Description
MODIFICATION P00013 - ADDS CASEWORK AND DESCOPES DISHWASHER UNITS
Base award description: IGF::OT::IGF CONSTRUCT PRRC BUILDING
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-06-04+$11,902,000= $11,902,000
- Mod P000012020-01-23+$28,197= $11,930,197
- Mod P000022020-06-23+$45,133= $11,975,330
- Mod P000032020-09-19+$82,834= $12,058,164
- Mod P000042020-12-07+$66,910= $12,125,074
- Mod P000052021-03-09+$40,667= $12,165,741
- Mod P000062021-04-20+$168,479= $12,334,220
- Mod P000072021-07-15+$39,712= $12,373,932
- Mod P000082021-08-09+$358,707= $12,732,639
- Mod P000092021-10-21+$36,378= $12,769,018
- Mod P000102021-11-23+$97,457= $12,866,475
- Mod P000112022-01-24+$60,876= $12,927,351
- Mod P000122022-02-25+$57,254= $12,984,605
- Mod P000132023-04-25-$0= $12,984,604
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-06-04 | +$11,902,000 | $11,902,000 | IGF::OT::IGF CONSTRUCT PRRC BUILDING |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-01-23 | +$28,197 | $11,930,197 | CONSTRUCT PRRC BUILDING VARIOUS CHANGES |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-23 | +$45,133 | $11,975,330 | CONSTRUCT PRRC BUILDING ELEVATOR CHANGES |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-19 | +$82,834 | $12,058,164 | CONSTRUCT PRRC BUILDING. MODIFICATION FOR COVID DELAY. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-07 | +$66,910 | $12,125,074 | ADDITIONAL WORK FOR ADDING SAFETY GUARDRAIL AND FRAMING STRUCTURAL SUPPORT |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-09 | +$40,667 | $12,165,741 | ADDITIONAL SERVICES FOR ELECTRICAL CORRECTION AND INSTALLATION OF ROOF GUTTER |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-20 | +$168,479 | $12,334,220 | ADDITIONAL SERVICES FOR ELECTRICAL CHANGES PART 2 |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-15 | +$39,712 | $12,373,932 | DESCOPES WALL MIRROR AND WHITE BOARDS ADDS ADDITIONAL SERVICE FOR CEILING FLASHING INSTALLATION, AND MODIFYING… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-09 | +$358,707 | $12,732,639 | ADDS PG&E GAS LINE UPGRADE, ELECTRICAL CHANGES, AND DISHWASHER MODEL CHANGES |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-21 | +$36,378 | $12,769,018 | MODIFICATION P00009 - ADDS CHANGES IN SIGNAGE DESIGN AND ADDITIONAL WORK FOR REQUIRED ELEVATOR PROVISIONS |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-23 | +$97,457 | $12,866,475 | MODIFICATION P00010 - ADDS CHANGES PER COR 20, 23, 31, 37, 38, 40, AND 41. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-24 | +$60,876 | $12,927,351 | MODIFICATION P00011 - ADDS CHANGES PER COR 42 AND 44 |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-25 | +$57,254 | $12,984,605 | MODIFICATION P00012 - INSTALL ELECTRIFIED HEADER AND TIME EXTENSION |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-25 | −$0 | $12,984,604 | MODIFICATION P00013 - ADDS CASEWORK AND DESCOPES DISHWASHER UNITS |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI Y4KHBT1J2H23)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26125N0642 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $579,182 | FY2025 |
| 36C26120N0688 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $2,000 | FY2020 |
| 36C26120D0085 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $0 | FY2020 |
Other recipients under Y1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26125C0066 | SENTINEL BUILDERS, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $6,970,122 | FY2025 |
| 36C26123N0397 | SENTINEL BUILDERS, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $138,958 | FY2023 |
| 36C26123N0391 | SENTINEL BUILDERS, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $0 | FY2023 |
| 36C26123N0319 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $3,005,818 | FY2023 |
| 36C26123N0140 | TALION CONSTRUCTION, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $279,081 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26119C0049_3600_-NONE-_-NONE- · retrieved 2026-09-26.