Description
PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON TUSKEGEE VETERAN MEDICAL CENTER
Modification chain · 16 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-01-27+$1,594,681= $1,594,681
- Mod P000012021-11-29+$0= $1,594,681
- Mod P000022022-01-12+$0= $1,594,681
- Mod P000032022-06-27+$0= $1,594,681
- Mod P000042022-10-03+$0= $1,594,681
- Mod P000052022-12-22+$0= $1,594,681
- Mod P000062023-03-14+$0= $1,594,681
- Mod P000072023-04-05+$0= $1,594,681
- Mod P000082023-05-18+$0= $1,594,681
- Mod P000092023-10-03+$0= $1,594,681
- Mod P000102023-11-21+$0= $1,594,681
- Mod P000112024-01-25+$42,841= $1,637,522
- Mod P000122024-03-26+$0= $1,637,522
- Mod P000132024-05-21+$0= $1,637,522
- Mod P000142024-06-21+$0= $1,637,522
- Mod P000152024-08-15+$31,718= $1,669,240
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-01-27 | +$1,594,681 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2021-11-29 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00002· OTHER ADMINISTRATIVE ACTION | 2022-01-12 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00003· OTHER ADMINISTRATIVE ACTION | 2022-06-27 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00004· OTHER ADMINISTRATIVE ACTION | 2022-10-03 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00005· OTHER ADMINISTRATIVE ACTION | 2022-12-22 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00006· OTHER ADMINISTRATIVE ACTION | 2023-03-14 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00007· OTHER ADMINISTRATIVE ACTION | 2023-04-05 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2023-05-18 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00009· OTHER ADMINISTRATIVE ACTION | 2023-10-03 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00010· OTHER ADMINISTRATIVE ACTION | 2023-11-21 | +$0 | $1,594,681 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-25 | +$42,841 | $1,637,522 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00012· OTHER ADMINISTRATIVE ACTION | 2024-03-26 | +$0 | $1,637,522 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00013· OTHER ADMINISTRATIVE ACTION | 2024-05-21 | +$0 | $1,637,522 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00014· OTHER ADMINISTRATIVE ACTION | 2024-06-21 | +$0 | $1,637,522 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-15 | +$31,718 | $1,669,240 | PROJECT # 619A4-19-101 - CORRECT CRITICAL ELECTRICAL PLUMBING AND ARCHITECTURE DEFICIENCIES IN BUILDING 129 ON… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZN18CLHUHKK4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24726C0077 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $8,568,011 | FY2026 |
| 36C24726C0068 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $4,503,785 | FY2026 |
| 36C77625C0133 | PCAC (36C776) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $15,556,415 | FY2025 |
| 36C24725C0111 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $11,495,391 | FY2025 |
| 36C24725C0099 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $17,526,679 | FY2025 |
| 36C25624C0092 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $4,457,049 | FY2024 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24721N0104_3600_36C24718D0133_3600 · retrieved 2026-09-26.