Description
PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT INCORPORTE CHANGES CONSIDERED WITHIN SCOPE AND REMOVE SOME SCOPE DUE TO OBSOLESENCE OF EQUIPMENT.
Base award description: PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-04-12+$1,600,944= $1,600,944
- Mod P000012024-04-09+$0= $1,600,944
- Mod P000022024-08-22+$0= $1,600,944
- Mod P000032024-10-15+$19,995= $1,620,939
- Mod P000042024-11-05+$0= $1,620,939
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-04-12 | +$1,600,944 | $1,600,944 | PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-04-09 | +$0 | $1,600,944 | PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-22 | +$0 | $1,600,944 | PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT INCORPORTE CHANGES CONSIDERED WITHIN SCOPE AND REMOVE SO… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-10-15 | +$19,995 | $1,620,939 | PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT INCORPORTE CHANGES CONSIDERED WITHIN SCOPE AND REMOVE SO… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-05 | +$0 | $1,620,939 | PROJECT # 6400A-14-124 BUILDING 348 CATCH ALL PROJECT INCORPORTE CHANGES CONSIDERED WITHIN SCOPE AND REMOVE SO… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NM6KLD3BTZY9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26126C0058 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $7,984,201 | FY2026 |
| 36C26126C0052 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1AA · MAINTENANCE OF OFFICE BUILDINGS | $598,358 | FY2026 |
| 36C26126C0045 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS | $1,659,309 | FY2026 |
| 36C26126C0048 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $17,341,422 | FY2026 |
| 36C26126P0015 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · J069 · MAINT/REPAIR/REBUILD OF EQUIPMENT- TRAINING AIDS AND DEVICES | $49,963 | FY2026 |
| 36C26125C0056 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $251,456 | FY2025 |
Other recipients under Z1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126C0064 | AMOROSO OVERWATCH LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $8,897,000 | FY2026 |
| 36C26126P1121 | SACRAMENTO COMPUTER POWER, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $217,673 | FY2026 |
| 36C26126C0067 | V. LOPEZ JR. & SONS GENERAL ENGINEERING CONTRACTORS, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $2,404,795 | FY2026 |
| 36C26126C0066 | BEXAR-ADVANCED SOLUTIONS GROUP, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $3,214,131 | FY2026 |
| 36C26126C0063 | MOONLITE CONSTRUCTION | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $113,041 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26123C0024_3600_-NONE-_-NONE- · retrieved 2026-09-26.