Description
THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL THINGS NECESSARY THAT WILL RESULT IN THE COMPLETION OF THE CONSTRUCT DENTAL CENTER (MINOR) CONSTRUCTION PROJECT.
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-08-07+$10,220,000= $10,220,000
- Mod P000012024-05-10+$57,828= $10,277,828
- Mod P000022025-02-19+$103,591= $10,381,419
- Mod P000032025-08-26+$40,237= $10,421,656
- Mod P000042026-08-25+$214,375= $10,636,031
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-08-07 | +$10,220,000 | $10,220,000 | THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-10 | +$57,828 | $10,277,828 | THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-02-19 | +$103,591 | $10,381,419 | THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-26 | +$40,237 | $10,421,656 | THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-08-25 | +$214,375 | $10,636,031 | THE CONTRACTOR SHALL PROVIDE ALL TOOLS, EQUIPMENT, MATERIALS, LABOR, SUPERVISION, PERSONNEL, AND SHALL DO ALL… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI Q6SMWAFUFDL7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24226P0594 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $19,200 | FY2026 |
| 36C24226P0185 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $64,883 | FY2026 |
| 36C24225P1388 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · J059 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS | $24,000 | FY2025 |
| 36C24225C0092 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $40,200 | FY2025 |
| 36C24225P1127 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · W041 · LEASE OR RENTAL OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $218,227 | FY2025 |
| 36C24225C0061 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1ND · CONSTRUCTION OF SEWAGE AND WASTE FACILITIES | $477,870 | FY2025 |
Other recipients under Y1AZ from PCAC (36C776) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C77624C0044 | CDEEM CO | PCAC (36C776) | $25,839,000 | FY2024 |
| 36C77624C0040 | ADVANCED TECHNOLOGY CONSTRUCTION CORPORATION | PCAC (36C776) | $4,115,849 | FY2024 |
| 36C77623C0180 | FALCON JV, LLC | PCAC (36C776) | $5,296,217 | FY2023 |
| 36C77623C0149 | THE POVOLNY GROUP INC | PCAC (36C776) | $50,244,113 | FY2023 |
| 36C77623C0023 | M.D. PAR, L.L.C. | PCAC (36C776) | $3,557,679 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C77623C0072_3600_-NONE-_-NONE- · retrieved 2026-09-26.