Description
MOD P00014, CREDIT TO ACCOUNT FOR FINAL TEST AND BALANCE/TRAINING THAT WAS NOT COMPLETED.
Base award description: MATERIAL MANAGEMENT BUILDING, 537-321
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-06-26+$3,996,000= $3,996,000
- Mod P000012020-02-19+$0= $3,996,000
- Mod P000022020-02-27+$0= $3,996,000
- Mod P000032020-06-21+$0= $3,996,000
- Mod P000042020-07-02+$0= $3,996,000
- Mod P000052020-07-07+$0= $3,996,000
- Mod P000062021-01-26+$0= $3,996,000
- Mod P000072021-03-24+$1,555= $3,997,555
- Mod P000082021-06-24+$55,535= $4,053,091
- Mod P000092021-07-30+$38,981= $4,092,071
- Mod P000102021-11-23+$0= $4,092,071
- Mod P000112022-01-12+$55,752= $4,147,823
- Mod P000122022-01-13+$83,728= $4,231,552
- Mod P000132022-01-24+$7,592= $4,239,144
- Mod P000142022-08-09-$4,220= $4,234,924
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-06-26 | +$3,996,000 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-02-19 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. SUSPENSION OF WORK |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-02-27 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. REMOVAL OF SUSPENSION OF WORK. RE-ESTABLISHES CONTRACT COMPLETION DAT… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-21 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. EXTEND POP TO JANUARY 25, 2021 |
| Mod P00004· CHANGE ORDER | 2020-07-02 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. PARTIAL SUSPENSION OF WORK DUE TO COLUMN INSTALLATION ACTIVITY. |
| Mod P00005· CHANGE ORDER | 2020-07-07 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. LIFT SUSPENSION OF WORK |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-26 | +$0 | $3,996,000 | MATERIAL MANAGEMENT BUILDING, 537-321. EXTEND PERIOD OF PERFORMANCE |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-24 | +$1,555 | $3,997,555 | MOD P00007 - MATERIAL MANAGEMENT BUILDING, 537-321. CITY OF CHICAGO PERMIT AND EXTEND PERIOD OF PERFORMANCE |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-24 | +$55,535 | $4,053,091 | MOD P00008 - 1. REVISED INTERIOR PHASING AND ARCHITECTURAL DRAWING AND 99 DAYS EXTEND PERIOD OF PERFORMANCE |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-30 | +$38,981 | $4,092,071 | MOD P00009 - 537-321 MATERIAL MANAGEMENT PROJECT MODIFICATION FOR SEWER LINE REPAIR THAT INCLUDES ASBESTOS PIP… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-23 | +$0 | $4,092,071 | EO14042 IMPLEMENT THE NEW COVID-19 PROTOCOLS IAW ACQUISITION FLASH 22-05 |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-12 | +$55,752 | $4,147,823 | MOD P00011, REQUEST FOR PROPOSAL FOR 03 ADDITIONAL TASK, ARCHITECTURAL ITEMS, DOORWAY 1504 A & B, AND FIRE ALA… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-13 | +$83,728 | $4,231,552 | MOD P00012, APPROVAL OF REQUEST FOR EQUITABLE ADJUSTMENT 002. THE CONTRACTOR SUBMITTED A REA FOR LABOR AND MAT… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-24 | +$7,592 | $4,239,144 | MOD P00013, APPROVAL OF REQUEST FOR EQUITABLE ADJUSTMENT 003. CAISSON SUBSURFACE OBSTRUCTION WORK THAT WAS COM… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-09 | −$4,220 | $4,234,924 | MOD P00014, CREDIT TO ACCOUNT FOR FINAL TEST AND BALANCE/TRAINING THAT WAS NOT COMPLETED. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI HUZQQ7RGZ6K8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26126P0016 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · H342 · INSPECTION- FIRE FIGHTING/RESCUE/SAFETY EQUIPMENT; ENVIRON PROTECT EQUIPMENT/MATLS | $140,064 | FY2026 |
| 36C26225P1236 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · H956 · OTHER QC/TEST/INSPECT- CONSTRUCTION AND BUILDING MATERIALS | $42,100 | FY2025 |
| 36C25025C0089 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $130,312 | FY2025 |
| 36C24725P0700 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · C213 · ARCHITECT AND ENGINEERING- GENERAL: INSPECTION (NON-CONSTRUCTION) | $27,400 | FY2025 |
| 36C24425N0601 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · R425 · SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL | $224,364 | FY2025 |
| 36C26025C0010 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $339,774 | FY2025 |
Other recipients under Y1DZ from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0043 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,464,800 | FY2026 |
| 36C25226C0006 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,353,007 | FY2026 |
| 36C25225C0056 | BLUE YONDER INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $0 | FY2025 |
| 36C25225C0052 | AMERITECH CONTRACTING LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $2,094,000 | FY2025 |
| 36C25225C0028 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $331,124 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25219C0158_3600_-NONE-_-NONE- · retrieved 2026-09-26.