Description
CHANGE TO COMPLETE THE LAST LEG OF THE MOUNTAIN HOME BYPASS FEEDER
Base award description: IGF::OT::IGF IMPLEMENTATION OF ELECTRICAL INFRASTRUCTURE UPGRADES
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2017-10-30+$1,808,328= $1,808,328
- Mod P000012018-01-25+$0= $1,808,328
- Mod P000022018-06-26+$8,118= $1,816,446
- Mod P000032018-08-08+$0= $1,816,446
- Mod P000042018-09-05+$0= $1,816,446
- Mod P000052018-09-20+$85,788= $1,902,234
- Mod P000062019-04-10+$0= $1,902,234
- Mod P000072019-06-13+$0= $1,902,234
- Mod P000082019-08-26+$112,376= $2,014,609
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2017-10-30 | +$1,808,328 | $1,808,328 | IGF::OT::IGF IMPLEMENTATION OF ELECTRICAL INFRASTRUCTURE UPGRADES |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2018-01-25 | +$0 | $1,808,328 | IGF::OT::IGF IMPLEMENTATION OF ELECTRICAL INFRASTRUCTURE UPGRADES |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-06-26 | +$8,118 | $1,816,446 | IGF::OT::IGF VAPOR BARRIER CHANGES AND EXCAVATION |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-08-08 | +$0 | $1,816,446 | IGF::OT::IGF EXTENDED FOR NEGOTIATION WITH CONTRACT COMPLETION DATE DUE TO DELAY IN SWITCH DELIVERY |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-09-05 | +$0 | $1,816,446 | IGF::OT::IGF EXTEND CONTRACT DUE TO VISTA SWITCH DELIVERY |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-09-20 | +$85,788 | $1,902,234 | IGF::OT::IGF BRIGHTRIDGE WORK FOR NECESSARY ELECTRICAL FAULT PROTECTION - EXTENDED CONTRACT UNTIL APRIL 12, 20… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-04-10 | +$0 | $1,902,234 | IGF::OT::IGF TIME EXTENSION DUE TO DIFFERING SITE CONDITION |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-13 | +$0 | $1,902,234 | IGF::OT::IGF TIME EXTENSION FOR DIFFERING SITE CONDITION |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-08-26 | +$112,376 | $2,014,609 | CHANGE TO COMPLETE THE LAST LEG OF THE MOUNTAIN HOME BYPASS FEEDER |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI F9MGMBN1KWW4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24626C0026 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $7,592,000 | FY2026 |
| 36C24625C0032 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $1,197,214 | FY2025 |
| 36C24625C0008 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $414,063 | FY2025 |
| 36C24624C0090 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · N045 · INSTALLATION OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $8,922,352 | FY2024 |
| 36C24924C0071 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS | $553,267 | FY2024 |
| 36C24923C0096 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $17,603 | FY2023 |
Other recipients under Z2DA from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24926C0059 | SEMPER TEK INC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $10,638,674 | FY2026 |
| 36C24926P0463 | JJ & J FACILITY MAINTENANCE LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $14,700 | FY2026 |
| 36C24926C0053 | STANDARD FEDERAL GROUP, LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $6,168,082 | FY2026 |
| 36C24926C0051 | TAYLOR CONSTRUCTION SERVICES, LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $247,604 | FY2026 |
| 36C24925P0898 | ESKOLA LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $12,379 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24918N0151_3600_VA24914D0012_3600 · retrieved 2026-09-26.