Description
NO COST TIME EXTENSION TO COMPLETE WITHIN SCOPE WORK.
Base award description: TASK ORDER TO REPLACE FLOORING ON ICU & SURGERY FLOORS OF THE OMAHA VAMC.
Modification chain · 7 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-01-22+$1,144,930= $1,144,930
- Mod P000012021-02-16+$0= $1,144,930
- Mod P000022021-04-21-$1,926= $1,143,004
- Mod P000032021-06-09+$12,860= $1,155,864
- Mod P000042021-10-13+$0= $1,155,864
- Mod P000052021-11-02+$0= $1,155,864
- Mod P000062022-02-22+$0= $1,155,864
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-01-22 | +$1,144,930 | $1,144,930 | TASK ORDER TO REPLACE FLOORING ON ICU & SURGERY FLOORS OF THE OMAHA VAMC. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-16 | +$0 | $1,144,930 | MODIFICATION TO ISSUE NOTICE TO PROCEED AND RESET THE START/COMPLETION DATE OF THIS PROJECT. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-21 | −$1,926 | $1,143,004 | MODIFICATION TO DE-SCOPE WORK AND ADD 60 CALENDAR DAYS TO PERIOD OF PERFORMANCE. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-09 | +$12,860 | $1,155,864 | MODIFICATION TO ADD WITHIN SCOPE WORK - ELECTRICAL WALL OUTLET RELOCATE AND INSTALL NURSE STATION COMPUTER MON… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-13 | +$0 | $1,155,864 | MODIFICATION P00004 IS TO EXTEND PERIOD OF PERFORMANCE BY 92 CALENDAR DAYS. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-02 | +$0 | $1,155,864 | EO14042 - COVID SAFETY PROTOCOL MODIFICATION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-22 | +$0 | $1,155,864 | NO COST TIME EXTENSION TO COMPLETE WITHIN SCOPE WORK. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZQSYA8Z3JBG1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25526C0060 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $739,012 | FY2026 |
| 36C78626N0293 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $30,275 | FY2026 |
| 36C78626N0290 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $30,492 | FY2026 |
| 36C25526C0016 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $6,036,009 | FY2026 |
| 36C26326C0030 | NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $1,364,402 | FY2026 |
| 36C78626N0244 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $58,468 | FY2026 |
Other recipients under Z1DA from NETWORK CONTRACT OFFICE 23 (36C263) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26326C0051 | MDM CONSTRUCTION LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $1,059,225 | FY2026 |
| 36C26326C0049 | DAKOTA ELECTRIC, INC. | NETWORK CONTRACT OFFICE 23 (36C263) | $11,485,965 | FY2026 |
| 36C26326C0045 | PEDERSEN & RANGEL | NETWORK CONTRACT OFFICE 23 (36C263) | $4,188,000 | FY2026 |
| 36C26326P0480 | MOYER EXTERIORS LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $27,217 | FY2026 |
| 36C26326P0499 | LIFE SAFETY GROUP, LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $12,850 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26321N0414_3600_36C26320D0027_3600 · retrieved 2026-09-26.