Description
P00003 - PER CONSTRUCTION BULLETIN #04 MODIFY FINISHES FOR THE AHU-9 LOCKER ROOM AT THE OSCAR G. JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MICHIGAN
Base award description: REPLACE AIR HANDLING UNIT 9 AND UPGRADE FINISHES IN LOCKER ROOM, BREAK ROOM, AND DIRTY LINEN SPACE IN BASEMENT FOR THE OSCAR G. JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MICHIGAN
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-03-14+$863,815= $863,815
- Mod P000012019-07-31+$43,164= $906,979
- Mod P000022019-08-27+$22,573= $929,552
- Mod P000032019-09-19+$8,738= $938,290
- Mod P000042019-12-11+$5,087= $943,377
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-03-14 | +$863,815 | $863,815 | REPLACE AIR HANDLING UNIT 9 AND UPGRADE FINISHES IN LOCKER ROOM, BREAK ROOM, AND DIRTY LINEN SPACE IN BASEMENT… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-07-31 | +$43,164 | $906,979 | MODIFICATION P00001 - VARIOUS CHANGES PER CONSTRUCTION BULLETIN 001 FOR THE REPLACE AIR HANDLING UNIT 9 AND UP… |
| Mod P00002· CHANGE ORDER | 2019-08-27 | +$22,573 | $929,552 | P00002 - PER CONSTRUCTION BULLETIN #2; PLUMBING, ELECTRICAL CHANGES REPLACE AIR HANDLING UNIT 9 AND UPGRADE FI… |
| Mod P00003· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-09-19 | +$8,738 | $938,290 | P00003 - PER CONSTRUCTION BULLETIN #03; A/E ERRORS/OMISSIONS: A/E REFERENCED EXISTING HARDWARE TO BE RE-USED T… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-12-11 | +$5,087 | $943,377 | P00003 - PER CONSTRUCTION BULLETIN #04 MODIFY FINISHES FOR THE AHU-9 LOCKER ROOM AT THE OSCAR G. JOHNSON VA ME… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI Z2Y2LJ4Z4KM3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25226N0206 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $698,500 | FY2026 |
| 36C25224P1142 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2024 |
| 36C25224D0077 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2024 |
| 36C25224N0250 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $982,107 | FY2024 |
| 36C25224N0237 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $635,128 | FY2024 |
| 36C25224N0201 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $24,833 | FY2024 |
Other recipients under Z1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0042 | JV6 CONTRACTING V2 LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,403,098 | FY2026 |
| 36C25226N0493 | PROGRESSIVE CONSTRUCTION SERVICES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $976,400 | FY2026 |
| 36C25226N0509 | RHI LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $111,799 | FY2026 |
| 36C25226C0036 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $131,843 | FY2026 |
| 36C25226P0501 | PRO FIRE AND WATER RESTORATION COMPANY | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $558,024 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25219C0101_3600_-NONE-_-NONE- · retrieved 2026-09-26.