Description
P00007 - POP EXTENSION OF 30 CALENDAR-DAYS TO COMPLETE FINAL INSPECTION ITEMS.
Base award description: MATOC TVHS CONSTRUCTION
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-08-04+$897,966= $897,966
- Mod P000012021-11-15+$0= $897,966
- Mod P000022021-12-20+$0= $897,966
- Mod P000032022-02-23+$0= $897,966
- Mod P000042022-04-18+$0= $897,966
- Mod P000052022-05-23+$0= $897,966
- Mod P000062022-10-20+$18,027= $915,993
- Mod P000072022-11-22+$0= $915,993
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-08-04 | +$897,966 | $897,966 | MATOC TVHS CONSTRUCTION |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-15 | +$0 | $897,966 | AMENDMENT TO EXTEND PROJECT 30 CALENDAR DAYS. NEW COMPLETION DATE IS 12/20/2021. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-20 | +$0 | $897,966 | TIME EXTENSION THROUGH JANUARY 19, 2022, A TOTAL OF 30 CALENDAR DAYS DUE TO SUBCONTRACTOR DELAYS AND WEATHER. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-23 | +$0 | $897,966 | SUSPENSION FROM JANUARY 20, 2022 TO APRIL 20, 2022 A TOTAL OF 90 CALENDAR DAYS. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-18 | +$0 | $897,966 | EXTEND SUSPENSION FROM 04/20/2022 THROUGH 5/20/2022, A TOTAL OF 30 CALENDAR DAYS. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-23 | +$0 | $897,966 | LIFTED SUSPENSION AND INCREASED THE POP 56 CALENDAR-DAYS FROM 5/21/2022 THROUGH 7/16/2022. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-10-20 | +$18,027 | $915,993 | P00006 - POP EXTENSION AND CHANGE ADDING REMOVAL OF 2 DEAD TRESS AND FIX HANDICAP RAMP AND SIDEWALK. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-22 | +$0 | $915,993 | P00007 - POP EXTENSION OF 30 CALENDAR-DAYS TO COMPLETE FINAL INSPECTION ITEMS. |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI LPPTFNUEME13)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24926C0059 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,638,674 | FY2026 |
| 36C24726C0056 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $344,261 | FY2026 |
| 36C77626C0008 | PCAC (36C776) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $29,743,000 | FY2026 |
| 36C24925C0073 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $7,991,030 | FY2025 |
| 36C24925P0800 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J061 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC WIRE AND POWER DISTRIBUTION EQUIPMENT | $41,257 | FY2025 |
| 36C24925C0039 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $11,976,090 | FY2025 |
Other recipients under Z1LZ from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24926C0063 | TAYLOR CONSTRUCTION SERVICES, LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $134,927 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24921N0554_3600_36C24919D0064_3600 · retrieved 2026-09-26.