REPLACE REFRIGERANT LINES PERIOD OF PERFORMANCE EXTENSION SUPPLY CHAIN DELAY ON TRANSFER SWITCH
Base award description: REPLACE REFRIGERANT LINES
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-05-31+$1,155,333= $1,155,333
- Mod P000012023-11-15+$0= $1,155,333
- Mod P000022024-05-09+$157,077= $1,312,410
- Mod P000032024-07-15+$0= $1,312,410
- Mod P000042024-10-03+$0= $1,312,410
- Mod P000052024-11-01+$4,322= $1,316,732
- Mod P000062025-01-24+$46,004= $1,362,736
- Mod P000072025-03-19+$0= $1,362,736
- Mod P000082025-04-25+$0= $1,362,736
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-05-31 | +$1,155,333 | $1,155,333 | REPLACE REFRIGERANT LINES |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-15 | +$0 | $1,155,333 | REPLACE REFRIGERANT LINES |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-09 | +$157,077 | $1,312,410 | REPLACE REFRIGERANT LINES ADDITIONAL STEEL AND LABOR TO RELOCATE EQUIPMENT DUE TO UNKNOWN SITE CONDITION. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-15 | +$0 | $1,312,410 | REPLACE REFRIGERANT LINES POP TIME EXTENSION |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-10-03 | +$0 | $1,312,410 | REPLACE REFRIGERANT LINES POP TIME EXTENSION |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-01 | +$4,322 | $1,316,732 | REPLACE REFRIGERANT LINES OUT OF SCOPE ADD FUELING AND MONITOR SERVICE FOR REFRIGERATION TRUCK |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-01-24 | +$46,004 | $1,362,736 | REPLACE REFRIGERANT LINES RE-ROUTE ELECTRICAL RUN AND PROVIDE REDUNDANT LINE AND TRANSFER SWITCH |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-03-19 | +$0 | $1,362,736 | REPLACE REFRIGERANT LINES PERIOD OF PERFORMANCE EXTENSION SUPPLY CHAIN DELAY ON TRANSFER SWITCH |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-04-25 | +$0 | $1,362,736 | REPLACE REFRIGERANT LINES PERIOD OF PERFORMANCE EXTENSION SUPPLY CHAIN DELAY ON TRANSFER SWITCH |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CJNYTL3J38Q5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26126C0057 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DB · MAINTENANCE OF LABORATORIES AND CLINICS | $103,652 | FY2026 |
| 36C26126P0632 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $114,503 | FY2026 |
| 36C26126C0016 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · N039 · INSTALLATION OF EQUIPMENT- MATERIALS HANDLING EQUIPMENT | $85,176 | FY2026 |
| 36C26125C0066 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $6,970,122 | FY2025 |
| 36C26124N0890 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $150,000 | FY2024 |
| 36C26124N0891 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · J049 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MAINTENANCE AND REPAIR SHOP EQUIPMENT | $14,025 | FY2024 |
Other recipients under Z1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126C0064 | AMOROSO OVERWATCH LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $8,897,000 | FY2026 |
| 36C26126P1121 | SACRAMENTO COMPUTER POWER, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $217,673 | FY2026 |
| 36C26126C0067 | V. LOPEZ JR. & SONS GENERAL ENGINEERING CONTRACTORS, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $2,404,795 | FY2026 |
| 36C26126C0066 | BEXAR-ADVANCED SOLUTIONS GROUP, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $3,214,131 | FY2026 |
| 36C26126C0063 | MOONLITE CONSTRUCTION | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $113,041 | FY2026 |