CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS MODIFICATION P00005 POP SUSPENSION LIFT
Base award description: CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-09-27+$728,884= $728,884
- Mod P000012022-02-24+$0= $728,884
- Mod P000022022-08-25+$0= $728,884
- Mod P000032023-01-11+$12,078= $740,962
- Mod P000042023-02-14+$0= $740,962
- Mod P000052023-04-05+$0= $740,962
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-09-27 | +$728,884 | $728,884 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-24 | +$0 | $728,884 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-25 | +$0 | $728,884 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS MODIFICATION P00002 NO COST TIME EXTENSION UNTIL DECEMBER 15,… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-11 | +$12,078 | $740,962 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS MODIFICATION P00003 |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-14 | +$0 | $740,962 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS MODIFICATION P00004 POP SUSPENSION |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-04-05 | +$0 | $740,962 | CON MATOC - PROJECT 550-21-119 REPLACE CHILLERS MODIFICATION P00005 POP SUSPENSION LIFT |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CD9SL37JKLK3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25226C0043 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $3,464,800 | FY2026 |
| 36C25226C0036 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $131,843 | FY2026 |
| 36C25226N0388 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $286,298 | FY2026 |
| 36S79726C0005 | NAC FACILITY PURCHASING SUPPORT (36S797) · Y1EZ · CONSTRUCTION OF OTHER INDUSTRIAL BUILDINGS | $1,826,855 | FY2026 |
| 36C25226C0006 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $3,353,007 | FY2026 |
| 36C25226C0003 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $1,505,527 | FY2026 |
Other recipients under Z1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0042 | JV6 CONTRACTING V2 LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,403,098 | FY2026 |
| 36C25226N0493 | PROGRESSIVE CONSTRUCTION SERVICES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $976,400 | FY2026 |
| 36C25226N0509 | RHI LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $111,799 | FY2026 |
| 36C25226P0501 | PRO FIRE AND WATER RESTORATION COMPANY | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $558,024 | FY2026 |
| 36C25226C0026 | JV6 CONTRACTING V2 LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,995,762 | FY2026 |