Description
MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), MOD 15 OUT OF SCOPE FOR FLOOD DAMAGE.
Base award description: MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS)
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2020-12-14+$7,705,969= $7,705,969
- Mod P000012021-06-03-$3,175= $7,702,794
- Mod P000022021-09-16+$37,136= $7,739,930
- Mod P000032021-09-29+$93,259= $7,833,189
- Mod P000042022-03-07+$27,574= $7,860,763
- Mod P000052022-09-01+$0= $7,860,763
- Mod P000062022-12-12+$38,857= $7,899,620
- Mod P000072023-05-12+$118,935= $8,018,555
- Mod P000082023-12-15+$146,280= $8,164,835
- Mod P000092024-05-17+$348,110= $8,512,944
- Mod P000102024-09-19+$174,642= $8,687,587
- Mod P000112024-09-20+$260,970= $8,948,557
- Mod P000122025-02-20+$0= $8,948,557
- Mod P000132025-08-11+$171,858= $9,120,415
- Mod P000142025-08-29+$360,828= $9,481,243
- Mod P000152026-01-01+$116,889= $9,598,132
- Mod P000162026-04-06+$63,191= $9,661,324
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2020-12-14 | +$7,705,969 | $7,705,969 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-03 | −$3,175 | $7,702,794 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-16 | +$37,136 | $7,739,930 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-29 | +$93,259 | $7,833,189 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-03-07 | +$27,574 | $7,860,763 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-01 | +$0 | $7,860,763 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS) |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-12 | +$38,857 | $7,899,620 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADD DRY SPRINKLER SYSTEM |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-12 | +$118,935 | $8,018,555 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00008· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-12-15 | +$146,280 | $8,164,835 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00009· CHANGE ORDER | 2024-05-17 | +$348,110 | $8,512,944 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-09-19 | +$174,642 | $8,687,587 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-09-20 | +$260,970 | $8,948,557 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00012· CHANGE ORDER | 2025-02-20 | +$0 | $8,948,557 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), ADDITIONAL ABATEMENT |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-11 | +$171,858 | $9,120,415 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), MOD 13 |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-29 | +$360,828 | $9,481,243 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), MOD 13 |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-01-01 | +$116,889 | $9,598,132 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), MOD 15 OUT OF SCOPE FOR FLOOD DAM… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-06 | +$63,191 | $9,661,324 | MN CONSTRUCTION MATOC, RENOVATE BLDG 4 FOR STERILE PROCESSING SERVICE (SPS), MOD 15 OUT OF SCOPE FOR FLOOD DAM… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI LTPUJJSU6WN9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24722N0135 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $393,180 | FY2022 |
| 36C26322N0233 | NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $3,172,344 | FY2022 |
| 36C25621P1591 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · S205 · HOUSEKEEPING- TRASH/GARBAGE COLLECTION | $69,963 | FY2021 |
| 36C26321N0777 | NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,377,420 | FY2021 |
| 36C26321N0477 | NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $9,402,763 | FY2021 |
| 36C24120N1129 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $843,689 | FY2020 |
Other recipients under Y1DZ from NETWORK CONTRACT OFFICE 23 (36C263) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26326C0055 | BILLY W. JARRETT CONSTRUCTION COMPANY, INC. | NETWORK CONTRACT OFFICE 23 (36C263) | $3,698,423 | FY2026 |
| 36C26326C0038 | GREENSTONE CONSTRUCTION, INC. | NETWORK CONTRACT OFFICE 23 (36C263) | $2,252,800 | FY2026 |
| 36C26326C0004 | DAX SAFETY & STAFFING SOLUTIONS, LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $36,587 | FY2026 |
| 36C26325C0071 | KEVIN PIET, LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $2,206,311 | FY2025 |
| 36C26325C0070 | PREFERRED COMMERCIAL CONTRACTING, INC | NETWORK CONTRACT OFFICE 23 (36C263) | $48,668 | FY2025 |