Description
EXTEND THE PROVISION OF CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES DURING THE EXTENDED PERIOD OF CONSTRUCTION FOR THE 3,800-NICHE COLUMBARIUM EXPANSION PROJECT AT THE NATIONAL MEMORIAL CEMETERY OF THE PACIFIC.
Base award description: THE CONTRACTOR SHALL PROVIDE INSPECTION AND RESIDENT ENGINEER SERVICES ON A PART TIME BASIS, APPROXIMATELY 4 HOURS PER DAY FOR TWO DAYS PER WEEK DURING THE FIRST TWO MONTHS OF CONSTRUCTION AND 4 HOURS PER DAY, FIVE DAYS PER WEEK DURING THE REMAINING TEN MONTHS UNTIL CONSRUCINT IS COMPLETED AT THE NATIONAL MEMORIAL CEMETERY OF THE PACIFIC.
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-08-10+$136,902= $136,902
- Mod SA12010-08-26+$43,263= $180,165
- Mod SA22011-11-08-$9,314= $170,851
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-08-10 | +$136,902 | $136,902 | THE CONTRACTOR SHALL PROVIDE INSPECTION AND RESIDENT ENGINEER SERVICES ON A PART TIME BASIS, APPROXIMATELY 4 H… |
| Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-26 | +$43,263 | $180,165 | EXTEND THE PROVISION OF CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES DURING THE EXTENDED PERIOD OF CONSTRUC… |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-08 | −$9,314 | $170,851 | EXTEND THE PROVISION OF CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES DURING THE EXTENDED PERIOD OF CONSTRUC… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI RMJMXU2A26R7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA787J0003 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $396,068 | FY2013 |
| V841Z30000 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $225,089 | FY2013 |
| VA786A13P0043 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $70,550 | FY2013 |
| V847Z10001 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $57,037 | FY2013 |
| V831Z30000 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $39,127 | FY2013 |
| V843Z30000 | NATIONAL CEMETERY ADMINISTRATION · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $69,602 | FY2013 |
Other recipients under C211 from NATIONAL CEMETERY ADMINISTRATION (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA786A16C0003 | ANDERSON ENGINEERING OF MINNESOTA, LLC | NATIONAL CEMETERY ADMINISTRATION | $28,870 | FY2016 |
| V906Z50003 | ANDERSON ENGINEERING OF MINNESOTA, LLC | NATIONAL CEMETERY ADMINISTRATION | $9,981 | FY2015 |
| V846Z50001 | ANDERSON ENGINEERING OF MINNESOTA, LLC | NATIONAL CEMETERY ADMINISTRATION | $72,801 | FY2015 |
| V911Z50001 | ANDERSON ENGINEERING OF MINNESOTA, LLC | NATIONAL CEMETERY ADMINISTRATION | $28,908 | FY2015 |
| V898Z50001 | ANDERSON ENGINEERING OF MINNESOTA, LLC | NATIONAL CEMETERY ADMINISTRATION | $209,779 | FY2015 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_V899Z90080_3600_VA786AP0079_3600 · retrieved 2026-09-26.