Description
537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER INCORPORATE RFP209.
Base award description: 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-03-26+$1,473,000= $1,473,000
- Mod P000012023-02-08+$389,103= $1,862,103
- Mod P000022023-05-19+$58,066= $1,920,169
- Mod P000032023-10-30+$24,498= $1,944,667
- Mod P000042023-11-30+$5,443= $1,950,110
- Mod P000052024-06-14+$215,715= $2,165,826
- Mod P000062024-08-20+$117,474= $2,283,300
- Mod P000072025-06-24+$103,280= $2,386,579
- Mod P000082025-07-31+$33,649= $2,420,228
- Mod P000092026-06-10+$137,844= $2,558,072
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-03-26 | +$1,473,000 | $1,473,000 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-08 | +$389,103 | $1,862,103 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-19 | +$58,066 | $1,920,169 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-10-30 | +$24,498 | $1,944,667 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-30 | +$5,443 | $1,950,110 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-14 | +$215,715 | $2,165,826 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-20 | +$117,474 | $2,283,300 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-06-24 | +$103,280 | $2,386,579 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-07-31 | +$33,649 | $2,420,228 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER INCORPORATE RFP209. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-06-10 | +$137,844 | $2,558,072 | 537-18-141 REPLACE FAILED AHU1 AND REMOTE CHILLER INCORPORATE RFP209. |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI J3DBYMSDPJ13)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25221C0122 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $2,542,313 | FY2021 |
Other recipients under Y1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25225C0027 | TL SERVICES, INC. | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $12,399 | FY2025 |
| 36C25225C0004 | VORTEX INDUSTRIES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $24,581 | FY2025 |
| 36C25222N0327 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $1,457,672 | FY2022 |
| 36C25222C0023 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,205,450 | FY2022 |
| 36C25222N0123 | RICHARD GROUP LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,726,328 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25221C0056_3600_-NONE-_-NONE- · retrieved 2026-09-26.