Award recordCONTRACT

PCL CONSTRUCTION SERVICES INC

PIID VA101183B4C0040· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2008· $33,663,887 net obligations· UEI DSDWJG89J1D7· WA

Description

THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTRATIVELY CHANGE THE ACCOUNTING LINE IN SA-080. IT SHOULD READ AS FOLLOWS: 663CA2400/11-3220-1, 36X0110 DECREASE $269.106.00; 663AS2400/11-3220-1, 36X0110 DECREASE $145.600.00; 663HW2400B/11-3220-1, 36X0110 DECREASE $8,500.00

Base award description: CONSTRUCT A NEW 120-BED NURSING HOME.

First action · last action
2008-08-29 · 2011-01-19
Transactions
91
First transaction's obligation
$32,720,000
Base + all options value (sum of deltas)
$33,663,887
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
3
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 91 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$34,087,093$0Base award · 2008-08-29 · this action $32,720,000 · running total $32,720,000Modification 1 · 2008-10-23 · this action $1,735 · running total $32,721,735Modification 2 · 2008-11-19 · this action $3,959 · running total $32,725,694Modification 3 · 2009-02-02 · this action $2,627 · running total $32,728,321Modification 4 · 2009-03-02 · this action $6,990 · running total $32,735,311Modification 5 · 2009-03-12 · this action $2,137 · running total $32,737,448Modification 6 · 2009-03-12 · this action $8,107 · running total $32,745,555Modification 7 · 2009-03-20 · this action $11,127 · running total $32,756,682Modification 8 · 2009-04-30 · this action $87,603 · running total $32,844,285Modification 9 · 2009-04-30 · this action $14,132 · running total $32,858,417Modification 10 · 2009-05-21 · this action $8,924 · running total $32,867,341Modification 11 · 2009-06-04 · this action $46,606 · running total $32,913,947Modification 12 · 2009-06-04 · this action $38,690 · running total $32,952,637Modification 13 · 2009-06-04 · this action $52,113 · running total $33,004,750Modification 14 · 2009-06-09 · this action $17,237 · running total $33,021,987Modification 15 · 2009-06-11 · this action $56,300 · running total $33,078,287Modification 20 · 2009-07-07 · this action $18,580 · running total $33,096,867Modification ISC001 · 2009-07-07 · this action $0 · running total $33,096,867Modification 16 · 2009-07-10 · this action $57,994 · running total $33,154,861Modification 17 · 2009-07-13 · this action $39,268 · running total $33,194,129Modification 18 · 2009-07-13 · this action $7,949 · running total $33,202,078Modification 21 · 2009-07-14 · this action $7,556 · running total $33,209,634Modification CO01C · 2009-07-16 · this action $25,000 · running total $33,234,634Modification CO01E · 2009-07-20 · this action $5,800 · running total $33,240,434Modification 25 · 2009-07-31 · this action $14,663 · running total $33,255,097Modification 19 · 2009-08-03 · this action $14,830 · running total $33,269,927Modification 22 · 2009-08-03 · this action $21,458 · running total $33,291,385Modification 24 · 2009-08-03 · this action $8,878 · running total $33,300,263Modification 26 · 2009-08-07 · this action $1,997 · running total $33,302,260Modification 27 · 2009-08-10 · this action $10,843 · running total $33,313,103Modification CO01F · 2009-08-26 · this action $20,000 · running total $33,333,103Modification 29 · 2009-09-11 · this action $4,415 · running total $33,337,518Modification 32 · 2009-09-14 · this action $10,035 · running total $33,347,553Modification 33 · 2009-09-14 · this action $13,441 · running total $33,360,994Modification 35 · 2009-09-15 · this action $1,428 · running total $33,362,422Modification 28 · 2009-09-16 · this action -$2,961 · running total $33,359,461Modification 34 · 2009-09-16 · this action $8,493 · running total $33,367,954Modification 31 · 2009-09-17 · this action $10,141 · running total $33,378,095Modification 36 · 2009-09-17 · this action $13,904 · running total $33,391,999Modification CO01G · 2009-09-17 · this action $23,000 · running total $33,414,999Modification 38 · 2009-09-18 · this action $34,684 · running total $33,449,683Modification 37 · 2009-09-24 · this action $55,525 · running total $33,505,208Modification 39 · 2009-09-25 · this action $7,316 · running total $33,512,524Modification CO01H · 2009-09-30 · this action $90,000 · running total $33,602,524Modification 23 · 2009-10-01 · this action $171,474 · running total $33,773,998Modification 41 · 2009-11-02 · this action $3,598 · running total $33,777,596Modification 42 · 2009-11-02 · this action $2,617 · running total $33,780,213Modification 30 · 2009-12-02 · this action $0 · running total $33,780,213Modification 45 · 2009-12-02 · this action $549 · running total $33,780,762Modification CO01I · 2009-12-02 · this action $1,000 · running total $33,781,762Modification 44 · 2009-12-09 · this action $9,396 · running total $33,791,158Modification 46 · 2009-12-09 · this action $1,758 · running total $33,792,916Modification 47 · 2009-12-09 · this action $4,139 · running total $33,797,055Modification 48 · 2009-12-09 · this action $1,510 · running total $33,798,565Modification 49 · 2009-12-17 · this action -$46,212 · running total $33,752,353Modification 50 · 2009-12-17 · this action $7,973 · running total $33,760,326Modification SA051 · 2009-12-17 · this action -$4,336 · running total $33,755,990Modification SA052 · 2009-12-17 · this action $4,862 · running total $33,760,852Modification 40 · 2009-12-20 · this action $9,091 · running total $33,769,943Modification SA053 · 2009-12-22 · this action $27,741 · running total $33,797,684Modification SA054 · 2010-01-12 · this action $1,032 · running total $33,798,716Modification SA056 · 2010-01-25 · this action $2,552 · running total $33,801,268Modification SA057 · 2010-01-25 · this action $16,764 · running total $33,818,032Modification SA058 · 2010-01-25 · this action $115 · running total $33,818,147Modification SA059 · 2010-01-25 · this action $32,463 · running total $33,850,610Modification CO01K · 2010-01-29 · this action $7,500 · running total $33,858,110Modification SA060 · 2010-02-01 · this action $13,582 · running total $33,871,692Modification CO01J · 2010-02-02 · this action $12,000 · running total $33,883,692Modification SA061 · 2010-02-04 · this action -$3,608 · running total $33,880,084Modification CO01L · 2010-02-08 · this action $1,100 · running total $33,881,184Modification SA062 · 2010-02-09 · this action $11,129 · running total $33,892,313Modification SA063 · 2010-02-09 · this action $15,271 · running total $33,907,584Modification SA064 · 2010-02-22 · this action -$11,758 · running total $33,895,826Modification SA065 · 2010-02-26 · this action $2,624 · running total $33,898,450Modification SA066 · 2010-03-02 · this action $1,218 · running total $33,899,668Modification SA067 · 2010-03-04 · this action $303 · running total $33,899,971Modification SA068 · 2010-03-05 · this action $1,536 · running total $33,901,507Modification SA069 · 2010-03-05 · this action $717 · running total $33,902,224Modification CO01M · 2010-03-15 · this action $16,600 · running total $33,918,824Modification SA070 · 2010-03-18 · this action $3,460 · running total $33,922,284Modification SA071 · 2010-03-19 · this action $1,192 · running total $33,923,476Modification SA072 · 2010-03-19 · this action $4,307 · running total $33,927,783Modification SA073 · 2010-03-23 · this action $4,079 · running total $33,931,862Modification SA074 · 2010-04-01 · this action $11,947 · running total $33,943,809Modification SA075 · 2010-04-02 · this action $2,364 · running total $33,946,173Modification SA076 · 2010-05-17 · this action $4,357 · running total $33,950,530Modification SA077 · 2010-05-19 · this action $91,385 · running total $34,041,915Modification SA078 · 2010-05-19 · this action $41,647 · running total $34,083,562Modification SA079 · 2010-07-06 · this action $3,531 · running total $34,087,093Modification SA080 · 2010-09-29 · this action -$423,206 · running total $33,663,887Modification SA081 · 2011-01-19 · this action $0 · running total $33,663,887
  • Base2008-08-29+$32,720,000= $32,720,000
  • Mod 12008-10-23+$1,735= $32,721,735
  • Mod 22008-11-19+$3,959= $32,725,694
  • Mod 32009-02-02+$2,627= $32,728,321
  • Mod 42009-03-02+$6,990= $32,735,311
  • Mod 52009-03-12+$2,137= $32,737,448
  • Mod 62009-03-12+$8,107= $32,745,555
  • Mod 72009-03-20+$11,127= $32,756,682
  • Mod 82009-04-30+$87,603= $32,844,285
  • Mod 92009-04-30+$14,132= $32,858,417
  • Mod 102009-05-21+$8,924= $32,867,341
  • Mod 112009-06-04+$46,606= $32,913,947
  • Mod 122009-06-04+$38,690= $32,952,637
  • Mod 132009-06-04+$52,113= $33,004,750
  • Mod 142009-06-09+$17,237= $33,021,987
  • Mod 152009-06-11+$56,300= $33,078,287
  • Mod 202009-07-07+$18,580= $33,096,867
  • Mod ISC0012009-07-07+$0= $33,096,867
  • Mod 162009-07-10+$57,994= $33,154,861
  • Mod 172009-07-13+$39,268= $33,194,129
  • Mod 182009-07-13+$7,949= $33,202,078
  • Mod 212009-07-14+$7,556= $33,209,634
  • Mod CO01C2009-07-16+$25,000= $33,234,634
  • Mod CO01E2009-07-20+$5,800= $33,240,434
  • Mod 252009-07-31+$14,663= $33,255,097
  • Mod 192009-08-03+$14,830= $33,269,927
  • Mod 222009-08-03+$21,458= $33,291,385
  • Mod 242009-08-03+$8,878= $33,300,263
  • Mod 262009-08-07+$1,997= $33,302,260
  • Mod 272009-08-10+$10,843= $33,313,103
  • Mod CO01F2009-08-26+$20,000= $33,333,103
  • Mod 292009-09-11+$4,415= $33,337,518
  • Mod 322009-09-14+$10,035= $33,347,553
  • Mod 332009-09-14+$13,441= $33,360,994
  • Mod 352009-09-15+$1,428= $33,362,422
  • Mod 282009-09-16-$2,961= $33,359,461
  • Mod 342009-09-16+$8,493= $33,367,954
  • Mod 312009-09-17+$10,141= $33,378,095
  • Mod 362009-09-17+$13,904= $33,391,999
  • Mod CO01G2009-09-17+$23,000= $33,414,999
  • Mod 382009-09-18+$34,684= $33,449,683
  • Mod 372009-09-24+$55,525= $33,505,208
  • Mod 392009-09-25+$7,316= $33,512,524
  • Mod CO01H2009-09-30+$90,000= $33,602,524
  • Mod 232009-10-01+$171,474= $33,773,998
  • Mod 412009-11-02+$3,598= $33,777,596
  • Mod 422009-11-02+$2,617= $33,780,213
  • Mod 302009-12-02+$0= $33,780,213
  • Mod 452009-12-02+$549= $33,780,762
  • Mod CO01I2009-12-02+$1,000= $33,781,762
  • Mod 442009-12-09+$9,396= $33,791,158
  • Mod 462009-12-09+$1,758= $33,792,916
  • Mod 472009-12-09+$4,139= $33,797,055
  • Mod 482009-12-09+$1,510= $33,798,565
  • Mod 492009-12-17-$46,212= $33,752,353
  • Mod 502009-12-17+$7,973= $33,760,326
  • Mod SA0512009-12-17-$4,336= $33,755,990
  • Mod SA0522009-12-17+$4,862= $33,760,852
  • Mod 402009-12-20+$9,091= $33,769,943
  • Mod SA0532009-12-22+$27,741= $33,797,684
  • Mod SA0542010-01-12+$1,032= $33,798,716
  • Mod SA0562010-01-25+$2,552= $33,801,268
  • Mod SA0572010-01-25+$16,764= $33,818,032
  • Mod SA0582010-01-25+$115= $33,818,147
  • Mod SA0592010-01-25+$32,463= $33,850,610
  • Mod CO01K2010-01-29+$7,500= $33,858,110
  • Mod SA0602010-02-01+$13,582= $33,871,692
  • Mod CO01J2010-02-02+$12,000= $33,883,692
  • Mod SA0612010-02-04-$3,608= $33,880,084
  • Mod CO01L2010-02-08+$1,100= $33,881,184
  • Mod SA0622010-02-09+$11,129= $33,892,313
  • Mod SA0632010-02-09+$15,271= $33,907,584
  • Mod SA0642010-02-22-$11,758= $33,895,826
  • Mod SA0652010-02-26+$2,624= $33,898,450
  • Mod SA0662010-03-02+$1,218= $33,899,668
  • Mod SA0672010-03-04+$303= $33,899,971
  • Mod SA0682010-03-05+$1,536= $33,901,507
  • Mod SA0692010-03-05+$717= $33,902,224
  • Mod CO01M2010-03-15+$16,600= $33,918,824
  • Mod SA0702010-03-18+$3,460= $33,922,284
  • Mod SA0712010-03-19+$1,192= $33,923,476
  • Mod SA0722010-03-19+$4,307= $33,927,783
  • Mod SA0732010-03-23+$4,079= $33,931,862
  • Mod SA0742010-04-01+$11,947= $33,943,809
  • Mod SA0752010-04-02+$2,364= $33,946,173
  • Mod SA0762010-05-17+$4,357= $33,950,530
  • Mod SA0772010-05-19+$91,385= $34,041,915
  • Mod SA0782010-05-19+$41,647= $34,083,562
  • Mod SA0792010-07-06+$3,531= $34,087,093
  • Mod SA0802010-09-29-$423,206= $33,663,887
  • Mod SA0812011-01-19+$0= $33,663,887
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2008-08-29+$32,720,000$32,720,000CONSTRUCT A NEW 120-BED NURSING HOME.
Mod 1· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2008-10-23+$1,735$32,721,735ADD VEHICLE GATE
Mod 2· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2008-11-19+$3,959$32,725,694—
Mod 3· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-02-02+$2,627$32,728,321—
Mod 4· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-03-02+$6,990$32,735,311—
Mod 5· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-03-12+$2,137$32,737,448CONSTRUCTION SERVICES CONCRETE WALL
Mod 6· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-03-12+$8,107$32,745,555CONSTRUCTION SERVICES CONCRETE WALL
Mod 7· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-03-20+$11,127$32,756,682CONSTRUCTION SERVICES CONCRETE WALL
Mod 8· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-04-30+$87,603$32,844,285CONSTRUCTION SERVICES CONCRETE WALL
Mod 9· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-04-30+$14,132$32,858,417CONSTRUCTION SERVICES CONCRETE WALL
Mod 10· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-05-21+$8,924$32,867,341CONSTRUCTION SERVICES CONCRETE WALL
Mod 11· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-06-04+$46,606$32,913,947CONSTRUCTION SERVICES CONCRETE WALL
Mod 12· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2009-06-04+$38,690$32,952,637CONSTRUCTION SERVICES CONCRETE WALL
Mod 13· OTHER ADMINISTRATIVE ACTION2009-06-04+$52,113$33,004,750CONSTRUCTION SERVICES CONCRETE WALL
Mod 14· OTHER ADMINISTRATIVE ACTION2009-06-09+$17,237$33,021,987CONSTRUCTION SERVICES CONCRETE WALL
Mod 15· OTHER ADMINISTRATIVE ACTION2009-06-11+$56,300$33,078,287CONSTRUCTION SERVICES CONCRETE WALL
Mod 20· OTHER ADMINISTRATIVE ACTION2009-07-07+$18,580$33,096,867CONSTRUCTION SERVICES CONCRETE WALL
Mod ISC001· OTHER ADMINISTRATIVE ACTION2009-07-07+$0$33,096,867CONSTRUCTION SERVICES CONCRETE WALL
Mod 16· OTHER ADMINISTRATIVE ACTION2009-07-10+$57,994$33,154,861CONSTRUCTION SERVICES CONCRETE WALL
Mod 17· OTHER ADMINISTRATIVE ACTION2009-07-13+$39,268$33,194,129CONSTRUCTION SERVICES CONCRETE WALL
Mod 18· OTHER ADMINISTRATIVE ACTION2009-07-13+$7,949$33,202,078CONSTRUCTION SERVICES CONCRETE WALL
Mod 21· OTHER ADMINISTRATIVE ACTION2009-07-14+$7,556$33,209,634CONSTRUCTION SERVICES CONCRETE WALL
Mod CO01C· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-16+$25,000$33,234,634ADDITIONAL MEDGAS OUTLETS INSTALLATION
Mod CO01E· OTHER ADMINISTRATIVE ACTION2009-07-20+$5,800$33,240,434CONSTRUCTION SERVICES CONCRETE WALL
Mod 25· OTHER ADMINISTRATIVE ACTION2009-07-31+$14,663$33,255,097CONSTRUCTION SERVICES CONCRETE WALL
Mod 19· OTHER ADMINISTRATIVE ACTION2009-08-03+$14,830$33,269,927CONSTRUCTION SERVICES CONCRETE WALL
Mod 22· OTHER ADMINISTRATIVE ACTION2009-08-03+$21,458$33,291,385CONSTRUCTION SERVICES CONCRETE WALL
Mod 24· OTHER ADMINISTRATIVE ACTION2009-08-03+$8,878$33,300,263CONSTRUCTION SERVICES CONCRETE WALL
Mod 26· OTHER ADMINISTRATIVE ACTION2009-08-07+$1,997$33,302,260CONSTRUCTION SERVICES CONCRETE WALL
Mod 27· OTHER ADMINISTRATIVE ACTION2009-08-10+$10,843$33,313,103CONSTRUCTION SERVICES CONCRETE WALL
Mod CO01F· OTHER ADMINISTRATIVE ACTION2009-08-26+$20,000$33,333,103CONSTRUCTION SERVICES CONCRETE WALL
Mod 29· OTHER ADMINISTRATIVE ACTION2009-09-11+$4,415$33,337,518CONSTRUCTION SERVICES CONCRETE WALL
Mod 32· OTHER ADMINISTRATIVE ACTION2009-09-14+$10,035$33,347,553CONSTRUCTION SERVICES CONCRETE WALL
Mod 33· OTHER ADMINISTRATIVE ACTION2009-09-14+$13,441$33,360,994CONSTRUCTION SERVICES CONCRETE WALL
Mod 35· OTHER ADMINISTRATIVE ACTION2009-09-15+$1,428$33,362,422CONSTRUCTION SERVICES CONCRETE WALL
Mod 28· OTHER ADMINISTRATIVE ACTION2009-09-16−$2,961$33,359,461CONSTRUCTION SERVICES CONCRETE WALL
Mod 34· OTHER ADMINISTRATIVE ACTION2009-09-16+$8,493$33,367,954CONSTRUCTION SERVICES CONCRETE WALL
Mod 31· OTHER ADMINISTRATIVE ACTION2009-09-17+$10,141$33,378,095CONSTRUCTION SERVICES CONCRETE WALL
Mod 36· OTHER ADMINISTRATIVE ACTION2009-09-17+$13,904$33,391,999CONSTRUCTION SERVICES CONCRETE WALL
Mod CO01G· OTHER ADMINISTRATIVE ACTION2009-09-17+$23,000$33,414,999CONSTRUCTION SERVICES CONCRETE WALL
Mod 38· OTHER ADMINISTRATIVE ACTION2009-09-18+$34,684$33,449,683CONSTRUCTION SERVICES CONCRETE WALL
Mod 37· OTHER ADMINISTRATIVE ACTION2009-09-24+$55,525$33,505,208CONSTRUCTION SERVICES CONCRETE WALL
Mod 39· OTHER ADMINISTRATIVE ACTION2009-09-25+$7,316$33,512,524CONSTRUCTION SERVICES CONCRETE WALL
Mod CO01H· CHANGE ORDER2009-09-30+$90,000$33,602,524CONSTRUCTION SERVICES CONCRETE WALL
Mod 23· OTHER ADMINISTRATIVE ACTION2009-10-01+$171,474$33,773,998CONSTRUCTION SERVICES CONCRETE WALL
Mod 41· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-02+$3,598$33,777,596CONSTRUCTION SERVICES STRUCTURAL CHANGES
Mod 42· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-02+$2,617$33,780,213CONSTRUCTION SERVICES ADD TOPSOIK IN NATIVE GRASS SEED AREAS DEFINITIZES CO-01H TOTAL VALUE OF BOTH ACTIONS $9…
Mod 30· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-02+$0$33,780,213CONSTRUCTION SERVICES METAL WALL PANEL CHANGES $0.00
Mod 45· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-02+$549$33,780,762CONSTRUCTION SERVICES REVISE WALL TYPE AT ELECTRICAL PANELS
Mod CO01I· CHANGE ORDER2009-12-02+$1,000$33,781,762CONSTRUCTION SERVICES TP AND PT DISPENSERS
Mod 44· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-09+$9,396$33,791,158CONSTRUCTION SERVICES PAINTING
Mod 46· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-09+$1,758$33,792,916CONSTRUCTION SERVICES SWITCH CURTAINWALL
Mod 47· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-09+$4,139$33,797,055CONSTRUCTION SERVICES SCUPPER AND STEEL CONFLICT REVISION
Mod 48· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-09+$1,510$33,798,565CONSTRUCTION SERVICES WOOD FLOOR AT E101B
Mod 49· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-17−$46,212$33,752,353CONSTRUCTION SERVICES MODIFICATION TO AREA D DEFINITIZES CHANGE ORDER 01F
Mod 50· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-17+$7,973$33,760,326CONSTRUCTION SERVICES MODIFY SCRIM WALL
Mod SA051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-17−$4,336$33,755,990MODIFICATION OF ROOF PAVERS DUE TO LACK OF SPECIFIED MATERIALS.
Mod SA052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-17+$4,862$33,760,852CHANGES TO OXYGEN PAD FOR LOCATION AND REINFORCING.
Mod 40· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-20+$9,091$33,769,943CONSTRUCTION SERVICES DOOR HARDWARE
Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-22+$27,741$33,797,684TO ALLOW FOR THE INSTALLATION OF MULTIPLE ELECTRICAL ITEMS DUE TO A/E ERROR AND OMISSIONS OR OWNER COORDINATIO…
Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-12+$1,032$33,798,716TO REVISE THE INSTALLED HEIGHT OF THE FIBER REINFORCED PANELS IN THE MOP SINK ROOMS SO IT DOES NOT INTERFERE W…
Mod SA056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-25+$2,552$33,801,268TO ALLOW FOR THE EXTENSION OF 4 PENETRATIONS THROUGH A SOFFIT IN ROOM F119.
Mod SA057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-25+$16,764$33,818,032TO ALLOW FOR THE INSTALLATION OF THE REDESIGNED DOMESTIC HOT WATER CIRCULATION SYSTEM, PER A/E ERROR. ALSO, T…
Mod SA058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-25+$115$33,818,147REPLACE CONTRACT TOILET PAPER AND PAPER TOWEL DISPENSERS WITH THOSE PROVIDED BY THE MEDICAL CENTER.
Mod SA059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-25+$32,463$33,850,610TO ALLOW FOR THE REVISION OF THE STOREFRONT HEIGHT AND FAMILY ROOM CEILING DUE TO CONFLICT. ALSO REVISE THE H…
Mod CO01K· CHANGE ORDER2010-01-29+$7,500$33,858,110TO CONSTRUCT PARTITIONS THAT BLOCK THE VIEWS OF UTILITIES ABOVE THE CLOUD CEILINGS IN THE OUTPATIENT DINING RO…
Mod SA060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-01+$13,582$33,871,692CHANGES TO STRUCTURAL STEEL WORK. THESE CHANGES WERE ALL BASED ON CLARIFICATION IN RFIS WHICH THE CONTRACTOR P…
Mod CO01J· CHANGE ORDER2010-02-02+$12,000$33,883,692TO PROVIDE FINISH PIECES AT LOCATIONS IN THE DINING ROOM AND REC ROOM WHERE A GAP EXISTS BETWEEN THE FLOATING…
Mod SA061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-04−$3,608$33,880,084TO PROVIDE FINISH PIECES AT LOCATIONS IN THE DINING ROOM AND REC ROOM WHERE A GAP EXISTS BETWEEN THE FLOATING…
Mod CO01L· CHANGE ORDER2010-02-08+$1,100$33,881,184TO ALLOW FOR THE CLARIFICATION OF THE HEATING WATER LOOP CONTROLS LOCATED ON MI607. ALSO TO PERMIT THE INSTAL…
Mod SA062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-09+$11,129$33,892,313SITEWORK CHANGES ON ROOF DRAINAGE AND INFILTRATION FIELDS.
Mod SA063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-09+$15,271$33,907,584USE OF 3D MODELING IN LIEU OF COORDINATION DRAWINGS.
Mod SA064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-22−$11,758$33,895,826DELETE KITCHEN EQUIPMENT IDENTIFIED BY THE MEDICAL CENTER AS NO LONGER NEEDED OR WANTED. ADD ONE FIRE EXTINGU…
Mod SA065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-26+$2,624$33,898,450TO CONSTRUCT PARTITIONS THAT BLOCK THE VIEWS OF UTILITIES ABOVE THE CLOUD CEILINGS IN THE OUTPATIENT DINING RO…
Mod SA066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-02+$1,218$33,899,668TO RELOCATE ABOVE-CEILING DUCTWORK INSTALLED ACCORDING TO CONTRACT THAT CONFLICTED WITH MEDICAL CENTER-CONTRAC…
Mod SA067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-04+$303$33,899,971TO ADD A NEW SECTION OF CURTAIN TRACK WHERE A SINGLE SECTION CONFLICTS WITH THE OPERABLE PARTITION IN THE OT/…
Mod SA068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-05+$1,536$33,901,507TO PROVIDE PROPER SUPPORT FOR DOWNSPOUTS SCHEDULED FOR INSTALLATION AT WINDOW MULLIONS IN AREAS 'C' AND 'D.'
Mod SA069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-05+$717$33,902,224TO CHANGE WALL STOPS TO DOOR STOPS IN LOCATIONS WHERE WALL STOPS DO NOT WORK DUE TO ROOM CONFIGURATIONS.
Mod CO01M· CHANGE ORDER2010-03-15+$16,600$33,918,824CORRECT SAFETY ISSUES IDENTIFIED ON THE INSPECTION BY THE VISN SAFETY MANAGER AND NOT COVERED BY THE CONTRACT.
Mod SA070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-18+$3,460$33,922,284TO RELOCATE A DOOR OPENING WHOSE PLACEMENT BY CONTRACT DOES NOT MEET ADA REQUIREMENTS.
Mod SA071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-19+$1,192$33,923,476TO MODIFY THE CISTERN SPOUTS SO THE RUNOFF DOES NOT RETURN TO THE BUILDING ENVELOPE.
Mod SA072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-19+$4,307$33,927,783TO RESIZE TWO DOOR OPENINGS TO FIT WITHIN THE REQUIREMENTS OF THE BUILDING DESIGN GEOMETRY.
Mod SA073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-23+$4,079$33,931,862TO REVISE CONTRACT CEILING HEIGHTS IN FOUR ROOMS AND ADD A PLUMBING WALL IN THE KITCHEN TO ACCOMMODATE UTILITI…
Mod SA074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-01+$11,947$33,943,809TO ALLOW FOR THE CLARIFICATION OF THE HEATING WATER LOOP CONTROLS LOCATED ON MI607. ALSO TO PERMIT THE INSTAL…
Mod SA075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-02+$2,364$33,946,173TO REROUTE A SMOKE WALL AWAY FROM TWO LARGE HVAC DUCTS.
Mod SA076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-17+$4,357$33,950,530TO ALLOW FOR THE UPDATE OF THE FIRE ALARM GRAPHICS OF THE EXISTING BUILDINGS SO THEY MAY BE IMPORTED TO THE NE…
Mod SA077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-19+$91,385$34,041,915TO ALLOW FOR THE REPLACEMENT OF THE CONTRACT SPECIFIED HOBART DISHWASHER WITH A HOBART FLIGHT TYPE DISHWASHER…
Mod SA078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-19+$41,647$34,083,562TO ALLOW FOR THE REVISION OF THE SCRAP TROUGHS LOCATED IN F121 PER REQUEST OF THE MEDICAL CENTER
Mod SA079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-06+$3,531$34,087,093TO CORRECT SAFETY ISSUES IDENTIFIED ON THE INSPECTION BY THE VISN SAFETY MANAGER AND NOT COVERED BY THE CONTRA…
Mod SA080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-29−$423,206$33,663,887TERMINATION FOR CONVENIENCE SETTLEMENT.
Mod SA081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-19+$0$33,663,887THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTRATIVELY CHANGE THE ACCOUNTING LINE IN SA-080. IT SHOULD READ…

Related awards · 5

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0167THE R.E.M. ENGINEERING CO INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$384,303FY2011
VA101CFMC0130TTL ASSOCIATES INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$101,742FY2011
VA101CFMC0111WALSH CONSTRUCTION PUERTO RICOOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$52,457,646FY2010
VA101CFMC0085ARCHER WESTERN/DEMARIA JOINT VENTURE IIIOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$58,427,947FY2010
VACFM05I0064N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$114,946FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101183B4C0040_3600_-NONE-_-NONE- · retrieved 2026-09-26.