Description
PROJECT 578-17-027: P0008: PROVIDE UNANTICIPATED ELECTRICAL REPAIRS AT VAULT 5 AND ASSOCIATED PIPES. MOD INVOLVES RECOVERY OF EXTRA COSTS DUE TO DOWNTIME AND NECESSARY OVERTIME TO MAINTAIN PROJECT SCHEDULE.
Base award description: PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE BETWEEN VAULT 9 AND PIT 5 AT THE HINES VA HOSPITAL.
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2023-09-26+$27,979,166= $27,979,166
- Mod P000012024-03-19+$176,997= $28,156,163
- Mod P000022024-04-12+$0= $28,156,163
- Mod P000032024-07-18+$2,617,462= $30,773,625
- Mod P000042024-08-19+$165,943= $30,939,567
- Mod P000052025-08-04+$1,721,498= $32,661,066
- Mod P000062025-09-22+$37,710= $32,698,776
- Mod P000072025-11-25+$857,058= $33,555,834
- Mod P000082026-04-22+$114,195= $33,670,029
- Mod P000092026-07-29+$493,785= $34,163,814
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2023-09-26 | +$27,979,166 | $27,979,166 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-03-19 | +$176,997 | $28,156,163 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-04-12 | +$0 | $28,156,163 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-18 | +$2,617,462 | $30,773,625 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-19 | +$165,943 | $30,939,567 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-04 | +$1,721,498 | $32,661,066 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-22 | +$37,710 | $32,698,776 | PROJECT 578-17-027: REPLACE EXISTING STEAM PIPE FROM VAULT 9 TO VAULT 7 STEAM TUNNEL AND REPLACE STEAM PIPE B… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-11-25 | +$857,058 | $33,555,834 | PROJECT 578-17-027: P0007: REROUTE STEAM LINE AROUND EXISTING ELLIPTICAL LINE |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-22 | +$114,195 | $33,670,029 | PROJECT 578-17-027: P0008: REVISE STRUCTURAL STEEL FOR PIPE SUPPORT. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-07-29 | +$493,785 | $34,163,814 | PROJECT 578-17-027: P0008: PROVIDE UNANTICIPATED ELECTRICAL REPAIRS AT VAULT 5 AND ASSOCIATED PIPES. MOD INVO… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI TJJ6HHAK46Z3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C77622C0068 | PCAC (36C776) · Y1EZ · CONSTRUCTION OF OTHER INDUSTRIAL BUILDINGS | $9,974,435 | FY2022 |
Other recipients under Z2NZ from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25225P1115 | VALLEY MECHANICAL INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $22,250 | FY2025 |
| 36C25225C0025 | DI MEO BROTHERS, INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $19,865 | FY2025 |
| 36C25224N0519 | BLUE YONDER INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $219,159 | FY2024 |
| VA69D17C0036 | MASTER DESIGN BUILD LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $392,500 | FY2017 |
| VA69D16C0283 | MASTERS BUILDING SOLUTIONS INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,439 | FY2016 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25223C0072_3600_-NONE-_-NONE- · retrieved 2026-09-25.