Description
MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI. MOD P00004 EXTEND THE POP DUE TO DELAY IN ARRIVAL OF FINAL PHILIP COILS.
Base award description: MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-07-28+$1,343,235= $1,343,235
- Mod P000012021-12-22+$0= $1,343,235
- Mod P000022022-02-23+$0= $1,343,235
- Mod P000032022-06-09+$25,993= $1,369,228
- Mod P000042022-11-09+$0= $1,369,228
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-07-28 | +$1,343,235 | $1,343,235 | MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-12-22 | +$0 | $1,343,235 | MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-23 | +$0 | $1,343,235 | MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-06-09 | +$25,993 | $1,369,228 | MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI. MOD P00003 ADD WITHIN SCOPE WORK NECESSIT… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-09 | +$0 | $1,369,228 | MATOC TVHS CONSTRUCTION - PROJECT 626-CSI-105, PREPARE SITE FOR MRI. MOD P00004 EXTEND THE POP DUE TO DELAY IN… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI X6N1HC5H7M74)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24926P0509 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $24,480 | FY2026 |
| 36C24926C0067 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS | $10,800 | FY2026 |
| 36C24926P0507 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2LZ · REPAIR OR ALTERATION OF PARKING FACILITIES | $18,144 | FY2026 |
| 36C24926P0499 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $69,231 | FY2026 |
| 36C24926P0442 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $19,613 | FY2026 |
| 36C24926P0472 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1LB · CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS | $15,480 | FY2026 |
Other recipients under Z1DA from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24926P0417 | DRI, INC. | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $2,961,475 | FY2026 |
| 36C24926P0352 | EWING/KESSLER INCORPORATED | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $269,355 | FY2026 |
| 36C24926P0371 | VALIANT CONSTRUCTION LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $110,770 | FY2026 |
| 36C24926P0319 | HUNTERSTONE DEVELOPMENT LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $10,000 | FY2026 |
| 36C24926P0200 | I-2-I SOLUTIONS, INC. | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $12,276 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24921N0548_3600_36C24919D0061_3600 · retrieved 2026-09-26.