Award recordCONTRACT

STRATEGIC PERSPECTIVES DEVELOPMENT, LLC

PIID VA101183B4C0016· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2008· $3,469,527 net obligations· UEI W2CKBG3DVL33· TX

Description

TO INCREASE THE BOND PREMIUM TO COVER CONTRACT MODIFICATIONS DURING CONSTRUCTION.

Base award description: THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1). WORK INCLUDES GENERAL ARCHITECTURAL CONSTRUCTION, ALTERATIONS, MECHANICAL AND ELECTRICAL WORK, FIRE ALARM AND NURSE CALL SYSTEM, FIRE PROTECTION, UTILITY SYSTEMS, LIMITED DEMOLITION OF EXISTING INTERIOR SPACES AND CERTAIN OTHER ITEMS.

First action · last action
2007-12-21 · 2011-12-14
Transactions
32
First transaction's obligation
$2,958,092
Base + all options value (sum of deltas)
$3,469,527
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
4
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 32 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$3,473,610$0Base award · 2007-12-21 · this action $2,958,092 · running total $2,958,092Modification SA001 · 2008-10-27 · this action $22,012 · running total $2,980,104Modification SA002 · 2008-10-30 · this action $5,902 · running total $2,986,006Modification SA003 · 2008-12-18 · this action $10,612 · running total $2,996,618Modification SA004 · 2009-01-26 · this action $7,091 · running total $3,003,709Modification SA005 · 2009-04-01 · this action $31,108 · running total $3,034,817Modification SA006 · 2009-04-08 · this action $6,914 · running total $3,041,731Modification SA007 · 2009-06-04 · this action $6,435 · running total $3,048,166Modification SA008 · 2009-06-04 · this action $338,690 · running total $3,386,856Modification SA009 · 2009-06-24 · this action $2,624 · running total $3,389,480Modification SA010 · 2009-06-24 · this action $1,994 · running total $3,391,474Modification SA011 · 2009-07-06 · this action $6,609 · running total $3,398,083Modification SA012 · 2009-07-08 · this action $883 · running total $3,398,966Modification SA013 · 2009-07-08 · this action $2,556 · running total $3,401,522Modification SA014 · 2009-08-18 · this action $16,885 · running total $3,418,407Modification SA015 · 2009-08-19 · this action $405 · running total $3,418,812Modification SA016 · 2009-08-27 · this action $5,400 · running total $3,424,212Modification SA017 · 2009-08-27 · this action $1,910 · running total $3,426,122Modification SA018 · 2009-09-09 · this action $3,113 · running total $3,429,235Modification SA019 · 2009-09-10 · this action $922 · running total $3,430,157Modification SA020 · 2009-10-07 · this action $3,903 · running total $3,434,060Modification SA021 · 2009-10-07 · this action $9,354 · running total $3,443,414Modification SA022 · 2009-10-16 · this action $3,173 · running total $3,446,587Modification SA023 · 2009-12-11 · this action $1,959 · running total $3,448,546Modification SA024 · 2010-01-11 · this action $3,168 · running total $3,451,714Modification SA025 · 2010-01-11 · this action $7,132 · running total $3,458,846Modification SA026 · 2010-05-13 · this action $1,370 · running total $3,460,216Modification SA027 · 2010-05-14 · this action $1,651 · running total $3,461,867Modification SA028 · 2010-05-14 · this action $2,008 · running total $3,463,875Modification SA029 · 2010-08-20 · this action $9,735 · running total $3,473,610Modification SA030 · 2011-12-01 · this action -$8,796 · running total $3,464,814Modification SA031 · 2011-12-14 · this action $4,713 · running total $3,469,527
  • Base2007-12-21+$2,958,092= $2,958,092
  • Mod SA0012008-10-27+$22,012= $2,980,104
  • Mod SA0022008-10-30+$5,902= $2,986,006
  • Mod SA0032008-12-18+$10,612= $2,996,618
  • Mod SA0042009-01-26+$7,091= $3,003,709
  • Mod SA0052009-04-01+$31,108= $3,034,817
  • Mod SA0062009-04-08+$6,914= $3,041,731
  • Mod SA0072009-06-04+$6,435= $3,048,166
  • Mod SA0082009-06-04+$338,690= $3,386,856
  • Mod SA0092009-06-24+$2,624= $3,389,480
  • Mod SA0102009-06-24+$1,994= $3,391,474
  • Mod SA0112009-07-06+$6,609= $3,398,083
  • Mod SA0122009-07-08+$883= $3,398,966
  • Mod SA0132009-07-08+$2,556= $3,401,522
  • Mod SA0142009-08-18+$16,885= $3,418,407
  • Mod SA0152009-08-19+$405= $3,418,812
  • Mod SA0162009-08-27+$5,400= $3,424,212
  • Mod SA0172009-08-27+$1,910= $3,426,122
  • Mod SA0182009-09-09+$3,113= $3,429,235
  • Mod SA0192009-09-10+$922= $3,430,157
  • Mod SA0202009-10-07+$3,903= $3,434,060
  • Mod SA0212009-10-07+$9,354= $3,443,414
  • Mod SA0222009-10-16+$3,173= $3,446,587
  • Mod SA0232009-12-11+$1,959= $3,448,546
  • Mod SA0242010-01-11+$3,168= $3,451,714
  • Mod SA0252010-01-11+$7,132= $3,458,846
  • Mod SA0262010-05-13+$1,370= $3,460,216
  • Mod SA0272010-05-14+$1,651= $3,461,867
  • Mod SA0282010-05-14+$2,008= $3,463,875
  • Mod SA0292010-08-20+$9,735= $3,473,610
  • Mod SA0302011-12-01-$8,796= $3,464,814
  • Mod SA0312011-12-14+$4,713= $3,469,527
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2007-12-21+$2,958,092$2,958,092THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2008-10-27+$22,012$2,980,104THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2008-10-30+$5,902$2,986,006THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2008-12-18+$10,612$2,996,618THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-01-26+$7,091$3,003,709THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-04-01+$31,108$3,034,817THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-04-08+$6,914$3,041,731THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-04+$6,435$3,048,166THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-04+$338,690$3,386,856THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-24+$2,624$3,389,480THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-24+$1,994$3,391,474THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-06+$6,609$3,398,083THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-08+$883$3,398,966THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-08+$2,556$3,401,522THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-18+$16,885$3,418,407THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-19+$405$3,418,812THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-27+$5,400$3,424,212THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-27+$1,910$3,426,122THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-09+$3,113$3,429,235THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-10+$922$3,430,157THIS PROCUREMENT PROVIDES FOR THE NECESSARY LABOR, MATERIALS AND EQUIPMENT TO RENOVATE WARD 5B (BUILDING 1).…
Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-10-07+$3,903$3,434,060CORRECTION TO PCU CABINET DUE TO INACCURATE DRAWINGS AND PLUMBING TEMPLATES
Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-10-07+$9,354$3,443,414REVISED INSTALLATION HEIGHTS FOR HEADWALLS, INCREASED BY VAMC APPROXIMATELY 18", HAVE TO BE LOWERED DUE TO IMP…
Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-10-16+$3,173$3,446,587DESPITE OF INSTALLATION OF A BRIDGE TO PROTECT THE AIR DUCT AT MECHANICAL ROOM, SOME MAINTENANCE PERSONNEL STI…
Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-11+$1,959$3,448,546THIS IS A TWO-PART SA. FOOT PEDALS WERE CHANGED TO BE INSTALLED UNDERNEATH CABINETS IN RMS. B504, B506 AND B52…
Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-11+$3,168$3,451,714THIS IS A FOUR-PART SA. FIRST, LITES FOR TWO DOORS IN ROOM B506, WHICH CONNECTS TWO ISOLATION ROOMS, WERE NOT…
Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-11+$7,132$3,458,846THIS IS A THREE-PART SA. FIRST, EXISTING NURSE STATION AND CABINETS HAD EDGE BANDING AND END CAPS DIFFERENT FR…
Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-13+$1,370$3,460,216ADDITIONAL SOUND INSULATION WAS INSTALLED OVER RM. B509 HEAD NURSE OFFICE BECAUSE OF THE NOISE CAUSED BY THE E…
Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$1,651$3,461,867DOOR FRAME PROTECTION SPECIFIED IN CONTRACT DRAWINGS FIT LOOSELY ON DOOR FRAME INSTALLED. HENCE, MODIFICATIONS…
Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$2,008$3,463,875SINCE ADDITIONAL INSTALLED SOUND INSULATION OVER RM. B509 DID NOT REDUCE THE NOISE CAUSED BY THE EXHAUST FAN,…
Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-20+$9,735$3,473,610BECAUSE OF HIGH HUMIDITY LEVELS AND VERY LOW CHILLED WATER SUPPLY TEMPERATURE AT THE 5B PCU AREA FIFTH FLOOR I…
Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-01−$8,796$3,464,814TO PROVIDE CREDIT FOR INSPECTION, TESTING, MAINTENANCE AND TRAINING AND REPAIR SERVICES FOR THE FIRE ALARM SYS…
Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-14+$4,713$3,469,527TO INCREASE THE BOND PREMIUM TO COVER CONTRACT MODIFICATIONS DURING CONSTRUCTION.

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI W2CKBG3DVL33)

AwardOffice · PSC / listingNet obligationsFY
VA101CFMC0056OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y111 · CONSTRUCTION OF OFFICE BUILDINGS$4,749,454FY2009
VA262C0331262-NETWORK CONTRACT OFFICE 22 · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$2,402,866FY2008

Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0167THE R.E.M. ENGINEERING CO INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$384,303FY2011
VA101CFMC0130TTL ASSOCIATES INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$101,742FY2011
VA101CFMC0111WALSH CONSTRUCTION PUERTO RICOOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$52,457,646FY2010
VA101CFMC0085ARCHER WESTERN/DEMARIA JOINT VENTURE IIIOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$58,427,947FY2010
VACFM05I0064N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$114,946FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101183B4C0016_3600_-NONE-_-NONE- · retrieved 2026-09-26.