MODIFICATION P00022 - CONSTRUCTION BULLETIN 024 ITEM 2 GENERAL CONDITIONS- EXTENDED OVERHEAD COSTS ASSOCIATED WITH DELAYING START OF PHASE 2 WORK FROM 12/4/2020 TO 01/04/2021 FOR THE EXPAND COMMUNITY LIVING CENTER CONSTRUCTION PROJECT AT OSCAR G. JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MICHIGAN, 49801
Base award description: EXPAND COMMUNITY LIVING CENTER AT OSCAR G. JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MICHIGAN. THIS PROJECT IS FOR THE RENOVATION OF 3,500 SQUARE FEET OF EXISTING SPACE AND A 12,300 SQUARE FOOT ADDITION OF NEW SPACE.
Modification chain · 23 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-02-27+$10,834,025= $10,834,025
- Mod P000012019-05-15-$7,133= $10,826,892
- Mod P000022019-07-26-$666= $10,826,227
- Mod P000032019-08-23-$8,014= $10,818,213
- Mod P000042019-10-24+$32,243= $10,850,456
- Mod P000052019-12-02+$0= $10,850,456
- Mod P000062020-01-23+$23,527= $10,873,983
- Mod P000072020-02-19+$2,133= $10,876,116
- Mod P000082020-03-04+$7,421= $10,883,538
- Mod P000092020-04-01+$0= $10,883,538
- Mod P000102020-04-02+$0= $10,883,538
- Mod P000112020-04-08+$9,716= $10,893,253
- Mod P000122020-04-13+$26,120= $10,919,373
- Mod P000132020-04-28+$14,026= $10,933,399
- Mod P000142020-05-13+$1,221= $10,934,619
- Mod P000152020-06-17+$146,402= $11,081,022
- Mod P000162020-07-06+$13,982= $11,095,004
- Mod P000172020-08-12-$464= $11,094,540
- Mod P000182020-09-04+$27,253= $11,121,793
- Mod P000192020-09-29+$65,970= $11,187,763
- Mod P000202021-03-01+$2,237= $11,190,000
- Mod P000212021-04-19+$3,700= $11,193,700
- Mod P000222021-08-23+$39,728= $11,233,428
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-02-27 | +$10,834,025 | $10,834,025 | EXPAND COMMUNITY LIVING CENTER AT OSCAR G. JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MICHIGAN. THIS PROJECT IS… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-05-15 | −$7,133 | $10,826,892 | MODIFICATION P00001 - INCLUDE CONSTRUCTION BULLETINS CB 001 - DOOR HARDWARE CHANGE FOR PRIVACY LOCKS AND CB 00… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-07-26 | −$666 | $10,826,227 | MODIFICATION P00002 - INCLUDE CONSTRUCTION BULLETINS CB 003 - DEMO BY OWNER AND CB 004 - REVISED GRADING PLAN… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-08-23 | −$8,014 | $10,818,213 | MODIFICATION P000032 - INCLUDE CONSTRUCTION BULLETINS CB 005 - ELECTRICAL CHANGES FOR THE EXPAND COMMUNITY LIV… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-10-24 | +$32,243 | $10,850,456 | MODIFICATION P00004 - INCLUDE CONSTRUCTION BULLETINS CB 006&007 - NEW PUMPS AND DRIVE FOR BASEMENT HEAT EXCHAN… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-12-02 | +$0 | $10,850,456 | MODIFICATION P00005 - INCLUDE CONSTRUCTION BULLETINS CB 008 - INCREASE WIDTH OF UTILITY CHASE FOR THE EXPAND C… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-01-23 | +$23,527 | $10,873,983 | MODIFICATION P00006 - INCLUDE CONSTRUCTION BULLETINS CB 009&010 FOR THE EXPAND COMMUNITY LIVING CENTER CONSTRU… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-02-19 | +$2,133 | $10,876,116 | MODIFICATION P00007 - INCLUDE CONSTRUCTION BULLETIN CB 011 FOR THE EXPAND COMMUNITY LIVING CENTER CONSTRUCTION… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-03-04 | +$7,421 | $10,883,538 | MODIFICATION P00007 - INCLUDE CONSTRUCTION BULLETIN CB 012 FOR THE EXPAND COMMUNITY LIVING CENTER CONSTRUCTION… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-01 | +$0 | $10,883,538 | MODIFICATION P00009 - OFFSITE MATERIALS STORAGE PAYMENT AGREEMENT FOR FLOORING MATERIALS FOR THE EXPAND COMMUN… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-02 | +$0 | $10,883,538 | MODIFICATION P00010 - OFF-SITE STORED MATERIALS PAYMENT AGREEMENT FOR CASEWORK MATERIALS TO BE INSTALLED FOR T… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-08 | +$9,716 | $10,893,253 | MODIFICATION P00011 - INCLUDES CONSTRUCTION BULLETIN CB 013 FOR CHANGES THAT INVOLVE DINING COLUMNS, CONDENSAT… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-13 | +$26,120 | $10,919,373 | MODIFICATION P00012 - INCLUDE CONSTRUCTION BULLETIN CB 014 FOR THE EXPAND COMMUNITY LIVING CENTER CONSTRUCTION… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-28 | +$14,026 | $10,933,399 | MODIFICATION P00013 - INCLUDES CONSTRUCTION BULLETIN CB 015 FOR CHANGES THAT INVOLVE CEILING - ELECTRICAL ROOM… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-05-13 | +$1,221 | $10,934,619 | MODIFICATION P00014 - INCLUDES CONSTRUCTION BULLETIN CB 016 FOR CHANGES THAT INVOLVE TOUCHLESS DOOR ACTUATORS,… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-17 | +$146,402 | $11,081,022 | MODIFICATION P00015 - INCLUDES CONSTRUCTION BULLETINS CB 017, CB 08 FOR VARIOUS CHANGES AND A TIME EXTENSION F… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-07-06 | +$13,982 | $11,095,004 | MODIFICATION P00016 - INCLUDES CONSTRUCTION BULLETIN CB 019 FOR CHANGES THAT INVOLVE CHANGES TO PATIENT LIFT T… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-12 | −$464 | $11,094,540 | MODIFICATION P00017 - INCLUDES CONSTRUCTION BULLETIN CB 020 FOR CHANGES THAT INVOLVE 5 VARIOUS FINISHES CHANGE… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-04 | +$27,253 | $11,121,793 | MODIFICATION P00018 - INCLUDES CONSTRUCTION BULLETINS CB 021&022 FOR VARIOUS CHANGES FOR THE EXPAND COMMUNITY… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-29 | +$65,970 | $11,187,763 | MODIFICATION P00019 - INCLUDES CONSTRUCTION BULLETIN 023 FOR VARIOUS CHANGES FOR THE EXPAND COMMUNITY LIVING C… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-01 | +$2,237 | $11,190,000 | MODIFICATION P0002019 - INCLUDES CONSTRUCTION BULLETIN 024 ITEMS 1, 3,& 4 FOR VARIOUS CHANGES FOR THE EXPAND C… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-19 | +$3,700 | $11,193,700 | MODIFICATION P00021 - INCLUDES CONSTRUCTION BULLETIN 025 ITEM 1 FOR ENGINEERING ANALYSIS OF BLAST RATING FOR E… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-23 | +$39,728 | $11,233,428 | MODIFICATION P00022 - CONSTRUCTION BULLETIN 024 ITEM 2 GENERAL CONDITIONS- EXTENDED OVERHEAD COSTS ASSOCIATED… |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1DZ from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0043 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,464,800 | FY2026 |
| 36C25226C0006 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,353,007 | FY2026 |
| 36C25225C0056 | BLUE YONDER INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $0 | FY2025 |
| 36C25225C0052 | AMERITECH CONTRACTING LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $2,094,000 | FY2025 |
| 36C25225C0028 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $331,124 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C25219C0035_3600_-NONE-_-NONE- · retrieved 2026-09-26.