Description
TERMINCATION FOR CONVENIENCE AND CLOSEOUT
Base award description: REPLACE AND RE-ROOF BUILDINGS 1D AND 10
Modification chain · 7 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-12-04+$3,804,000= $3,804,000
- Mod P000012024-04-09+$803,501= $4,607,501
- Mod P000022024-07-17+$0= $4,607,501
- Mod P000032024-12-23+$52,242= $4,659,743
- Mod P000042025-01-13+$0= $4,659,743
- Mod P000052025-03-20+$10,202= $4,669,945
- Mod P000062025-10-28-$2,611,099= $2,058,846
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-12-04 | +$3,804,000 | $3,804,000 | REPLACE AND RE-ROOF BUILDINGS 1D AND 10 |
| Mod P00001· FUNDING ONLY ACTION | 2024-04-09 | +$803,501 | $4,607,501 | MODIFICATION FOR ADDITIONAL FUNDING FOR MODIFICATION OF WORK HOURS. |
| Mod P00002· OTHER ADMINISTRATIVE ACTION | 2024-07-17 | +$0 | $4,607,501 | NO-COST MODIFICATION EXTENDING POP DUE TO ADDITIONAL TIME IN STAGING. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-12-23 | +$52,242 | $4,659,743 | REMOVAL OF SECOND TAR AND GRAVEL ROOF AND 30 DAY TIME EXTENSION. |
| Mod P00004· OTHER ADMINISTRATIVE ACTION | 2025-01-13 | +$0 | $4,659,743 | NO-COST POP MODIFICATION |
| Mod P00005· FUNDING ONLY ACTION | 2025-03-20 | +$10,202 | $4,669,945 | ADD WORK FOR DRAIN RETROFIT/EXTEND POP. |
| Mod P00006· TERMINATE FOR CONVENIENCE (COMPLETE OR PARTIAL) | 2025-10-28 | −$2,611,099 | $2,058,846 | TERMINCATION FOR CONVENIENCE AND CLOSEOUT |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI XNWZFJBMRR86)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26026C0051 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $468,437 | FY2026 |
| 36C26026C0039 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $46,531 | FY2026 |
| 36C26026C0030 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Z2NZ · REPAIR OR ALTERATION OF OTHER UTILITIES | $13,698,493 | FY2026 |
| 36C26026P0528 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $153,567 | FY2026 |
| 36C26026N0242 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $0 | FY2026 |
| 36C25926C0027 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2NE · REPAIR OR ALTERATION OF WATER SUPPLY FACILITIES | $3,120,383 | FY2026 |
Other recipients under Z1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126P1121 | SACRAMENTO COMPUTER POWER, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $217,673 | FY2026 |
| 36C26126C0064 | AMOROSO OVERWATCH LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $8,897,000 | FY2026 |
| 36C26126C0067 | V. LOPEZ JR. & SONS GENERAL ENGINEERING CONTRACTORS, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $2,404,795 | FY2026 |
| 36C26126C0066 | BEXAR-ADVANCED SOLUTIONS GROUP, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $3,214,131 | FY2026 |
| 36C26126C0063 | MOONLITE CONSTRUCTION | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $113,041 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26124C0030_3600_-NONE-_-NONE- · retrieved 2026-09-26.