Description
MODIFICATION TO PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- MODIFICATION TO CHANGE THE CONTRACT END DATE TO 3/31/2021
Base award description: PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- VENDOR TO REPLACE THE BOILERS AT THE GRAND ISLAND VAMC
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-07-31+$3,150,000= $3,150,000
- Mod P000012019-09-26+$0= $3,150,000
- Mod P000022020-06-02+$0= $3,150,000
- Mod P000032020-09-17+$0= $3,150,000
- Mod P000042021-01-27+$0= $3,150,000
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-07-31 | +$3,150,000 | $3,150,000 | PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- VENDOR TO REPLACE THE BOILERS AT THE GRAND ISLAND VAMC |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-09-26 | +$0 | $3,150,000 | MODIFICATION TO PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- MODIFICATION TO ISSUE THE NOTICE TO PROC… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-02 | +$0 | $3,150,000 | MODIFICATION TO PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- MODIFICATION TO ADD TIME DUE TO BOILER S… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-17 | +$0 | $3,150,000 | MODIFICATION TO PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- MODIFICATION TO CHANGE METHOD IN WHICH B… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-27 | +$0 | $3,150,000 | MODIFICATION TO PROJECT NUMBER: 636-13-103, REPLACE BOILERS 2&3 (GI)- MODIFICATION TO CHANGE THE CONTRACT END… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CKRASC1SL4F5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24723N0580 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $23,297,410 | FY2023 |
| 36C26120N0691 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $2,000 | FY2020 |
| 36C26120D0088 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $0 | FY2020 |
| 36C10F20C0002 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $4,078,853 | FY2020 |
| 36C25219N0565 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $2,000 | FY2019 |
| 36C25219P0924 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $0 | FY2019 |
Other recipients under Z1DA from NETWORK CONTRACT OFFICE 23 (36C263) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26326C0051 | MDM CONSTRUCTION LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $1,059,225 | FY2026 |
| 36C26326C0049 | DAKOTA ELECTRIC, INC. | NETWORK CONTRACT OFFICE 23 (36C263) | $11,485,965 | FY2026 |
| 36C26326P0480 | MOYER EXTERIORS LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $27,217 | FY2026 |
| 36C26326C0045 | PEDERSEN & RANGEL | NETWORK CONTRACT OFFICE 23 (36C263) | $4,188,000 | FY2026 |
| 36C26326P0499 | LIFE SAFETY GROUP, LLC | NETWORK CONTRACT OFFICE 23 (36C263) | $12,850 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26319C0186_3600_-NONE-_-NONE- · retrieved 2026-09-26.