Description
THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE END OF CONTRACT DATE 302 CALENDAR DAYS TO 6-18-2027 AND INCORPORATE A NEW CLAUSE FAR 52.222-90 ((EO) 14398).
Base award description: VISN 21 WIDE DESIGN IDIQ - OPTION YEAR TWO DESIGN PRRC
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2020-03-12+$1,212,138= $1,212,138
- Mod P000012023-06-06+$123,109= $1,335,247
- Mod P000022025-02-26+$0= $1,335,247
- Mod P000032025-09-03+$33,142= $1,368,389
- Mod P000042026-07-28+$0= $1,368,389
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2020-03-12 | +$1,212,138 | $1,212,138 | VISN 21 WIDE DESIGN IDIQ - OPTION YEAR TWO DESIGN PRRC |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-06-06 | +$123,109 | $1,335,247 | REA DUE TO RE-DESIGN EFFORTS |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-02-26 | +$0 | $1,335,247 | NO COST TIME EXTENSION |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-03 | +$33,142 | $1,368,389 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REDESIGN EFFORT FOR COR#1-ROOF ACCESS STAIRS AND COR#2-ADD'… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-07-28 | +$0 | $1,368,389 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE END OF CONTRACT DATE 302 CALENDAR DAYS TO 6-18-2027 AND INCO… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JRH5B399U5W5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24826C0035 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · C1BG · ARCHITECT AND ENGINEERING- CONSTRUCTION: ELECTRONIC AND COMMUNICATIONS FACILITIES | $74,244 | FY2026 |
| 36C24826C0036 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $67,330 | FY2026 |
| 36C26326N0567 | NETWORK CONTRACT OFFICE 23 (36C263) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $229,620 | FY2026 |
| 36C24826N0590 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $308,060 | FY2026 |
| 36C26126N0437 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $383,084 | FY2026 |
| 36C24826N0534 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $185,024 | FY2026 |
Other recipients under C1DZ from PCAC (36C776) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C77626F0040 | VALI COOPER INTERNATIONAL LLC | PCAC (36C776) | $3,597,720 | FY2026 |
| 36C77626N0800 | DAV ENERGY SOLUTIONS, INC. | PCAC (36C776) | $3,409,209 | FY2026 |
| 36C77626N0688 | OEI-AECOM JOINT VENTURE | PCAC (36C776) | $7,499,808 | FY2026 |
| 36C77626F0033 | SIRIS LLC | PCAC (36C776) | $624,187 | FY2026 |
| 36C77626C0048 | OBRIEN ENGINEERING INC | PCAC (36C776) | $209,144 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26120N0474_3600_VA26117D0101_3600 · retrieved 2026-09-26.