MODIFICATION P00009 IS TO EXTEND PERIOD OF PERFORMANCE 189 DAYS TO END 03/28/2025 TO ALLOW COMPLETION
Base award description: REQUIREMENT IS FOR CONSTRUCTION SERVICES TO CONVERT THE 8TH FLOOR NORTH OF BUILDING 126 IN THE LONG BEACH VA HEALTH CARE SYSTEM (VALBHCS) TO SINGLE PATIENT ROOMS.
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-08-16+$4,998,577= $4,998,577
- Mod P000012022-06-10+$73,943= $5,072,520
- Mod P000022022-08-01+$167,070= $5,239,590
- Mod P000032022-09-22+$92,451= $5,332,041
- Mod P000042022-12-12+$233,578= $5,565,619
- Mod P000052023-01-12+$232,512= $5,798,130
- Mod P000062023-08-07+$418,888= $6,217,018
- Mod P000072023-09-13+$37,284= $6,254,301
- Mod P000082024-06-14+$285,620= $6,539,921
- Mod P000092025-02-25+$0= $6,539,921
- Mod P000102025-08-13+$0= $6,539,921
- Mod P000112025-09-29+$54,864= $6,594,785
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-08-16 | +$4,998,577 | $4,998,577 | REQUIREMENT IS FOR CONSTRUCTION SERVICES TO CONVERT THE 8TH FLOOR NORTH OF BUILDING 126 IN THE LONG BEACH VA H… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-10 | +$73,943 | $5,072,520 | REQUIREMENT IS FOR CONSTRUCTION SERVICES TO CONVERT THE 8TH FLOOR NORTH OF BUILDING 126 IN THE LONG BEACH VA H… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-01 | +$167,070 | $5,239,590 | THIS MODIFICATION IS TO CHANGE THE RESILIENT FLOORING TO TERRAZZO FLOORING, ADD MULTI-PHASING AND 30 DAYS TO T… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-22 | +$92,451 | $5,332,041 | THIS MODIFICATION IS TO ACCOUNT FOR ADDITIONAL PLUMBING AND BARRIERS THAT WERE UNANTICIPATED. NO ADDITIONAL DA… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-12 | +$233,578 | $5,565,619 | THIS MODIFICATION IS TO ACCOUNT FOR THE 8 EXISTING DOORS WITH FRAMING REQUIRED TO BE REPLACED WITH NEW DOOR AN… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-12 | +$232,512 | $5,798,130 | MODIFICATION P00005 IS FOR EXTERIOR WINDOWS. NO ADDITIONAL TIME ADDED. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-07 | +$418,888 | $6,217,018 | MODIFICATION P00006 HAS MULTIPLE CHANGES AS DICTATED BY THE SOW |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-13 | +$37,284 | $6,254,301 | MODIFICATION P00007 IS TO ADD AN ADDITIONAL DATA PORT TO THE NEW NURSES STATIONS |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-14 | +$285,620 | $6,539,921 | MODIFICATION P00008 IS TO INSTALL FIRE DAMPERS AND ADD 294 DAYS TO THE PERIOD OF PERFORMANCE |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-02-25 | +$0 | $6,539,921 | MODIFICATION P00009 IS TO EXTEND PERIOD OF PERFORMANCE 189 DAYS TO END 03/28/2025 TO ALLOW COMPLETION |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-13 | +$0 | $6,539,921 | MODIFICATION P00009 IS TO EXTEND PERIOD OF PERFORMANCE 189 DAYS TO END 03/28/2025 TO ALLOW COMPLETION |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-29 | +$54,864 | $6,594,785 | MODIFICATION P00009 IS TO EXTEND PERIOD OF PERFORMANCE 189 DAYS TO END 03/28/2025 TO ALLOW COMPLETION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MKVHWMBN7NZ6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26126C0067 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,404,795 | FY2026 |
| 36C78626N0395 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $201,109 | FY2026 |
| 36C78626C0010 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $41,476 | FY2026 |
| 36C78626N0258 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $30,468 | FY2026 |
| 36C78626N0139 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $500 | FY2026 |
| 36C78626D0024 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $0 | FY2026 |
Other recipients under Z2DZ from 262-NETWORK CONTRACT OFFICE 22 (36C262) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26226N0745 | FEDVET CONSTRUCTION | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $6,491,230 | FY2026 |
| 36C26226P0870 | SOUTHWEST HAZARD CONTROL INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $139,597 | FY2026 |
| 36C26226N0266 | NELSON HCS, INC. | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $0 | FY2026 |
| 36C26225N0940 | JXR CONSTRUCTORS INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $3,900,000 | FY2025 |
| 36C26225N0974 | SYGNOS INC | 262-NETWORK CONTRACT OFFICE 22 (36C262) | $6,400,000 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25821C0076_3600_-NONE-_-NONE- · retrieved 2026-09-26.