Description
UPGRADE CATH LAB - SUSPENSION OF WORK FROM FEBRUARY 11, 2019 THROUGH MARCH 4, 2019 DUE TO DELAY IN EQUIPMENT DUE TO FIRE AT PHILLIPS FACTORY.
Base award description: UPGRADE CATH LAP CONSTRUCTION PROJECT AT THE NASHVILLE VA MEDICAL CENTER.
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-04-17+$699,297= $699,297
- Mod P000012018-07-24+$0= $699,297
- Mod P000022018-08-21+$0= $699,297
- Mod P000032019-01-19+$0= $699,297
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-04-17 | +$699,297 | $699,297 | UPGRADE CATH LAP CONSTRUCTION PROJECT AT THE NASHVILLE VA MEDICAL CENTER. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-07-24 | +$0 | $699,297 | UPGRADE CATH LAB - SUSPENSION OF WORK FOR 30 CALENDAR DAYS ISSUES WITH EQUIPMENT FROM PHILLIPS |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-08-21 | +$0 | $699,297 | UPGRADE CATH LAB - SUSPENSION TO SEPTEMBER 4, 2018 DUE TO ISSUES WITH EQUIPMENT FROM PHILLIPS |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-01-19 | +$0 | $699,297 | UPGRADE CATH LAB - SUSPENSION OF WORK FROM FEBRUARY 11, 2019 THROUGH MARCH 4, 2019 DUE TO DELAY IN EQUIPMENT D… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI X6N1HC5H7M74)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24926P0509 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $24,480 | FY2026 |
| 36C24926C0067 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS | $10,800 | FY2026 |
| 36C24926P0507 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Z2LZ · REPAIR OR ALTERATION OF PARKING FACILITIES | $18,144 | FY2026 |
| 36C24926P0499 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $69,231 | FY2026 |
| 36C24926P0442 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $19,613 | FY2026 |
| 36C24926P0472 | 249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1LB · CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS | $15,480 | FY2026 |
Other recipients under Y1DA from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24926P0438 | A TOTAL SOLUTION LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $234,720 | FY2026 |
| 36C24926C0047 | A TOTAL SOLUTION LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $19,870 | FY2026 |
| 36C24926C0005 | FIREWATCH CONTRACTING OF FLORIDA LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $6,109,411 | FY2026 |
| 36C24926C0007 | AEONRG LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $293,865 | FY2026 |
| 36C24925C0052 | APOGEE CONSULTING GROUP, P.A. | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $30,667 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24918C0124_3600_-NONE-_-NONE- · retrieved 2026-09-26.