SA27 · 2011-10-14 · this action $0 · running total $19,537,227Modification P00028 · 2011-12-15 · this action $0 · running total $19,537,227Modification P00029 · 2012-01-27 · this action $0 · running total $19,537,227Modification P00031 · 2012-03-28 · this action $0 · running total $19,537,227Modification P00032 · 2012-05-28 · this action $0 · running total $19,537,227Modification P00030 · 2013-02-19 · this action $0 · running total $19,537,227
  • Base2009-09-28+$18,769,956= $18,769,956
  • Mod SA12010-02-18+$0= $18,769,956
  • Mod SA22010-06-17+$0= $18,769,956
  • Mod SA32010-07-21+$1,121= $18,771,077
  • Mod SA52010-08-04+$73,339= $18,844,416
  • Mod SA42010-09-16+$16,536= $18,860,952
  • Mod SA62010-09-21+$41,816= $18,902,768
  • Mod SA92010-09-30+$2,582= $18,905,349
  • Mod SA72010-10-26+$0= $18,905,349
  • Mod SA102010-11-03+$0= $18,905,349
  • Mod SA112010-12-28+$0= $18,905,349
  • Mod SA122010-12-28+$82,895= $18,988,244
  • Mod SA132011-01-05+$89,949= $19,078,193
  • Mod SA82011-01-24+$0= $19,078,193
  • Mod SA142011-02-01+$131,547= $19,209,740
  • Mod SA152011-02-01+$13,953= $19,223,693
  • Mod SA192011-03-10+$0= $19,223,693
  • Mod SA202011-04-27+$4,048= $19,227,741
  • Mod SA182011-05-18+$4,336= $19,232,077
  • Mod SA212011-05-24+$5,675= $19,237,752
  • Mod SA222011-05-24+$6,387= $19,244,139
  • Mod SA232011-05-26+$2,026= $19,246,165
  • Mod SA242011-06-08+$25,000= $19,271,165
  • Mod SA252011-06-08+$11,892= $19,283,057
  • Mod SA172011-07-21+$254,170= $19,537,227
  • Mod SA162011-08-02+$0= $19,537,227
  • Mod SA262011-10-14+$0= $19,537,227
  • Mod SA272011-10-14+$0= $19,537,227
  • Mod P000282011-12-15+$0= $19,537,227
  • Mod P000292012-01-27+$0= $19,537,227
  • Mod P000312012-03-28+$0= $19,537,227
  • Mod P000322012-05-28+$0= $19,537,227
  • Mod P000302013-02-19+$0= $19,537,227
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-09-28+$18,769,956$18,769,956ADVANCED ELECTRICAL METERING PROJECT
Mod SA1· OTHER ADMINISTRATIVE ACTION2010-02-18+$0$18,769,956ADVANCED ELECTRICAL METERING PROJECT
Mod SA2· OTHER ADMINISTRATIVE ACTION2010-06-17+$0$18,769,956ADVANCED ELECTRICAL METERING PROJECT
Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-21+$1,121$18,771,077ADVANCED ELECTRICAL METERING PROJECT
Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-04+$73,339$18,844,416ADVANCED ELECTRICAL METERING PROJECT
Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-16+$16,536$18,860,952ADVANCED ELECTRICAL METERING PROJECT
Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-21+$41,816$18,902,768ADVANCED ELECTRICAL METERING PROJECT
Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-30+$2,582$18,905,349ADVANCED ELECTRICAL METERING PROJECT
Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-10-26+$0$18,905,349ADVANCED ELECTRICAL METERING PROJECT
Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-03+$0$18,905,349ADVANCED ELECTRICAL METERING PROJECT
Mod SA11· OTHER ADMINISTRATIVE ACTION2010-12-28+$0$18,905,349ADVANCED ELECTRICAL METERING PROJECT
Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-28+$82,895$18,988,244ADVANCED ELECTRICAL METERING PROJECT
Mod SA13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-05+$89,949$19,078,193ADVANCED ELECTRICAL METERING PROJECT
Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-24+$0$19,078,193ADVANCED ELECTRICAL METERING PROJECT
Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-01+$131,547$19,209,740ADVANCED ELECTRICAL METERING PROJECT
Mod SA15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-01+$13,953$19,223,693ADVANCED ELECTRICAL METERING PROJECT
Mod SA19· OTHER ADMINISTRATIVE ACTION2011-03-10+$0$19,223,693ADVANCED ELECTRICAL METERING PROJECT
Mod SA20· OTHER ADMINISTRATIVE ACTION2011-04-27+$4,048$19,227,741ADVANCED ELECTRICAL METERING PROJECT - REVISIT CHEYENE FACILITY IN VISN 19 TO RELOCATE THE WIRELESS AND METERI…
Mod SA18· OTHER ADMINISTRATIVE ACTION2011-05-18+$4,336$19,232,077ADVANCED ELECTRICAL METERING PROJECT
Mod SA21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-24+$5,675$19,237,752ADVANCED ELECTRICAL METERING PROJECT
Mod SA22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-24+$6,387$19,244,139ADVANCED ELECTRICAL METERING PROJECT
Mod SA23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-26+$2,026$19,246,165ADVANCED ELECTRICAL METERING PROJECT
Mod SA24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-08+$25,000$19,271,165ADVANCED ELECTRICAL METERING PROJECT
Mod SA25· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-08+$11,892$19,283,057ADVANCED ELECTRICAL METERING PROJECT
Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$254,170$19,537,227ADVANCED ELECTRICAL METERING PROJECT
Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-02+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - TIME EXTENSION
Mod SA26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-14+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT
Mod SA27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-14+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - TIME EXTENSION
Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-15+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - 45 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THRO…
Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-27+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - 59 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THRO…
Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-28+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - 59 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THRO…
Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-28+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - 59 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THRO…
Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-19+$0$19,537,227ADVANCED ELECTRICAL METERING PROJECT - 59 DAY TIME EXTENSION TO PERIOD OF PERFORMANCE FOR ELECTRIC METERS THRO…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI S8DVLUWG7KQ5)

AwardOffice · PSC / listingNet obligationsFY
36C24426P0096244-NETWORK CONTRACT OFFICE 4 (36C244) · 5999 · MISCELLANEOUS ELECTRICAL AND ELECTRONIC COMPONENTS$291,735FY2026
36C25525P0465255-NETWORK CONTRACT OFFICE 15 (36C255) · H359 · INSPECTION- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS$38,859FY2025
36C26325P0159NETWORK CONTRACT OFFICE 23 (36C263) · U009 · EDUCATION/TRAINING- GENERAL$2,636FY2025
36C26025P0197260-NETWORK CONTRACT OFFICE 20 (36C260) · J036 · MAINT/REPAIR/REBUILD OF EQUIPMENT- SPECIAL INDUSTRY MACHINERY$4,959FY2025
36C77624P0099PCAC (36C776) · DA10 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SOFTWARE AS A SERVICE$181,000FY2024
36C24424P0698244-NETWORK CONTRACT OFFICE 4 (36C244) · J059 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS$7,890FY2024

Other recipients under N059 from PCAC NATIONAL ENERGY BUSINESS CENTER (most recent first)

AwardRecipientOfficeNet obligationsFY
VA70114F0131EFFICIENT ENERGY OF TENNESSEE, LLCPCAC NATIONAL ENERGY BUSINESS CENTER$1,042,303FY2014
VA70114F0171PACHECO COMPANY LLCPCAC NATIONAL ENERGY BUSINESS CENTER$63,187FY2014
VA70114F0168EFFICIENT ENERGY OF TENNESSEE, LLCPCAC NATIONAL ENERGY BUSINESS CENTER$4,038,301FY2014
VA70114F0133J.R. CONKEY & ASSOCIATES, INC.PCAC NATIONAL ENERGY BUSINESS CENTER$179,852FY2014
VA70114F0140NOVI ENERGY LLCPCAC NATIONAL ENERGY BUSINESS CENTER$218,956FY2014

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101C95132_3600_GS07F9462G_4730 · retrieved 2026-09-26.