EO 14398 AND AE DESIGN SUBMISSION SCHEDULE REVISION
Base award description: PROJECT INVOLVES THE ARCHITECTURAL AND ENGINEERING (A/E) DESIGN SERVICES FOR THE REPLACEMENT OF THREE EXISTING STEAM BOILERS, CONTROLS AND CONTROL ROOM IN BUILDING 501. GOAL IS TO MODERNIZE THE INFRASTRUCTURE FOR UTILITY PLANT IN BUILDING 501.
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2024-08-14+$2,946,913= $2,946,913
- Mod P000012025-05-09+$0= $2,946,913
- Mod P000022025-08-07+$0= $2,946,913
- Mod P000032026-05-21+$0= $2,946,913
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2024-08-14 | +$2,946,913 | $2,946,913 | PROJECT INVOLVES THE ARCHITECTURAL AND ENGINEERING (A/E) DESIGN SERVICES FOR THE REPLACEMENT OF THREE EXISTING… |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2025-05-09 | +$0 | $2,946,913 | MODERNIZE BOILER PLANT PROJECT ADMIN MOD DUE TO PRESIDENTIAL EOS. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-07 | +$0 | $2,946,913 | MODERNIZE BOILER PLANT PROJECT NO COST DESIGN SCHEDULE REVISION AND ACO REASSIGN. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-05-21 | +$0 | $2,946,913 | EO 14398 AND AE DESIGN SUBMISSION SCHEDULE REVISION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI UZMNKG2APNV2)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25026C0170 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $339,644 | FY2026 |
| 36C24426N0791 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $840,414 | FY2026 |
| 36C24726C0038 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $297,548 | FY2026 |
| 36C24426N0509 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · C221 · ARCHITECT AND ENGINEERING- GENERAL: PLUMBING SYSTEMS | $523,222 | FY2026 |
| 36C24126F0091 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $492,344 | FY2026 |
| 36C24126N0472 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · C1NZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER UTILITIES | $1,347,690 | FY2026 |
Other recipients under C1DZ from 246-NETWORK CONTRACTING OFFICE 6 (36C246) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24626N0896 | TOLAND MIZELL MOLNAR LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $164,429 | FY2026 |
| 36C24626C0042 | AWEN SOLUTIONS GROUP, LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $218,185 | FY2026 |
| 36C24625C0062 | GUIDON-CHARLOTTE ENGINEERS SDVOSB JV II LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $367,311 | FY2025 |
| 36C24624C0066 | LOGOSAKF LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $430,463 | FY2024 |
| 36C24624C0042 | VALHALLA ENGINEERING GROUP, LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $560,668 | FY2024 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24624C0070_3600_-NONE-_-NONE- · retrieved 2026-09-26.