CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY OPTION YEAR 3.
Base award description: IGF::OT::IGF CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY.
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-03-02+$22,500= $22,500
- Mod P000012018-09-17+$0= $22,500
- Mod P000022018-10-01+$18,993= $41,493
- Mod P000032019-10-01+$43,500= $84,993
- Mod P000042020-10-01+$18,993= $103,986
- Mod P000052021-12-03-$4,748= $99,238
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-03-02 | +$22,500 | $22,500 | IGF::OT::IGF CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY. |
| Mod P00001· EXERCISE AN OPTION | 2018-09-17 | +$0 | $22,500 | IGF::OT::IGF CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY. |
| Mod P00002· EXERCISE AN OPTION | 2018-10-01 | +$18,993 | $41,493 | IGF::OT::IGF CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY. |
| Mod P00003· EXERCISE AN OPTION | 2019-10-01 | +$43,500 | $84,993 | CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY. |
| Mod P00004· EXERCISE AN OPTION | 2020-10-01 | +$18,993 | $103,986 | CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY OPTION YEAR 3. |
| Mod P00005· FUNDING ONLY ACTION | 2021-12-03 | −$4,748 | $99,238 | CONDENSING BOILER PREVENTIVE MAINTENANCE AT VAMC LEXINGTON, KY OPTION YEAR 3. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI Z1TBD9AK2EX1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26225P0205 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · H244 · EQUIPMENT AND MATERIALS TESTING- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $0 | FY2025 |
| 36C26324P1201 | NETWORK CONTRACT OFFICE 23 (36C263) · H345 · INSPECTION- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $18,600 | FY2024 |
| 36C26324P0431 | NETWORK CONTRACT OFFICE 23 (36C263) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $74,588 | FY2024 |
| 36C26320P0440 | NETWORK CONTRACT OFFICE 23 (36C263) · H344 · INSPECTION- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $25,990 | FY2020 |
| 36C26319C0144 | NETWORK CONTRACT OFFICE 23 (36C263) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $38,670 | FY2019 |
| 36C26319C0118 | NETWORK CONTRACT OFFICE 23 (36C263) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $128,155 | FY2019 |
Other recipients under J043 from 249-NETWORK CONTRACT OFFICE 9 (36C249) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24923P0590 | DUNBAR MECHANICAL CONTRACTORS, LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $69,305 | FY2023 |
| 36C24923C0010 | DUNBAR MECHANICAL CONTRACTORS, LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $326,400 | FY2023 |
| 36C24922P0015 | CALDAIA CONTROLS LLC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $176,914 | FY2022 |
| 36C24920P0580 | POWER EQUIPMENT CO. OF MEMPHIS | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $3,525 | FY2020 |
| 36C24920P0235 | A2A INTEGRATED LOGISTICS INC | 249-NETWORK CONTRACT OFFICE 9 (36C249) | $35,961 | FY2020 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24918C0076_3600_-NONE-_-NONE- · retrieved 2026-09-26.