Award recordCONTRACT

CAPEX CONSTRUCTION LLC

PIID 36C26124C0042· VHA· 261-NETWORK CONTRACT OFFICE 21 (36C261)· Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS· FY2024· $12,859,324 net obligations· UEI VJWLNDEBBDM5· UT

Description

IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO

First action · last action
2023-12-15 · 2026-08-14
Transactions
11
First transaction's obligation
$12,004,375
Base + all options value (sum of deltas)
$12,859,324
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
2
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 11 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$12,859,324$0Base award · 2023-12-15 · this action $12,004,375 · running total $12,004,375Modification P00001 · 2024-08-08 · this action $85,173 · running total $12,089,548Modification P00002 · 2024-08-13 · this action $14,653 · running total $12,104,201Modification P00003 · 2025-02-04 · this action $48,751 · running total $12,152,952Modification P00004 · 2025-05-13 · this action $16,478 · running total $12,169,430Modification P00005 · 2025-07-31 · this action $414,961 · running total $12,584,391Modification P00006 · 2025-10-07 · this action -$10,801 · running total $12,573,590Modification P00007 · 2025-12-15 · this action $23,100 · running total $12,596,690Modification P00008 · 2026-02-04 · this action $7,861 · running total $12,604,551Modification P00009 · 2026-07-20 · this action $233,942 · running total $12,838,493Modification P00010 · 2026-08-14 · this action $20,831 · running total $12,859,324
  • Base2023-12-15+$12,004,375= $12,004,375
  • Mod P000012024-08-08+$85,173= $12,089,548
  • Mod P000022024-08-13+$14,653= $12,104,201
  • Mod P000032025-02-04+$48,751= $12,152,952
  • Mod P000042025-05-13+$16,478= $12,169,430
  • Mod P000052025-07-31+$414,961= $12,584,391
  • Mod P000062025-10-07-$10,801= $12,573,590
  • Mod P000072025-12-15+$23,100= $12,596,690
  • Mod P000082026-02-04+$7,861= $12,604,551
  • Mod P000092026-07-20+$233,942= $12,838,493
  • Mod P000102026-08-14+$20,831= $12,859,324
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2023-12-15+$12,004,375$12,004,375IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-08-08+$85,173$12,089,548IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-08-13+$14,653$12,104,201IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-02-04+$48,751$12,152,952IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-05-13+$16,478$12,169,430IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-07-31+$414,961$12,584,391IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-10-07−$10,801$12,573,590IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-12-15+$23,100$12,596,690IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO EMERGENCY SEWER CLEANOUT
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-02-04+$7,861$12,604,551IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-07-20+$233,942$12,838,493IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-08-14+$20,831$12,859,324IMPROVE SITE ACCESS AND PHYSICAL SECURITY DEFICIENCIES FOR VA FRESNO

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI VJWLNDEBBDM5)

AwardOffice · PSC / listingNet obligationsFY
36C26226C0157262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$2,107,859FY2026
36C26225C0229262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$5,050,372FY2025
36C26225P1307262-NETWORK CONTRACT OFFICE 22 (36C262) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$80,396FY2025
36C26225P0993262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$57,372FY2025
36C26225C0119262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$711,633FY2025
36C26125C0022261-NETWORK CONTRACT OFFICE 21 (36C261) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$3,997,554FY2025

Other recipients under Z1DZ from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C26126P0929ATLANTIC FIRST INDUSTRIES CORPORATION261-NETWORK CONTRACT OFFICE 21 (36C261)$76,243FY2026
36C26126P0824MILLENNIUM EASTERN GROUP LLC261-NETWORK CONTRACT OFFICE 21 (36C261)$105,374FY2026
36C26126F0195TITAN-AUXO, LLC261-NETWORK CONTRACT OFFICE 21 (36C261)$602,675FY2026
36C26126C0012PATRIOT CONSTRUCTION INC261-NETWORK CONTRACT OFFICE 21 (36C261)$752,500FY2026
36C26125N0707PATRIOT CONSTRUCTION INC261-NETWORK CONTRACT OFFICE 21 (36C261)$345,000FY2025

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26124C0042_3600_-NONE-_-NONE- · retrieved 2026-09-26.