Description
DEOBLIGATE EXCESS FUNDS IN THE AMOUNT OF $1,306.20, STATION LEVEL
Base award description: SCHEMATIC DESIGN FOR NEW BED TOWER.
Modification chain · 149 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-05-29+$14,749,222= $14,749,222
- Mod SA0082008-12-02+$113,327= $14,862,549
- Mod CO01D2009-02-27+$10,000,000= $24,862,549
- Mod SA0112009-07-22+$62,101= $24,924,650
- Mod SA0102009-07-24+$46,592= $24,971,242
- Mod CO01E2009-09-24+$95,000= $25,066,242
- Mod SA0122009-09-28+$1,470,635= $26,536,877
- Mod CO01F2009-09-30+$8,000,000= $34,536,877
- Mod CO01A2009-12-11+$20,000= $34,556,877
- Mod SA0042009-12-11+$27,534= $34,584,411
- Mod SA0052009-12-11+$5,060= $34,589,471
- Mod SA0092009-12-29+$3,035,641= $37,625,112
- Mod SA0132009-12-29+$38,055= $37,663,167
- Mod SA0142009-12-29+$17,246= $37,680,413
- Mod SA0152009-12-29+$67,112= $37,747,525
- Mod SA0162009-12-30+$39,700= $37,787,225
- Mod SA0172010-01-11+$29,840= $37,817,065
- Mod SA0182010-02-15+$41,745= $37,858,810
- Mod SA0202010-02-16+$35,373= $37,894,183
- Mod SA202010-02-16+$35,373= $37,929,556
- Mod SA0192010-02-22+$99,917= $38,029,473
- Mod CO01G2010-04-01+$0= $38,029,473
- Mod SA0212010-04-14+$51,455= $38,080,928
- Mod SA222010-04-30+$56,313= $38,137,241
- Mod SA232010-06-14+$1,843= $38,139,084
- Mod SA242010-06-17+$2,860= $38,141,944
- Mod SA0252010-11-04+$11,403,031= $49,544,975
- Mod SA0262010-11-04+$8,831= $49,553,806
- Mod SA272010-11-16+$5,160= $49,558,966
- Mod SA282010-11-29+$2,934= $49,561,900
- Mod SA292010-12-03+$21,859= $49,583,759
- Mod SA302010-12-03+$14,857= $49,598,616
- Mod SA312010-12-20+$14,476= $49,613,092
- Mod SA322011-02-11+$13,395= $49,626,487
- Mod SA332011-02-18+$3,746= $49,630,233
- Mod SA342011-02-22+$4,998= $49,635,231
- Mod SA352011-02-25+$8,476= $49,643,707
- Mod SA362011-03-04+$5,662= $49,649,369
- Mod SA382011-03-10+$4,837= $49,654,206
- Mod SA392011-03-15+$69,693= $49,723,899
- Mod SA372011-03-20+$33,188= $49,757,087
- Mod SA412011-03-24+$93,716= $49,850,803
- Mod SA422011-04-08+$392,504= $50,243,307
- Mod SA432011-04-08+$12,530= $50,255,837
- Mod SA442011-04-20+$91,843= $50,347,680
- Mod SA452011-05-18+$99,247= $50,446,927
- Mod SA462011-06-08+$22,594= $50,469,521
- Mod SA0482011-06-21+$73,663= $50,543,184
- Mod SA492011-06-21+$25,090= $50,568,274
- Mod SA512011-06-21+$3,172= $50,571,446
- Mod SA472011-06-23+$99,939= $50,671,385
- Mod SA502011-06-23+$26,309= $50,697,694
- Mod SA522011-07-15+$49,755= $50,747,449
- Mod SA532011-07-22+$59,447= $50,806,896
- Mod SA582011-08-16+$23,522= $50,830,418
- Mod SA592011-10-03+$53,251= $50,883,669
- Mod SA602011-10-03+$34,874= $50,918,543
- Mod SA622011-10-03+$33,390= $50,951,933
- Mod SA632011-10-04+$4,153= $50,956,086
- Mod SA642011-10-07+$13,904= $50,969,990
- Mod SA612011-10-18+$39,635= $51,009,625
- Mod SA652011-10-31+$13,802= $51,023,427
- Mod SA662011-10-31+$14,793= $51,038,220
- Mod SA672011-10-31+$10,278= $51,048,498
- Mod SA682011-11-09+$12,621= $51,061,119
- Mod SA692011-11-09+$14,444= $51,075,563
- Mod SA702011-11-09+$18,826= $51,094,389
- Mod SA402011-11-18+$1,161,693= $52,256,082
- Mod SA712011-11-18+$4,228= $52,260,310
- Mod SA722011-11-18+$2,359= $52,262,669
- Mod SA732011-11-18+$12,637= $52,275,306
- Mod SA742011-11-18+$4,288= $52,279,594
- Mod SA752011-12-05+$2,344= $52,281,938
- Mod SA762011-12-15+$16,399= $52,298,337
- Mod SA772011-12-15+$84,452= $52,382,789
- Mod SA782011-12-16+$11,307= $52,394,096
- Mod SA792012-01-12+$28,906= $52,423,002
- Mod SA802012-01-15+$47,819= $52,470,821
- Mod SA812012-01-17+$65,253= $52,536,074
- Mod SA822012-01-23+$64,378= $52,600,452
- Mod SA832012-02-08+$89,282= $52,689,734
- Mod SA842012-02-27+$73,382= $52,763,116
- Mod SA852012-02-27+$38,198= $52,801,314
- Mod SA872012-02-27+$3,205= $52,804,519
- Mod SA882012-03-21+$66,753= $52,871,272
- Mod SA892012-03-28+$39,911= $52,911,183
- Mod SA902012-03-28+$10,057= $52,921,240
- Mod SA862012-04-09+$472,308= $53,393,548
- Mod SA922012-04-27+$5,498= $53,399,046
- Mod SA932012-05-04+$5,060= $53,404,106
- Mod SA942012-05-07+$7,180= $53,411,286
- Mod SA962012-06-04+$9,131= $53,420,417
- Mod SA972012-06-06+$24,675= $53,445,092
- Mod SA992012-06-22+$49,509= $53,494,601
- Mod P000022012-06-25+$3,650= $53,498,251
- Mod P000042012-07-16+$54,290= $53,552,541
- Mod SA952012-07-16+$59,161= $53,611,702
- Mod P000052012-07-30+$35,609= $53,647,311
- Mod P000062012-07-30+$89,861= $53,737,172
- Mod P000082012-08-07+$35,888= $53,773,060
- Mod P000092012-08-07+$10,676= $53,783,736
- Mod P000102012-09-07+$6,625= $53,790,361
- Mod P000112012-09-25+$10,373= $53,800,734
- Mod P000122012-09-25+$5,431= $53,806,165
- Mod P000132012-10-08+$8,321= $53,814,486
- Mod P000142012-10-16+$89,332= $53,903,818
- Mod P000172012-11-21+$10,068= $53,913,886
- Mod P000232012-11-21+$10,068= $53,923,954
- Mod P000192013-01-09+$88,007= $54,011,961
- Mod P000202013-01-09+$88,007= $54,099,968
- Mod P000212013-01-23+$7,551= $54,107,519
- Mod P000182013-01-28+$99,802= $54,207,321
- Mod P000222013-03-11+$96,071= $54,303,392
- Mod P000242013-03-12+$88,007= $54,391,399
- Mod P000252013-04-04+$85,584= $54,476,983
- Mod P000282013-04-19+$7,421= $54,484,404
- Mod P000032013-05-31+$615,759= $55,100,163
- Mod P000072013-05-31+$1,199,997= $56,300,160
- Mod P000162013-05-31+$272,395= $56,572,555
- Mod SA912013-05-31+$330,797= $56,903,352
- Mod P000012013-06-11+$31,111= $56,934,463
- Mod P000322013-08-25+$15,969= $56,950,432
- Mod P000342013-08-31+$85,606= $57,036,038
- Mod P000332013-09-16+$4,006= $57,040,044
- Mod P000372013-12-19+$9,226= $57,049,270
- Mod P000382013-12-20+$17,810= $57,067,080
- Mod P000352014-01-21+$139,018= $57,206,098
- Mod P000362014-01-21+$85,280= $57,291,378
- Mod P000392014-01-27+$92,909= $57,384,287
- Mod P000402014-03-11+$85,000= $57,469,287
- Mod P000432014-03-24+$20,000= $57,489,287
- Mod P000442014-04-14+$85,000= $57,574,287
- Mod P000452014-06-17+$85,000= $57,659,287
- Mod P000462014-06-18+$85,000= $57,744,287
- Mod P000472014-08-14+$9,043= $57,753,330
- Mod P000482014-08-18+$3,500= $57,756,830
- Mod P000492014-09-11+$80,000= $57,836,830
- Mod P000502014-09-18+$100,000= $57,936,830
- Mod P000512018-02-28+$2,972= $57,939,802
- Mod P000522018-02-28+$5,500= $57,945,302
- Mod P000532018-02-28+$85,000= $58,030,302
- Mod P000542018-02-28+$91,108= $58,121,410
- Mod P000552018-02-28+$90,000= $58,211,410
- Mod P000562018-02-28+$4,000= $58,215,410
- Mod P000572018-02-28+$44,000= $58,259,410
- Mod P000582018-02-28-$5,500= $58,253,910
- Mod P000592018-02-28+$95,000= $58,348,910
- Mod P000602018-02-28-$51,023= $58,297,887
- Mod P000612018-02-28-$1,306= $58,296,581
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2008-05-29 | +$14,749,222 | $14,749,222 | SCHEMATIC DESIGN FOR NEW BED TOWER. |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2008-12-02 | +$113,327 | $14,862,549 | SCHEMATIC DESIGN FOR NEW BED TOWER. |
| Mod CO01D· CHANGE ORDER | 2009-02-27 | +$10,000,000 | $24,862,549 | SCHEMATIC DESIGN FOR NEW BED TOWER. |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-22 | +$62,101 | $24,924,650 | SCHEMATIC DESIGN FOR NEW BED TOWER. |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-24 | +$46,592 | $24,971,242 | SCHEMATIC DESIGN FOR NEW BED TOWER. |
| Mod CO01E· CHANGE ORDER | 2009-09-24 | +$95,000 | $25,066,242 | VA MEDICAL CENTER, ORLANDO, FL |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-28 | +$1,470,635 | $26,536,877 | VA MEDICAL CENTER ORLANDO SA-012 |
| Mod CO01F· CHANGE ORDER | 2009-09-30 | +$8,000,000 | $34,536,877 | VA MEDICAL CENTER, ORLANDO, FL |
| Mod CO01A· CHANGE ORDER | 2009-12-11 | +$20,000 | $34,556,877 | COMM LIVING CTR, DOM&CHAPEL, ORLANDO, FL CO-01A |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-11 | +$27,534 | $34,584,411 | VA MEDICAL CENTER ORLANDO SA-004 |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-11 | +$5,060 | $34,589,471 | VA MEDICAL CENTER ORLANDO SA-005 |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-29 | +$3,035,641 | $37,625,112 | VA MEDICAL CENTER ORLANDO SA-012 |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-29 | +$38,055 | $37,663,167 | VA MEDICAL CENTER ORLANDO SA-013 |
| Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-29 | +$17,246 | $37,680,413 | VA MEDICAL CENTER ORLANDO SA-014 |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-29 | +$67,112 | $37,747,525 | VA MEDICAL CENTER ORLANDO SA-015 |
| Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-30 | +$39,700 | $37,787,225 | VA MEDICAL CENTER ORLANDO SA-016 |
| Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-11 | +$29,840 | $37,817,065 | EXTERIOR DESIGN CHANGES CLC |
| Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-15 | +$41,745 | $37,858,810 | REDESIGN FLOORPLAN,VBA |
| Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-16 | +$35,373 | $37,894,183 | REDESIGN SPD AREA |
| Mod SA20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-16 | +$35,373 | $37,929,556 | REDESIGN OF SPD AREA |
| Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-22 | +$99,917 | $38,029,473 | 3D-MODEL |
| Mod CO01G· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-01 | +$0 | $38,029,473 | CONSTRUCTION PERIOD SERVICES |
| Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-14 | +$51,455 | $38,080,928 | SIMLEARN CENTER PRE-DESIGN |
| Mod SA22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-30 | +$56,313 | $38,137,241 | ADDL SECURITY CONTROL CENTER AND PATIENT TRACKING |
| Mod SA23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-14 | +$1,843 | $38,139,084 | MARKET SURVEY |
| Mod SA24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-17 | +$2,860 | $38,141,944 | CLC CONCRETE WALLS |
| Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-04 | +$11,403,031 | $49,544,975 | CONSTRUCTION PERIOD SERVICES |
| Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-04 | +$8,831 | $49,553,806 | WAREHOUSE CHANGES |
| Mod SA27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-16 | +$5,160 | $49,558,966 | RENEWABLE ENERGY ESTIMATES |
| Mod SA28· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-29 | +$2,934 | $49,561,900 | CORRECTIVE MEASURES, ICF WALLS |
| Mod SA29· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-03 | +$21,859 | $49,583,759 | TEMPORARY CHILLER DESIGN, WHSE |
| Mod SA30· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-03 | +$14,857 | $49,598,616 | TEMPORARY POWER DESIGN, WAREHOUSE/PARKING |
| Mod SA31· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-20 | +$14,476 | $49,613,092 | TEMPORARY BOILER DESIGN, WAREHOUSE/PARKING |
| Mod SA32· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-11 | +$13,395 | $49,626,487 | NURSE CALL EMERG BUTTON |
| Mod SA33· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-18 | +$3,746 | $49,630,233 | NURSE CALL EMERG BUTTON |
| Mod SA34· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-22 | +$4,998 | $49,635,231 | CASEWORK&SINKS |
| Mod SA35· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-25 | +$8,476 | $49,643,707 | COLUMN STRUCT ANA |
| Mod SA36· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-04 | +$5,662 | $49,649,369 | COLORED PRECAST CONCRETE ANA |
| Mod SA38· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-10 | +$4,837 | $49,654,206 | GAS SURVEY |
| Mod SA39· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-15 | +$69,693 | $49,723,899 | SPD REDESIGN |
| Mod SA37· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-20 | +$33,188 | $49,757,087 | RADIOLOGY CHANGES |
| Mod SA41· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-24 | +$93,716 | $49,850,803 | FFA REDESIGN |
| Mod SA42· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$392,504 | $50,243,307 | SITE VISITS |
| Mod SA43· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$12,530 | $50,255,837 | INFUSION CLINIC |
| Mod SA44· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-20 | +$91,843 | $50,347,680 | OPERATING ROOM, GOVT EQUIP, REDES |
| Mod SA45· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-18 | +$99,247 | $50,446,927 | DESIGN, FURNITURE, FIXTURES, ARTWORK |
| Mod SA46· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-08 | +$22,594 | $50,469,521 | ESTIMATING SERVICE |
| Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-21 | +$73,663 | $50,543,184 | DESIGN LEAD SHIELDING |
| Mod SA49· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-21 | +$25,090 | $50,568,274 | REDESIGN DENTAL DEPT |
| Mod SA51· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-21 | +$3,172 | $50,571,446 | MODIFY DUMBWAITER |
| Mod SA47· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-23 | +$99,939 | $50,671,385 | DEVELOPMENT FINAL ARTWORK |
| Mod SA50· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-23 | +$26,309 | $50,697,694 | REDESIGN GENERAL RADIOGRAPHY |
| Mod SA52· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-15 | +$49,755 | $50,747,449 | ESTIMATING SERVICES, ADDL |
| Mod SA53· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-22 | +$59,447 | $50,806,896 | CYSTO&ENDO ROOM REDESIGN |
| Mod SA58· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$23,522 | $50,830,418 | DATA&POWER OUTLETS |
| Mod SA59· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-03 | +$53,251 | $50,883,669 | PATIENT HEADWALL SYSTEMS |
| Mod SA60· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-03 | +$34,874 | $50,918,543 | COMMUNICATION CLOSETS |
| Mod SA62· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-03 | +$33,390 | $50,951,933 | OPERATION AIR PERMIT |
| Mod SA63· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-04 | +$4,153 | $50,956,086 | TV BRACKETS |
| Mod SA64· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-07 | +$13,904 | $50,969,990 | ROOFING REVIEW |
| Mod SA61· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-18 | +$39,635 | $51,009,625 | AMBIENT MRI, CAT |
| Mod SA65· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-31 | +$13,802 | $51,023,427 | MODIFY OFFICE |
| Mod SA66· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-31 | +$14,793 | $51,038,220 | BOOMS, ICU ROOMS |
| Mod SA67· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-31 | +$10,278 | $51,048,498 | IN-WALL MED CABINETS |
| Mod SA68· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-09 | +$12,621 | $51,061,119 | CYSTOLOGY ROOM |
| Mod SA69· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-09 | +$14,444 | $51,075,563 | SINK, STERILIZER, OR |
| Mod SA70· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-09 | +$18,826 | $51,094,389 | OR INTEGRATION |
| Mod SA40· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$1,161,693 | $52,256,082 | SIMLEARN SD AND DD |
| Mod SA71· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$4,228 | $52,260,310 | OR INTEGRATION |
| Mod SA72· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$2,359 | $52,262,669 | OR INTEGRATION |
| Mod SA73· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$12,637 | $52,275,306 | OR INTEGRATION |
| Mod SA74· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$4,288 | $52,279,594 | OR INTEGRATION |
| Mod SA75· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-05 | +$2,344 | $52,281,938 | OR INTEGRATION |
| Mod SA76· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-15 | +$16,399 | $52,298,337 | OR INTEGRATION |
| Mod SA77· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-15 | +$84,452 | $52,382,789 | OR INTEGRATION |
| Mod SA78· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-16 | +$11,307 | $52,394,096 | PROVIDE CEILING MOUNTED BOOMS IN LIEU OF UTILITY PEDESTALS FOR CATH. LAB, 3L806D, EP LAB, 3L806B, AND SPECIAL… |
| Mod SA79· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-12 | +$28,906 | $52,423,002 | PROVIDE CEILING MOUNTED BOOMS IN LIEU OF UTILITY PEDESTALS FOR CATH. LAB, 3L806D, EP LAB, 3L806B, AND SPECIAL… |
| Mod SA80· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-15 | +$47,819 | $52,470,821 | PROVIDE ADDITIONAL CONSTRUCTION ADMINISTRATOR SERVICE |
| Mod SA81· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-17 | +$65,253 | $52,536,074 | PROVIDE TWO (2) MONTHS OF ADDITIONAL CONSTRUCTION ADMINISTRATOR SERVICE FOR THE NEW VA MEDICAL CENTER, ORLANDO… |
| Mod SA82· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-23 | +$64,378 | $52,600,452 | PROVIDE DESIGN DOCUMENTATION ASSOCIATED WITH THE EARLY ACCEPTANCE OF THE CLINIC PORTION OF THE NEW VA MEDICAL… |
| Mod SA83· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-08 | +$89,282 | $52,689,734 | PROVIDE DESIGN DOCUMENTATION ASSOCIATED WITH CLIENT REQUESTED CHANGES ASSOCIATED WITH THE NEW RESUSCITATION PR… |
| Mod SA84· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-27 | +$73,382 | $52,763,116 | SA-84, PRODUCE CONSTRUCTION DOCUMENTS REQUIRED TO CONVERT VASCULAR OR#5, ROOM 3N335, TO A HYBRID OPERATING ROO… |
| Mod SA85· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-27 | +$38,198 | $52,801,314 | PROVIDE PROFESSIONAL DESIGN SERVICES TO REVISE THE DESIGN OF THE SITE ENTRIES TO ACCOMMODATE THE NEW LAKE NONA… |
| Mod SA87· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-27 | +$3,205 | $52,804,519 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCORPORATE THE DESIGN DOCUMENTATION ASSOCIATED WITH INCREASING THE FE… |
| Mod SA88· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-21 | +$66,753 | $52,871,272 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCLUDE ALL LABOR, MATERIALS, SUPPLIES, TOOLS,EQUIPMENT AND TRAVEL ASS… |
| Mod SA89· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-28 | +$39,911 | $52,911,183 | ATTEND AND PARTICIPATE IN THE APRIL 3, 2012 SD/2 CONSULTING SUPPORT SERVICE PROJECT REVIEW IN VACO FOR THE NEW… |
| Mod SA90· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-28 | +$10,057 | $52,921,240 | UPDATE THE BUILDING INFORMATION MODEL EFFECTIVE MARCH 26, 2012, FOR THE NEW VA MEDICAL CENTER, ORLANDO, FL |
| Mod SA86· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-09 | +$472,308 | $53,393,548 | SA-86, PROVIDE PROFESSIONAL DESIGN SERVICES FOR FULL TIME A/E CONSTRUCTION PERIOD SERVICES FOR THE NEW VA MEDI… |
| Mod SA92· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-27 | +$5,498 | $53,399,046 | ALLOW THE JOINT VENTURE DESIGN TEAM TO PERFORM MISCELLANEOUS UTILITY EASEMENT SURVEYS |
| Mod SA93· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-04 | +$5,060 | $53,404,106 | PERFORM MISCELLANEOUS UTILITY EASEMENT SURVEYS FOR THE NEW VA MEDICAL CENTER |
| Mod SA94· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-07 | +$7,180 | $53,411,286 | PROVIDE PROFESSIONAL DESIGN SERVICES TO MODIFY THE CONNECTION OF THE CEILING MOUNTED EQUIPMENT IN THE ICU TO B… |
| Mod SA96· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-04 | +$9,131 | $53,420,417 | PROVIDE PROFESSIONAL DESIGN SERVICES TO EXTENDED SITE VISIT TO PERFORM AN INTERMEDIATE REVIEW AND INSPECTION O… |
| Mod SA97· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-06 | +$24,675 | $53,445,092 | PROVIDE CERTIFIED ELEVATOR INSPECTION SERVICES |
| Mod SA99· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-22 | +$49,509 | $53,494,601 | PROVIDE PROFESSIONAL DESIGN SERVICES TO ATTEND AND PARTICIPATE IN THE JULY 12, 2012 DD/2 CONSULTING SUPPORT SE… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-25 | +$3,650 | $53,498,251 | ROOF CONSULTANT |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-16 | +$54,290 | $53,552,541 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE TWO ADDITIONAL FULL TIME ON SITE CONSTRUCTION ADMINISTRATIVE P… |
| Mod SA95· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-16 | +$59,161 | $53,611,702 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE TWO (2) MONTHS OF CONSTRUCTION ADMINISTRATOR NEGOTIATION ASSIS… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-30 | +$35,609 | $53,647,311 | ACCOMMODATE DISPERSION ANALYSIS, COMMISSIONING AND PERFORM A TOPOGRAPHIC SURVEY RELATED TO THE SCHEMATIC AND… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-30 | +$89,861 | $53,737,172 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL TWELVE (12) WEEKS OF CONSTRUCTION ADMINISTRATOR NEG… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-07 | +$35,888 | $53,773,060 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL ARTWORK PROCUREMENT SERVICES, FOR THE NEW VA MEDICA… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-07 | +$10,676 | $53,783,736 | PROVIDE PROFESSIONAL SERVICES RELATED TO ADDITIONAL DESIGN ASSOCIATED WITH FURNITURE, FURNISHINGS AND ACCESSOR… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-07 | +$6,625 | $53,790,361 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCORPORATE THE DESIGN DOCUMENTATION ASSOCIATED WITH MODIFYING THE UTI… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-25 | +$10,373 | $53,800,734 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCORPORATE THE DESIGN DOCUMENTATION ASSOCIATED WITH MODIFYING THE HOO… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-25 | +$5,431 | $53,806,165 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCORPORATE THE DESIGN DOCUMENTATION ASSOCIATED WITH THE COORDINATION… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-08 | +$8,321 | $53,814,486 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCORPORATE THE DESIGN DOCUMENTATION ASSOCIATED WITH MODIFYING THE LIG… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-16 | +$89,332 | $53,903,818 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL TWELVE (12) WEEKS OF CONSTRUCTION ADMINISTRATOR NEG… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-21 | +$10,068 | $53,913,886 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE FINAL INSPECTIONS OF THE VARIOUS SECURITY ELEMENTS FOR BID PAC… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-21 | +$10,068 | $53,923,954 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE FINAL INSPECTIONS OF THE VARIOUS SECURITY ELEMENTS FOR BID PAC… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-09 | +$88,007 | $54,011,961 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL TWELVE (12) WEEKS OF CONSTRUCTION ADMINISTRATOR NEG… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-09 | +$88,007 | $54,099,968 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL TWELVE (12) WEEKS OF CONSTRUCTION ADMINISTRATOR NEG… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-23 | +$7,551 | $54,107,519 | PROVIDE PROFESSIONAL DESIGN SERVICES TO UPDATE THE BUILDING INFORMATION MODEL IN ORDER TO FACILITATE CONSTRUCT… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-28 | +$99,802 | $54,207,321 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE THE FURNITURE, FURNISHINGS AND ACCESSORIES (FF&A), RFI ASSISTA… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-11 | +$96,071 | $54,303,392 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE AN ADDITIONAL THREE (3) MONTHS FULL TIME ARCHITECTURAL CONSTRU… |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-12 | +$88,007 | $54,391,399 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE ADDITIONAL TWELVE (12) WEEKS OF CONSTRUCTION ADMINISTRATOR NEG… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-04 | +$85,584 | $54,476,983 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE 16 WEEKS OF FULL TIME ON SITE ARCHITECTURAL CONSTRUCTION ADMIN… |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-19 | +$7,421 | $54,484,404 | PROVIDE PROFESSIONAL DESIGN SERVICES TO RE-REVIEW THE FOOD SERVICE CONVEYOR EQUIPMENT, FOR THE NEW VA MEDICAL… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-31 | +$615,759 | $55,100,163 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCLUDE ALL LABOR, MATERIALS, SUPPLIES, TOOLS, EQUIPMENT AND TRAVEL RE… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-31 | +$1,199,997 | $56,300,160 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE CONSTRUCTION DOCUMENTS FOR THE NEW NATIONAL SIMLEARN CENTER AT… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-31 | +$272,395 | $56,572,555 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDE FULL TIME ARCHITECTURAL CONSTRUCTION ADMINISTRATOR SITE VISIT… |
| Mod SA91· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-31 | +$330,797 | $56,903,352 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INCLUDE ALL LABOR, MATERIALS, SUPPLIES, TOOLS, EQUIPMENT AND TRAVEL AS… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-11 | +$31,111 | $56,934,463 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PROVIDING FOUR (4) WEEKS OF CONSTRUCTION ADMINISTRATOR NEGOTIATION ASS… |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-25 | +$15,969 | $56,950,432 | PROVIDE PROFESSIONAL DESIGN SERVICES TO INTEGRATED CAMPUS WIDE SECURITY SYSTEM DESIGN, NEW VA MEDICAL US CENTE… |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-31 | +$85,606 | $57,036,038 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-16 | +$4,006 | $57,040,044 | PROVIDE PROFESSIONAL DESIGN SERVICES TO PERFORM TOPOGRAPHIC SURVEY OF THE CONSTRUCTION TRAILER COMPOUND ON THE… |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-19 | +$9,226 | $57,049,270 | SA-137, VAO - LOOP ROAD ASPHALT MATERIAL TESTING |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-20 | +$17,810 | $57,067,080 | SA-138, PROVIDE MISC CHANGES TO THE SIMLEARN CENTER |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-21 | +$139,018 | $57,206,098 | 26 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-21 | +$85,280 | $57,291,378 | SA-136, ADDITIONAL 16 WEEKS (4 MONTHS) RLF FULL-TIME ON-SITE REPRESENTATION |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-27 | +$92,909 | $57,384,287 | ACTIVATION ASSITANCE SERVICES, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJECT NO. 675-950 |
| Mod P00040· CHANGE ORDER | 2014-03-11 | +$85,000 | $57,469,287 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00043· CHANGE ORDER | 2014-03-24 | +$20,000 | $57,489,287 | CO-01Q, SUBMITTAL REVIEW OF GC'S REQUESTED VARIANCE, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJECT NO. 675-95… |
| Mod P00044· CHANGE ORDER | 2014-04-14 | +$85,000 | $57,574,287 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00045· CHANGE ORDER | 2014-06-17 | +$85,000 | $57,659,287 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00046· CHANGE ORDER | 2014-06-18 | +$85,000 | $57,744,287 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL CENTER, ORLANDO, FL. PROJECT… |
| Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-14 | +$9,043 | $57,753,330 | SA-140, VA SIMLEARN TRIRIGA SOFTWARE&TRAINING, ORLANDO, FL. PROJECT NO. 675-950 |
| Mod P00048· CHANGE ORDER | 2014-08-18 | +$3,500 | $57,756,830 | ADDITIONAL A/E REVIEW OF EQUIPMENT LAYOUT, ORLANDO, FL. PROJECT NO. 675-950 |
| Mod P00049· CHANGE ORDER | 2014-09-11 | +$80,000 | $57,836,830 | 15 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00050· CHANGE ORDER | 2014-09-18 | +$100,000 | $57,936,830 | ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJECT NO. 675-… |
| Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$2,972 | $57,939,802 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$5,500 | $57,945,302 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$85,000 | $58,030,302 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$91,108 | $58,121,410 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$90,000 | $58,211,410 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$4,000 | $58,215,410 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$44,000 | $58,259,410 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | −$5,500 | $58,253,910 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-02-28 | +$95,000 | $58,348,910 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00060· OTHER ADMINISTRATIVE ACTION | 2018-02-28 | −$51,023 | $58,297,887 | 16 WEEKS OF ON SITE FULL TIME A/E CONSTRUCTION PERIOD SITE VISITS, NEW VA MEDICAL US CENTER, ORLANDO, FL. PROJ… |
| Mod P00061· OTHER ADMINISTRATIVE ACTION | 2018-02-28 | −$1,306 | $58,296,581 | DEOBLIGATE EXCESS FUNDS IN THE AMOUNT OF $1,306.20, STATION LEVEL |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JYDHXLMWNBM7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA688C10897 | 688-WASHINGTON DC · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $418,839 | FY2011 |
| VA688C10892 | 688-WASHINGTON DC · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $325,006 | FY2011 |
| VA688C10893 | 688-WASHINGTON DC · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $190,117 | FY2011 |
| VA688C10890 | 688-WASHINGTON DC · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $51,596 | FY2011 |
| VA688C10587 | 688-WASHINGTON DC · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $17,000 | FY2011 |
| VATOJUN07 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · C114 · HOSPITAL BUILDINGS | $7,200 | FY2011 |
Other recipients under C114 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VATODEC05 | LEO A. DALY LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | -$1,261 | FY2018 |
| VATOJUL07 | LEO A. DALY LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | -$188,468 | FY2016 |
| VA101CFMP0148 | CANNON DESIGN, INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,571 | FY2011 |
| VACFM05C0095 | E B A ERNEST BLAND ASSOCIATES, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $53,624 | FY2011 |
| V101BP0249 | N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $0 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_V101BP0239_3600_-NONE-_-NONE- · retrieved 2026-09-26.