Award recordCONTRACT

UTILITY SYSTEMS SOLUTIONS, INC.

PIID 36C25922C0034· VHA· NETWORK CONTRACT OFFICE 19 (36C259)· Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS· FY2022· $13,666,354 net obligations· UEI MEKRC9F8BZY7· TX

Description

JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR CLEANING AND SANITARY SEWER PUMPS.

Base award description: JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT

First action · last action
2022-05-10 · 2026-08-12
Transactions
10
First transaction's obligation
$12,725,257
Base + all options value (sum of deltas)
$13,666,354
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
3
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 10 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$13,666,354$0Base award · 2022-05-10 · this action $12,725,257 · running total $12,725,257Modification P00001 · 2023-02-07 · this action $189,953 · running total $12,915,210Modification P00002 · 2024-02-14 · this action $93,202 · running total $13,008,412Modification P00003 · 2024-08-30 · this action $0 · running total $13,008,412Modification P00004 · 2025-05-02 · this action $423,605 · running total $13,432,017Modification P00005 · 2025-07-23 · this action $0 · running total $13,432,017Modification P00006 · 2025-09-30 · this action $0 · running total $13,432,017Modification P00007 · 2025-12-11 · this action $0 · running total $13,432,017Modification P00008 · 2026-02-05 · this action $0 · running total $13,432,017Modification P00009 · 2026-08-12 · this action $234,337 · running total $13,666,354
  • Base2022-05-10+$12,725,257= $12,725,257
  • Mod P000012023-02-07+$189,953= $12,915,210
  • Mod P000022024-02-14+$93,202= $13,008,412
  • Mod P000032024-08-30+$0= $13,008,412
  • Mod P000042025-05-02+$423,605= $13,432,017
  • Mod P000052025-07-23+$0= $13,432,017
  • Mod P000062025-09-30+$0= $13,432,017
  • Mod P000072025-12-11+$0= $13,432,017
  • Mod P000082026-02-05+$0= $13,432,017
  • Mod P000092026-08-12+$234,337= $13,666,354
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2022-05-10+$12,725,257$12,725,257JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2023-02-07+$189,953$12,915,210JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT MODIFICATION 1
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-02-14+$93,202$13,008,412JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT ROOF REPAIR AND SHORING
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-08-30+$0$13,008,412JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-05-02+$423,605$13,432,017JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-07-23+$0$13,432,017JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-09-30+$0$13,432,017JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-12-11+$0$13,432,017JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-02-05+$0$13,432,017JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR DELIVERY AND INSTALLATION OF ELECTRICAL COMPONENTS
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-08-12+$234,337$13,666,354JACK C. MONTGOMERY VAMC REPLACE CHILLER PLANT EXTENSION FOR CLEANING AND SANITARY SEWER PUMPS.

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI MEKRC9F8BZY7)

AwardOffice · PSC / listingNet obligationsFY
36C25926N0420NETWORK CONTRACT OFFICE 19 (36C259) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT$11,500FY2026
36C26126C0046261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$900,657FY2026
36C77626P0027PCAC (36C776) · B543 · SPECIAL STUDIES/ANALYSIS- ENERGY$828,060FY2026
36C25926C0034NETWORK CONTRACT OFFICE 19 (36C259) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS$49,015FY2026
36C25626C0027256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1NZ · CONSTRUCTION OF OTHER UTILITIES$1,154,467FY2026
36C25925N0591NETWORK CONTRACT OFFICE 19 (36C259) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT$11,500FY2025

Other recipients under Z2DZ from NETWORK CONTRACT OFFICE 19 (36C259) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C25926C0068COPPER CREEK, LLCNETWORK CONTRACT OFFICE 19 (36C259)$440,420FY2026
36C25926C0049GDM-AE, INC.NETWORK CONTRACT OFFICE 19 (36C259)$87,500FY2026
36C25926N0177RHI LLCNETWORK CONTRACT OFFICE 19 (36C259)$301,136FY2026
36C25925P1096VETERANS PRE-CONSTRUCTION & VISUAL SOLUTIONS, LLCNETWORK CONTRACT OFFICE 19 (36C259)$50,105FY2025
36C25925C0098JACKSON MECHANICAL SERVICE INCNETWORK CONTRACT OFFICE 19 (36C259)$588,730FY2025