Description
THE PURPOSE OF THIS MODIFICATION IS TO REMOVE EXCESS FUNDS AND TO CLOSE OUT THIS CONTRACT. ALL WORK HAS BEEN COMPLETED AND INVOICES HAVE BEEN PAID.
Base award description: BOILER BURNER REPLACEMENT PROJECT.
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2022-03-24+$2,506,532= $2,506,532
- Mod P000012023-02-16+$0= $2,506,532
- Mod P000022023-04-07+$158,400= $2,664,932
- Mod P000032023-07-05+$0= $2,664,932
- Mod P000042024-03-17+$0= $2,664,932
- Mod P000052025-03-27-$28,300= $2,636,632
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2022-03-24 | +$2,506,532 | $2,506,532 | BOILER BURNER REPLACEMENT PROJECT. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-16 | +$0 | $2,506,532 | BOILER BURNER REPLACEMENT PROJECT. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-07 | +$158,400 | $2,664,932 | BOILER BURNER REPLACEMENT PROJECT. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-07-05 | +$0 | $2,664,932 | BOILER BURNER REPLACEMENT PROJECT. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-03-17 | +$0 | $2,664,932 | BOILER BURNER REPLACEMENT PROJECT. |
| Mod P00005· CLOSE OUT | 2025-03-27 | −$28,300 | $2,636,632 | THE PURPOSE OF THIS MODIFICATION IS TO REMOVE EXCESS FUNDS AND TO CLOSE OUT THIS CONTRACT. ALL WORK HAS BEEN C… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI HUTXCHCVKL86)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26224P2352 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $175,000 | FY2024 |
| 36C26224P1518 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $64,854 | FY2024 |
| 36C26224P1286 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · N099 · INSTALLATION OF EQUIPMENT- MISCELLANEOUS | $20,293 | FY2024 |
| 36C26224P0439 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $88,542 | FY2024 |
| 36C26223P1472 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $98,828 | FY2023 |
| 36C26223P0732 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $145,252 | FY2023 |
Other recipients under J045 from 262-NETWORK CONTRACT OFFICE 22 (36C262) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26226P1512 | ANDREWS PLUMBING SERVICES INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $14,846 | FY2026 |
| 36C26226C0263 | J3 ENTERPRISE LLC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $68,679 | FY2026 |
| 36C26226P1398 | AKP TECHNOLOGY INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $60,958 | FY2026 |
| 36C26226P1261 | METERING SERVICES, INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $13,008 | FY2026 |
| 36C26226C0239 | STERILECO LLC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $193,900 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26222P0339_3600_-NONE-_-NONE- · retrieved 2026-09-26.