Description
MODIFICATION TO ADD WORK WITHIN SCOPE - 50 LF GUTTER.
Base award description: USP 800 PHARMACY COMPLIANCE CONSTRUCTION PROJECT FOR THE ALVIN C. YORK VA MEDICAL CENTER IN MURFREESBORO, TN.
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-09-26+$2,872,401= $2,872,401
- Mod P000012020-06-02+$78,351= $2,950,752
- Mod P000022020-10-01+$27,151= $2,977,903
- Mod P000032020-12-16+$18,207= $2,996,110
- Mod P000042021-01-16+$0= $2,996,110
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-09-26 | +$2,872,401 | $2,872,401 | USP 800 PHARMACY COMPLIANCE CONSTRUCTION PROJECT FOR THE ALVIN C. YORK VA MEDICAL CENTER IN MURFREESBORO, TN. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-02 | +$78,351 | $2,950,752 | MODIFICATION TO ADD ADDITIONAL PIPE&INSULATION, METAL STAIRCASE, AND DOORS WORK WITHIN SCOPE FOR THE USP 800 P… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-10-01 | +$27,151 | $2,977,903 | MODIFICATION TO ADD DESIGN OMISSIONS. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-16 | +$18,207 | $2,996,110 | MODIFICATION TO ADD WORK WITHIN SCOPE - CHILL WATER CONTROL VALVES. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-16 | +$0 | $2,996,110 | MODIFICATION TO ADD WORK WITHIN SCOPE - 50 LF GUTTER. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI X6N1HC5H7M74)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24926P0509 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $24,480 | FY2026 |
| 36C24926C0067 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS | $10,800 | FY2026 |
| 36C24926P0507 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2LZ · REPAIR OR ALTERATION OF PARKING FACILITIES | $18,144 | FY2026 |
| 36C24926P0499 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $69,231 | FY2026 |
| 36C24926P0442 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $19,613 | FY2026 |
| 36C24926P0472 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1LB · CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS | $15,480 | FY2026 |
Other recipients under Y1DA from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24926P0438 | A TOTAL SOLUTION LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $234,720 | FY2026 |
| 36C24926C0047 | A TOTAL SOLUTION LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $19,870 | FY2026 |
| 36C24926C0005 | FIREWATCH CONTRACTING OF FLORIDA LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $6,109,411 | FY2026 |
| 36C24926C0007 | AEONRG LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $293,865 | FY2026 |
| 36C24925C0052 | APOGEE CONSULTING GROUP, P.A. | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $30,667 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24919C0212_3600_-NONE-_-NONE- · retrieved 2026-09-26.