MODIFICATION P00014 - POP EXTENSION FRESNO PHASE II CHILLER
Base award description: PHASE II CHILLER PROJECT FOR VA CENTRAL CALIFORNIA HEALTHCARE SYSTEM.
Modification chain · 16 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-09-28+$13,411,019= $13,411,019
- Mod P000012020-07-28-$10,815= $13,400,204
- Mod P000022020-09-21+$4,862= $13,405,066
- Mod P000032021-01-25+$165,560= $13,570,626
- Mod P000042021-04-23+$366,810= $13,937,436
- Mod P000052021-12-03+$0= $13,937,436
- Mod P000062022-01-14-$5,218= $13,932,218
- Mod P000072022-02-03+$79,848= $14,012,066
- Mod P000082022-06-13+$485,522= $14,497,588
- Mod P000092022-07-20+$65,025= $14,562,613
- Mod P000102023-01-20+$54,907= $14,617,520
- Mod P000112023-05-25+$293,575= $14,911,095
- Mod P000122023-08-08+$277,669= $15,188,764
- Mod P000132024-01-29+$25,484= $15,214,248
- Mod P000142024-04-22+$0= $15,214,248
- Mod P000152024-05-21+$0= $15,214,248
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-09-28 | +$13,411,019 | $13,411,019 | PHASE II CHILLER PROJECT FOR VA CENTRAL CALIFORNIA HEALTHCARE SYSTEM. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-07-28 | −$10,815 | $13,400,204 | ALTERNATE METHOD TO PERFORM ELECTRICAL CONNECTIONS WITHIN SCOPE OF THE ORIGINAL CONTRACT. |
| Mod P00002· FUNDING ONLY ACTION | 2020-09-21 | +$4,862 | $13,405,066 | ADDITIONAL FUNDING FOR CONTRACTOR ACCRUED EXPENSES DURING GOVERNMENT ISSUED COVID-19 SUSPENSION OF WORK. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-25 | +$165,560 | $13,570,626 | WITHIN SCOPE MODIFICATION TO ADDRESS EXCESSIVE UNDERGROUND CONFLICTS FOR WATER LINE RELATED STRUCTURE AT THE F… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-23 | +$366,810 | $13,937,436 | WITHIN SCOPE MODIFICATION TO PROVIDE EQUITABLE ADJUSTMENT AND EXTENDED PERFORMANCE DUE TO UNDERGROUND CONFLICT… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-03 | +$0 | $13,937,436 | EO14042 - COVID VACCINE MODIFICATION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-14 | −$5,218 | $13,932,218 | WITHIN SCOPE CHANGES TO CONTRACT FOR UNDERGROUND UTILITIES. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-03 | +$79,848 | $14,012,066 | WITHIN SCOPE EQUITABLE ADJUSTMENT TO CONTRACT FOR DIFFERING SITE CONDITIONS. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-13 | +$485,522 | $14,497,588 | ADDS SEWER LINE AND MEDIUM VOLTAGE ELECTRICAL RELOCATION DUE TO DIFFERING SITE CONDITIONS |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-07-20 | +$65,025 | $14,562,613 | EQUITABLE ADJUSTMENT DUE TO DIFFERING SITE CONDITIONS |
| Mod P00010· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2023-01-20 | +$54,907 | $14,617,520 | OUT-OF-SCOPE MODIFICATION ADDS SUB-BASEMENT SUMP PUMP, VALVES AND CERTIFIED MEDICAL TESTING |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-25 | +$293,575 | $14,911,095 | OUT-OF-SCOPE MODIFICATION ADDS CANOPY STRUCTURE BETWEEN B1 AND 24. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-08 | +$277,669 | $15,188,764 | MODIFICATION STORM DRAIN_MED GAS ALARM SYS |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-29 | +$25,484 | $15,214,248 | MODIFICATION P00013 - REA FOR ADDITIONAL WORK |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-04-22 | +$0 | $15,214,248 | MODIFICATION P00014 - POP EXTENSION FRESNO PHASE II CHILLER |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-21 | +$0 | $15,214,248 | MODIFICATION P00014 - POP EXTENSION FRESNO PHASE II CHILLER |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI K514LY25RBX5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26226P1377 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $287,635 | FY2026 |
| 36C26226C0276 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $617,282 | FY2026 |
| 36C26226C0232 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $2,274,650 | FY2026 |
| 36C26226N0531 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $12,732,577 | FY2026 |
| 36C26226P1081 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $24,987 | FY2026 |
| 36C26226P1078 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $24,987 | FY2026 |
Other recipients under Z2DZ from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126C0047 | HAWK CONTRACTING GROUP LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $5,082,745 | FY2026 |
| 36C26126C0045 | STRATEGIC INDUSTRY INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $1,659,309 | FY2026 |
| 36C26125N0756 | SERGENTS MECHANICAL SYSTEMS INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $525,000 | FY2025 |
| 36C26125N0751 | SERGENTS MECHANICAL SYSTEMS INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $498,980 | FY2025 |
| 36C26125C0057 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $48,000 | FY2025 |