GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. FINALIZED SOIL SORTING AND REMOVAL COSTS
Base award description: GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2020-08-06+$5,450,372= $5,450,372
- Mod P000012020-10-16+$0= $5,450,372
- Mod P000022021-07-12+$0= $5,450,372
- Mod P000032021-07-12+$0= $5,450,372
- Mod P000042021-08-19+$15,242= $5,465,614
- Mod P000052021-12-15+$0= $5,465,614
- Mod P000062022-05-02+$45,840= $5,511,453
- Mod P000072022-06-15+$99,579= $5,611,032
- Mod P000082022-06-15+$29,637= $5,640,669
- Mod P000092022-08-15+$204,837= $5,845,506
- Mod P000102022-08-24+$48,368= $5,893,874
- Mod P000112023-01-13+$429,563= $6,323,437
- Mod P000122023-07-19+$111,885= $6,435,322
- Mod P000132023-11-17+$0= $6,435,322
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2020-08-06 | +$5,450,372 | $5,450,372 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2020-10-16 | +$0 | $5,450,372 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. NO COST TIME EXTENSION |
| Mod P00002· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2021-07-12 | +$0 | $5,450,372 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. NO COST TIME EXTENSION |
| Mod P00003· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2021-07-12 | +$0 | $5,450,372 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. NO COST TIME EXTENSION |
| Mod P00004· CHANGE ORDER | 2021-08-19 | +$15,242 | $5,465,614 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. NO COST TIME EXTENSION |
| Mod P00005· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2021-12-15 | +$0 | $5,465,614 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. UNFORESEEN SITE CONDITIONS - ROCKS |
| Mod P00006· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-05-02 | +$45,840 | $5,511,453 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. UNFORESEEN SITE CONDITIONS - ROCKS |
| Mod P00007· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-06-15 | +$99,579 | $5,611,032 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. ROCK REMOVAL |
| Mod P00008· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-06-15 | +$29,637 | $5,640,669 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL, NCA. REMOVAL OF FOUNDATION, ASPHALT, AND C… |
| Mod P00009· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-08-15 | +$204,837 | $5,845,506 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. ADDITIONAL ROCK REMOVAL AND NO COST TIME E… |
| Mod P00010· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-08-24 | +$48,368 | $5,893,874 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. FINALIZED SOIL SORTING AND REMOVAL COSTS |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-13 | +$429,563 | $6,323,437 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. FINALIZED SOIL SORTING AND REMOVAL COSTS |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-07-19 | +$111,885 | $6,435,322 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. FINALIZED SOIL SORTING AND REMOVAL COSTS |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-17 | +$0 | $6,435,322 | GRAVESITE EXPANSION, ROCK ISLAND NATIONAL CEMETERY, ROCK ISLAND IL. FINALIZED SOIL SORTING AND REMOVAL COSTS |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI P3CTJ2KMB3J8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26326C0031 | NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $3,071,800 | FY2026 |
| 36C77625C0121 | PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $19,181,217 | FY2025 |
| 36C77625C0102 | PCAC (36C776) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $11,091,002 | FY2025 |
| 36C26324C0085 | NETWORK CONTRACT OFFICE 23 (36C263) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $2,271,222 | FY2024 |
| 36C77624C0093 | PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $10,069,728 | FY2024 |
| 36C77624C0117 | PCAC (36C776) · Y1LZ · CONSTRUCTION OF PARKING FACILITIES | $2,755,965 | FY2024 |
Other recipients under Y1PZ from NATIONAL CEMETERY ADMIN (36C786) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C78626N0454 | US DIVERSIFIED CONTRACTING SERVICES INC. | NATIONAL CEMETERY ADMIN (36C786) | $301,173 | FY2026 |
| 36C78626N0418 | US DIVERSIFIED CONTRACTING SERVICES INC. | NATIONAL CEMETERY ADMIN (36C786) | $59,741 | FY2026 |
| 36C78626N0443 | US DIVERSIFIED CONTRACTING SERVICES INC. | NATIONAL CEMETERY ADMIN (36C786) | $53,627 | FY2026 |
| 36C78626N0448 | US DIVERSIFIED CONTRACTING SERVICES INC. | NATIONAL CEMETERY ADMIN (36C786) | $20,506 | FY2026 |
| 36C78626N0441 | US DIVERSIFIED CONTRACTING SERVICES INC. | NATIONAL CEMETERY ADMIN (36C786) | $18,843 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C78620C0298_3600_-NONE-_-NONE- · retrieved 2026-09-26.