Description
ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 MODIFICATION P00003 - CHANGE ORDER #2 INVOLVING DEMOLITION OF A CONCRETE PAD AND THE ELIMINATION OF 3 UNDER SINK MIXING VALVES, AND CONTRACTING OFFICER'S REPRESENTATIVE HAS CHANGED FROM MICHAEL MCLAUGHLIN TO JENNIFER MILLER.
Base award description: ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-08-29+$710,000= $710,000
- Mod P000012019-03-22+$0= $710,000
- Mod P000022019-07-16+$0= $710,000
- Mod P000032019-08-08+$0= $710,000
- Mod P000042022-04-08-$389= $709,611
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-08-29 | +$710,000 | $710,000 | ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2019-03-22 | +$0 | $710,000 | ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 MODIFICATION P00001 - ADMINISTRATIVE MODIFICATION T… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-07-16 | +$0 | $710,000 | ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 MODIFICATION P00002 - SUPPLEMENTAL AGREEMENT TO EXT… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-08-08 | +$0 | $710,000 | ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 MODIFICATION P00003 - CHANGE ORDER #2 INVOLVING DEM… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-08 | −$389 | $709,611 | ADD DOMESTIC WATER PRESSURE BOOSTER PROJECT#: 757-19-203 MODIFICATION P00003 - CHANGE ORDER #2 INVOLVING DEM… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI FMEUJEE7X2S8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C77626N0166 | PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,000 | FY2026 |
| 36C77626D0027 | PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2026 |
| 36C25526C0054 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2NB · REPAIR OR ALTERATION OF HEATING AND COOLING PLANTS | $4,796,707 | FY2026 |
| 36C25526C0013 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $19,919,242 | FY2026 |
| 36C25626C0007 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $3,635,426 | FY2026 |
| 36C25626C0008 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $3,008,034 | FY2026 |
Other recipients under Z1DZ from 250-NETWORK CONTRACT OFFICE 10 (36C250) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25025C0073 | ALF III, INC. | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $8,000 | FY2025 |
| 36C25024C0171 | ED RIKE PLUMBING, INC. | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $66,111 | FY2024 |
| 36C25022N0644 | ARMCORP CONSTRUCTION INC | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $8,003 | FY2022 |
| 36C25022C0143 | ARMCORP CONSTRUCTION INC | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $45,500 | FY2022 |
| 36C25022P1033 | ARMCORP CONSTRUCTION INC | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $124,631 | FY2022 |