Award recordCONTRACT

BURTON CONSTRUCTION, INC.

PIID 36C26018N1259· VHA· 260-NETWORK CONTRACT OFFICE 20 (36C260)· Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES· FY2018· $21,588,983 net obligations· UEI NH7JETMN3L59· WA

Description

THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO COMPLETE WORK THAT IS WITHIN SCOPE FOR THE BOILER PLANT REPLACEMENT PROJECT 668-14-110 AT SPOKANE VAMC.

Base award description: NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT

First action · last action
2018-09-20 · 2024-02-09
Transactions
11
First transaction's obligation
$19,883,510
Base + all options value (sum of deltas)
$21,593,169
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
—
Offers received
1
SDVOSB flag on record
Yes (self-representation)
Parent IDV
36C26018D0007
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 11 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$21,592,581$0Base award · 2018-09-20 · this action $19,883,510 · running total $19,883,510Modification P00001 · 2019-09-03 · this action $130,363 · running total $20,013,873Modification P00002 · 2020-03-11 · this action $522,589 · running total $20,536,463Modification P00003 · 2020-06-17 · this action $503,629 · running total $21,040,092Modification P00004 · 2021-03-24 · this action $273,229 · running total $21,313,321Modification P00005 · 2022-04-22 · this action $115,487 · running total $21,428,809Modification P00006 · 2022-06-21 · this action $13,731 · running total $21,442,539Modification P00008 · 2023-01-31 · this action $0 · running total $21,442,539Modification P00007 · 2023-05-11 · this action $150,042 · running total $21,592,581Modification P00010 · 2023-06-26 · this action $0 · running total $21,592,581Modification P00011 · 2024-02-09 · this action -$3,598 · running total $21,588,983
  • Base2018-09-20+$19,883,510= $19,883,510
  • Mod P000012019-09-03+$130,363= $20,013,873
  • Mod P000022020-03-11+$522,589= $20,536,463
  • Mod P000032020-06-17+$503,629= $21,040,092
  • Mod P000042021-03-24+$273,229= $21,313,321
  • Mod P000052022-04-22+$115,487= $21,428,809
  • Mod P000062022-06-21+$13,731= $21,442,539
  • Mod P000082023-01-31+$0= $21,442,539
  • Mod P000072023-05-11+$150,042= $21,592,581
  • Mod P000102023-06-26+$0= $21,592,581
  • Mod P000112024-02-09-$3,598= $21,588,983
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2018-09-20+$19,883,510$19,883,510NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-09-03+$130,363$20,013,873NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-03-11+$522,589$20,536,463NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-06-17+$503,629$21,040,092NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-03-24+$273,229$21,313,321NRM PROJECT 668-14-110 BOILER PLANT REPLACEMENT
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-04-22+$115,487$21,428,809CREDIT TO THE GOVERNMENT: UNDERGROUND FUEL TANK WORK ADDED INCLUDES: STEAM CONDENSATE PIPE SIZE / ELEVATION B…
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-06-21+$13,731$21,442,539REPAIR LEAKING CONDENSATE PIPE IN VAULT 40 AT THE SPOKANE VA MEDICAL CENTER
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-01-31+$0$21,442,539MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE TO ACCOMMODATE THE UPDATED SCHEDULE FOR THE BOILER PLANT REPL…
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-05-11+$150,042$21,592,581THIS MODIFICATION IS TO REPLACE EMERGENCY GAS SHUTOFF, PROVIDE CO SENSORS, INSTALL 4 CABINET FOR CURRENT RELAY…
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-06-26+$0$21,592,581THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO COMPLETE WORK THAT IS WITHIN SCOPE FOR THE BOILER…
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-02-09−$3,598$21,588,983THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO COMPLETE WORK THAT IS WITHIN SCOPE FOR THE BOILER…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI NH7JETMN3L59)

AwardOffice · PSC / listingNet obligationsFY
36C26022N0289260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$99,875FY2022
36C26022P0364260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$76,391FY2022
36C26022N0217260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$242,287FY2022
36C26022N0167260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$293,718FY2022
36C26022N0110260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$593,126FY2022
36C26022N0097260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$225,671FY2022

Other recipients under Z2DA from 260-NETWORK CONTRACT OFFICE 20 (36C260) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C26026C0040SEABEE CONSTRUCTION, INC.260-NETWORK CONTRACT OFFICE 20 (36C260)$6,270,606FY2026
36C26026C0018SKYTEK LLC260-NETWORK CONTRACT OFFICE 20 (36C260)$6,711,663FY2026
36C26026C0013RJK CONSTRUCTION LLC260-NETWORK CONTRACT OFFICE 20 (36C260)$349,682FY2026
36C26025C0042SKYTEK LLC260-NETWORK CONTRACT OFFICE 20 (36C260)$11,899,896FY2025
36C26025P0371HUGHES GROUP LLC260-NETWORK CONTRACT OFFICE 20 (36C260)$9,928FY2025

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C26018N1259_3600_36C26018D0007_3600 · retrieved 2026-09-26.