Description
INSTALL APPROXIMATELY 190' OF PRIMED 1 1/4" STEEL DOUBLE RAIL GUARDRAIL WITH GRAB BAR ALONG BOTH SIDES OF NEW SIDEWALK AT THE ENTRANCE. POSTS FOR RAILING WILL BE INSTALLED 18" DEEP WITH CONCRETE. ALL RAILING WILL HAVE 2 COATS OF PRIMER BEFORE INSTALLATION AND EXPOSED RAILING WILL BE PAINTED WITH SHERWIN WILLIAMS DARK BRONZE.
Base award description: IGF::OT::IGF RELOCATE AND EXPAND RENAL DIAYLSIS
Modification chain · 13 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-12-17+$9,293,800= $9,293,800
- Mod P000012019-05-29+$0= $9,293,800
- Mod P000022019-06-14+$0= $9,293,800
- Mod P000032019-06-18+$88,192= $9,381,992
- Mod P000042019-11-22+$29,658= $9,411,650
- Mod P000052020-04-06+$210,855= $9,622,505
- Mod P000062020-10-29+$40,303= $9,662,808
- Mod P000072020-12-08+$75,131= $9,737,939
- Mod P000082021-01-06+$53,726= $9,791,665
- Mod P000092021-03-11+$39,689= $9,831,354
- Mod P000102021-08-05+$43,207= $9,874,561
- Mod P000112021-09-14+$39,256= $9,913,817
- Mod P000122021-09-17+$4,458= $9,918,275
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-12-17 | +$9,293,800 | $9,293,800 | IGF::OT::IGF RELOCATE AND EXPAND RENAL DIAYLSIS |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2019-05-29 | +$0 | $9,293,800 | IGF::OT::IGF RELOCATE AND EXPAND RENAL DIAYLSIS |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-14 | +$0 | $9,293,800 | IGF::OT::IGF RELOCATE AND EXPAND RENAL DIAYLSIS |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-18 | +$88,192 | $9,381,992 | RELOCATE AND EXPAND RENAL DIAYLSIS MODIFICATION |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-11-22 | +$29,658 | $9,411,650 | RELOCATE AND EXPAND RENAL DIAYLSIS MODIFICATION |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-06 | +$210,855 | $9,622,505 | RELOCATE AND EXPAND RENAL DIAYLSIS MODIFICATION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-10-29 | +$40,303 | $9,662,808 | HEADWALL, SANITARY SEWER, WATER HEATER. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-08 | +$75,131 | $9,737,939 | RENAL PATIENT LIFT CURTAIN SYSTEM |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-06 | +$53,726 | $9,791,665 | RENAL PATIENT FIRE SUPPRESSION WATER SERVICE LINE |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-11 | +$39,689 | $9,831,354 | 1) CHANGE SWING OF DOORS ON ELECTRICAL ROOMS B75 & B74 & HALLWAY CB 9.1 PER RFI 53. 2) ADD DOOR FOR LOCKER ROO… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-05 | +$43,207 | $9,874,561 | 1) CHANGE SWING OF DOORS ON ELECTRICAL ROOMS B75 & B74 & HALLWAY CB 9.1 PER RFI 53. 2) ADD DOOR FOR LOCKER ROO… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-14 | +$39,256 | $9,913,817 | INSTALL APPROXIMATELY 190' OF PRIMED 1 1/4" STEEL DOUBLE RAIL GUARDRAIL WITH GRAB BAR ALONG BOTH SIDES OF NEW… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-17 | +$4,458 | $9,918,275 | INSTALL APPROXIMATELY 190' OF PRIMED 1 1/4" STEEL DOUBLE RAIL GUARDRAIL WITH GRAB BAR ALONG BOTH SIDES OF NEW… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI C9AFMLP98K27)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24624C0033 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · N063 · INSTALLATION OF EQUIPMENT- ALARM, SIGNAL, AND SECURITY DETECTION SYSTEMS | $888,243 | FY2024 |
| 36C24624P0474 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $68,800 | FY2024 |
| 36C24623C0106 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $3,750 | FY2023 |
| 36C24623C0086 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $10,008,452 | FY2023 |
| 36C24623P1090 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $88,418 | FY2023 |
| 36C24623C0027 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $3,002,879 | FY2023 |
Other recipients under Y1DA from 246-NETWORK CONTRACTING OFFICE 6 (36C246) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24626C0060 | GUARDIAN ENVIRONMENTAL SERVICES CO INC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $2,364,539 | FY2026 |
| 36C24626C0047 | TERALINKS LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $232,275 | FY2026 |
| 36C24626C0055 | GROUP III MANAGEMENT INC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $17,474,199 | FY2026 |
| 36C24626F0148 | TRAUNER CONSULTING SERVICES, INC. | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $72,266 | FY2026 |
| 36C24625C0064 | BRYMAK FSI JV, LLC | 246-NETWORK CONTRACTING OFFICE 6 (36C246) | $7,623,654 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C24619C0008_3600_-NONE-_-NONE- · retrieved 2026-09-26.